Mr. Aidan O'Connor:

It was the fault of the contractor and also the fault of those who were overseeing his activities. The errors, mistakes, oversights or whatever were due to the way Priory Hall was built. The omission of the fire-stopping insulation within the cavity walls is the issue that really brought everything into focus.