Written answers

Tuesday, 30 May 2023

Department of Education and Skills

School Accommodation

Photo of Duncan SmithDuncan Smith (Dublin Fingal, Labour)
Link to this: Individually | In context | Oireachtas source

310. To ask the Minister for Education and Skills the up-to-date position with the provision of an extension to a primary school (details supplied) in County Kildare; and if she will make a statement on the matter. [26260/23]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The large scale capital project referred to by the Deputy is at Architectural Planning Stage 4 - Construction. The project commenced on site in March 2022. Works are progressing satisfactorily with a contract completion date of Q4 2024.

Photo of Duncan SmithDuncan Smith (Dublin Fingal, Labour)
Link to this: Individually | In context | Oireachtas source

311. To ask the Minister for Education and Skills the up-to-date position with the provision of an extension to a primary school (details supplied) in County Kildare; and if she will make a statement on the matter. [26261/23]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The large scale capital project referred to by the Deputy is at Architectural Planning Stage 4 - Construction. Works commenced on site in October 2021 with an estimated completion date of Q1 2024.

Photo of Duncan SmithDuncan Smith (Dublin Fingal, Labour)
Link to this: Individually | In context | Oireachtas source

312. To ask the Minister for Education and Skills the up-to-date position with the extension of secondary school (details supplied) in County Kildare; and if she will make a statement on the matter. [26262/23]

Photo of Norma FoleyNorma Foley (Kerry, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The project to which the Deputy refers has been devolved for delivery to the National Development Finance Agency (NDFA) as part of a programme of school building projects. This school is in the bundle referred to as ‘Project Boyne’.

The Planning Application for this project has been lodged with Kildare County Council and the final grant of planning is anticipated in Q2 2023. The project will then proceed to tender and construction in due course.

At this stage it is not possible to provide an accurate timeline for completion of the project; the NDFA will be engaging directly with the school authority to keep it informed of progress.