Written answers
Thursday, 27 November 2025
Department of Education and Skills
Schools Building Projects
Malcolm Byrne (Wicklow-Wexford, Fianna Fail)
Link to this: Individually | In context
302. To ask the Minister for Education and Skills the total number of school building projects at each stage, and at primary and at secondary level, being managed by her Department; and if she will make a statement on the matter. [66903/25]
Hildegarde Naughton (Galway West, Fine Gael)
Link to this: Individually | In context
Since 2020, my department has invested over €6 billion in our schools throughout the country under the National Development Plan, involving the completion of over 1,300 school building projects. In addition, repurposing and optimisation of existing accommodation capacity across the school estate has been a key enabler of timely, local provision of special class capacity in a way that supports best practice in inclusion and integration. Circa 80% of new special classes in 2025/26 are being facilitated in repurposed classroom accommodation.
Government support for this investment, including by way of supplementary capital funding, has delivered real benefits for school communities. Supplementary capital funding of €210 million approved by Government has brought the total capital allocation for 2025 for my department to €1.6 billion.
In July the Government announced a capital allocation of €7.55 billion for the Department of Education and Youth for the period 2026-2030 under the National Development Plan. As part of this NDP allocation my department will place a strong emphasis on provision for children with special educational needs, with a particular focus on meeting annual school place needs. In relation to project roll-out for Large-Scale projects and Additional School Accommodation scheme projects, the approach will be to continue to maximise the capacity of the existing school estate as much as possible in the first instance and provide necessary additional capacity through targeted and prioritised project roll-out over the course of 2026 to 2030 period to meet the most urgent and prioritised needs. It is planned that circa 80 school building projects will progress to construction across 2026 and 2027 as part of a 2-year rolling programme.
All Government departments are expected to publish their sectoral NDP Implementation Plans shortly. My department’s plan will optimise outputs from the NDP allocations, with a strong focus on maximising existing school capacity, progressing priority projects where local capacity across schools in the area is insufficient, and ensuring delivery that is affordable, offers value for money, and meets functional needs.
The current status of all projects is set out under item number ten at the following link . This is updated on a regular basis to reflect project progress through the various stages of capital appraisal, site acquisition, design, tender and construction. Currently there are over 1400 school buildings projects at various stages which comprises of over 480 Post Primary Schools, over 950 Primary Schools.
No comments