252. To ask the Minister for Transport, Tourism and Sport the timeframe for the detailed project brief and procurement strategy for consideration at approval gate 2 for Metro North; and if he will make a statement on the matter. [66273/25]

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal East, Fianna Fail)
Link to this: Individually | In context

As Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. The National Transport Authority (NTA) has the statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area (GDA), which includes MetroLink.

A significant milestone in the progression of the MetroLink project was cleared in July 2022, when the Minister for Transport secured approval for the project from the Cabinet under Decision Gate 1 of the then-Public Spending Code. This approval enabled the project to move to the planning application stage, and in September 2022 Transport Infrastructure Ireland (TII) submitted a Railway Order application to An Coimisiún Pleanála. An Coimisiún Pleanála published its decision to grant the MetroLink Railway Order on 30 September 2025.

A Detailed Project Brief and Procurement Strategy will be prepared for consideration at Approval Gate 2, in line with the Infrastructure Guidelines.

Noting the NTA's responsibility in the matter, I have referred the Deputy's question to the NTA for a direct reply. Please contact my private office if you do not receive a reply within 10 days.