Written answers

Tuesday, 27 July 2021

Photo of Catherine MurphyCatherine Murphy (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

2012. To ask the Minister for Health the date to which the moratorium regarding claims made by a company (details supplied) has been extended to in respect of National Paediatric Hospital Development Board in view of the fact it was due to cease at the end of June 2021 in relation to court actions being taken. [36180/21]

Photo of Stephen DonnellyStephen Donnelly (Wicklow, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

As the National Paediatric Hospital Development Board (NPHDB) has statutory responsibility for planning, designing, building, and equipping the new children's hospital. This includes assessment and defence of claims submitted by the contractor under the construction contract. I have therefore referred your question to the NPHDB for direct reply. 

Photo of Catherine MurphyCatherine Murphy (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

2013. To ask the Minister for Health the status of the independent employer representative that is engaged to adjudicate on the dispute between the National Paediatric Hospital Development Board and a company (details supplied); the number of claims adjudicated on; the value of those claims; the eventual settlement that has been agreed; the number of outstanding claims; and the value of same. [36181/21]

Photo of Stephen DonnellyStephen Donnelly (Wicklow, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I am aware that the main contractor has submitted a significant number of claims to the National Paediatric Hospital Development Board (NPHDB), which it alleges are outside the agreed scope of the construction contract. It is entitled to do so. However, the NPHDB has a revised and strengthened process in place for the assessment of claims by the contractor in accordance with the construction contract. It is robustly defending all claims where, in the opinion of the Board and its advisors, there is no contractual entitlement. This is vital to mitigating the risk of escalating costs and delays on this project.

Last month, as part of the NPHDB’s ongoing engagement with BAM, both parties agreed to a period of moratorium on claims. This will allow both parties to dedicate all their energies towards delivering the project as quickly as possible.

As the National Paediatric Hospital Development Board (NPHDB) has statutory responsibility for planning, designing, building and equipping the new children's hospital. I have referred your question to the NPHDB for direct reply.