Written answers

Tuesday, 3 November 2020

Department of Public Expenditure and Reform

Garda Stations

Photo of Violet-Anne WynneViolet-Anne Wynne (Clare, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

484. To ask the Minister for Public Expenditure and Reform the Garda stations within the Clare division that were refurbished by the OPW over the past 18 months; the nature of works that were carried out at each station during this period; and if he will indicate if works are still ongoing or completed, by station. [33856/20]

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I can confirm that the Office of Public Works has carried out refurbishment works to 15 Garda Stations in the Clare Division between May 2019 and October 2020. Details of these works are given the following table and include works funded by both the Office of Public Works and An Garda Síochána.

Station Description of Works Status
Ballyvaughan GS External Painting Complete
Corrofin GS Kitchen Upgrade Complete
Crusheen GS Full Station Upgrade Complete
Ennis GS Structural Works to Boundary Walls; Realignment of carparking spaces in rear carpark Ongoing
Ennistymon GS Kitchen Replacement; Removal of Security Railing; Realignment of carparking spaces Ongoing
Kildysart GS Exterior painting , Power washing of driveway Complete
Kilkee GS Public Office Upgrade; New Kitchen; Fire Safety Upgrade; Resurface Tarmac Ongoing
Killaloe GS Window Replacement; External Painting; Cell Area Upgrade Completed
Lisdoonvarna GS Public Office Upgrade Ongoing
Miltown Malbay GS Insulation Upgrade to Station and Married Quarters; Internal & External Painting; Chimney Repairs Completed
Newmarket-on-Fergus GS Public Office Upgrade; Insulation Upgrade; Driveway Repair; Heating Upgrade Completed
Scarriff GS Redash External Wall; Roof & Chimney Repairs; Internal Water Damage Repairs; External & Internal Painting Ongoing
Shannon GS External Works; Replace Gutters; Windows Replacement Ongoing
Sixmilebridge GS External Painting; Rebuild Front Wall; Footpath Repairs; Replacement of Soffit & Fascia Completed
Tulla GS Window & Door Replacement; New Entrance Gate Ongoing