Written answers

Tuesday, 20 October 2020

Department of Communications, Climate Action and Environment

National Broadband Plan

Photo of Patricia RyanPatricia Ryan (Kildare South, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

144. To ask the Minister for Communications, Climate Action and Environment if the roll-out of the national broadband plan will be expedited; if rural areas of County Kildare will be prioritised; and if he will make a statement on the matter. [31445/20]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract signed last November to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in over 544,000 premises, including almost 100,000 businesses and farms along with 695 schools.

The deployment plan forecasts premises passed in all counties within the first 2 years and over 90% of premises in the State having access to high speed broadband within the next four years. As of 13 October, design work is complete or ongoing in target townlands across 24 counties and steady progress is being made with over 103,000 premises surveyed to date. This activity is increasing week on week and NBI expects to have completed some 120,000 surveys by the end of the year. In County Kildare, surveys have been completed in areas including Naas, Johnstown and Kill.This activity involves physically walking the routes and documenting images, notes and measurements of the poles, cables and underground ducts in each area. This is informing design solutions for provision of the fibre network. This detailed design is then used to initiate the ‘make ready’ project with eir for the area, where eir ensure any poles and ducts being reused are fit for purpose. It is also used to initiate works with the subcontractors deploying the actual fibre in the area. The laying of fibre should commence shortly with the first fibre to the home connections expected around December this year in Cork. NBI provides a facility for any premises within the AMBER area to register their interest in being provided with deployment updates through its website ().

Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. As of 13 October 2020, some 164 BCP sites have been installed by NBI and 51 of these are now connected with high speed publicly accessible broadband, through a service provider contract managed by the Department of Rural and Community Development. It is anticipated that 275 BCP sites will be connected by the end of the year. Further details can be found at .

BCPs locations due for installation in Kildare include Backgate Lodge, Kilkee Demesne, Castledermot and Crookstown Further Education and Training Centre. BCPs installed and waiting connectivity include Lullymore Heritage Park and Bigstone Community Hall.

In addition some schools will be provided with high speed broadband through the BCP Programme, for educational use only, through a service provider contract managed by the Department of Education and Skills. A number of schools in Kildare including Saint David’s National School, Killashee, Naas and Rathmore National School, Rathmore West, Naas will be connected to high speed broadband as part of the BCP initiative. My Department will work with Department of Education and Skills to prioritise the remaining schools to be connected over the term of the NBP.

While substantial progress has been made to date, the Covid 19 pandemic has had an impact on the delivery of the fibre network. The extent of this impact is currently being assessed and NBI has committed to put in place measures to mitigate the impact in as far as possible. The Covid 19 pandemic has also highlighted the importance of good reliable broadband to ensure that citizens across Ireland can avail of remote working, education and other essential online facilities. This is reflected in the commitments in the Programme for Government where delivery of the National Broadband Plan will be a key enabler to many of the policies envisaged particularly around increased levels of remote working. The Programme for Government has committed to seek to accelerate the roll out of the National Broadband Plan. In this regard, my Department continues to engage with NBI to explore the feasibility of accelerating aspects of this rollout to establish the possibility of bringing forward premises which are currently scheduled in years 6 and 7 of the current plan to an earlier date. Exploring the potential to accelerate the network rollout is being undertaken in parallel with the measures required to mitigate delays arising as a result of Covid-19.

Photo of Holly CairnsHolly Cairns (Cork South West, Social Democrats)
Link to this: Individually | In context | Oireachtas source

145. To ask the Minister for Communications, Climate Action and Environment if the national broadband plan involves the laying of fibre broadband lines in areas that are already served; and if he will make a statement on the matter. [31460/20]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract signed last November to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in over 544,000 premises, including almost 100,000 businesses and farms along with 695 schools.

The NBP network will offer users a high speed broadband service with a minimum download speed of 500Mbps from the outset. This represents an increase from the 150Mbps committed to under the Contract.

The deployment plan forecasts premises passed in all counties within the first 2 years and approximately 70,000 to 100,000 premises will be passed each year thereafter which will result in over 90% of premises in the State having access to high speed broadband within the next four years.

Since 2013, my Department has engaged in an extensive process of mapping broadband availability in Ireland in order to identify areas which have no existing or planned Next Generation Access networks. A mapping consultation was conducted in 2019 to conclude the NBP mapping exercise to determine the final scope of the Intervention Area before contract award. The mapping exercise identified the areas where intervention is needed and where no private investor has demonstrated a concrete plan to invest commercially in high speed broadband in the near future. The mapping exercise confirmed the scope of the Intervention Area for the purposes of the contract with NBI.

NBI is now contracted to deploy high speed broadband within the Intervention Area. NBI deployment will maximise the re-use of existing infrastructure predominantly through the existing eir pole and duct network and the State owned Metropolitan Area Networks co-location sites.

Photo of Christopher O'SullivanChristopher O'Sullivan (Cork South West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

146. To ask the Minister for Communications, Climate Action and Environment the timeline and key benchmarks for rolling out the national broadband scheme in view of the requirement that more persons work from home; and if he will make a statement on the matter. [31466/20]

Photo of Eamon RyanEamon Ryan (Dublin Bay South, Green Party)
Link to this: Individually | In context | Oireachtas source

The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract signed last November to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in over 544,000 premises, including almost 100,000 businesses and farms along with 695 schools. The NBP network will offer users a high speed broadband service with a minimum download speed of 500Mbps from the outset. This represents an increase from the 150Mbps committed to under the Contract.

The deployment plan forecasts premises passed in all counties within the first 2 years and approximately 70,000 to 100,000 premises will be passed each year thereafter which will result in over 90% of premises in the State having access to high speed broadband within the next four years.

As of 13 October, design work is complete or ongoing in target townlands across 24 counties and steady progress is being made with over 103,000 premises surveyed to date. This activity is increasing week on week and by year end, NBI expects to have completed some 120,000 surveys. This activity involves physically walking the routes and documenting images, notes and measurements of the poles, cables and underground ducts in each area. This is informing design solutions for provision of the fibre network. This detailed design is then used to initiate the ‘make ready’ project with eir for the area, where eir ensure any poles and ducts being reused are fit for purpose. It is also used to initiate works with the subcontractors deploying the actual fibre in the area. The laying of fibre should commence shortly with the first fibre to the home connections expected around December this year in Cork.

Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. As of 13 October 2020, some 164 BCP sites have been installed by NBI and 51 of these are now connected with high speed publicly accessible broadband, through a service provider contract managed by the Department of Rural and Community Development. In addition some schools will be provided with high speed broadband for educational access only through service provider contracts managed by the Department of Education and Skills. My Department will work with Department of Education and Skills to prioritise the schools to be connected over the term of the NBP. It is anticipated that 275 BCP sites will be connected by the end of the year.

Further details can be found at .

While substantial progress has been made to date, the Covid 19 pandemic has had an impact on the delivery of the fibre network. The extent of this impact is currently being assessed and NBI has committed to put in place measures to mitigate the impact in as far as possible. The Covid 19 pandemic has also highlighted the importance of good reliable broadband to ensure that citizens across Ireland can avail of remote working, education and other essential online facilities.

This is reflected in the commitments in the Programme for Government where delivery of the National Broadband Plan will be a key enabler to many of the policies envisaged particularly around increased levels of remote working. The Programme for Government has committed to seek to accelerate the roll out of the National Broadband Plan. In this regard, my Department continues to engage with NBI to explore the feasibility of accelerating aspects of this rollout to establish the possibility of bringing forward premises which are currently scheduled in years 6 and 7 of the current plan to an earlier date. Exploring the potential to accelerate the network rollout is being undertaken in parallel with the measures required to mitigate delays arising as a result of Covid-19.

Comments

No comments

Log in or join to post a public comment.