Written answers

Tuesday, 1 October 2019

Department of Public Expenditure and Reform

Capital Expenditure Programme

Photo of Michael McGrathMichael McGrath (Cork South Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

172. To ask the Minister for Public Expenditure and Reform the final agreed tender price, the date of the tender for the contract and the final overall amount actually paid and the date of the final payment in respect of each capital expenditure project completed since 1 January 2014 by his Department or an agency under the remit of his Department and which ended up costing €10 million or more in tabular form; the reason the final amount paid exceeded the final tender price; the details available in respect of projects in which construction is not complete to date or in which the final settlement account has not been agreed to date; and if he will make a statement on the matter. [39929/19]

Photo of Paschal DonohoePaschal Donohoe (Dublin Central, Fine Gael)
Link to this: Individually | In context | Oireachtas source

My Department has not incurred any capital expenditure on projects in excess of €10 million since 1 January 2014. 

In respect of the relevant bodies under the aegis of the Department, the National Shared Services Office will respond to the Deputy directly.  The position regarding the Office of Public Works (OPW) is set out in the following tables:

OPW Vote Capital Projects

Project NameFinal Agreed Tender PriceTender Contract DateFinal Overall Amount PaidDate of Final PaymentReason final amount paid exceeded the final tender priceDetails available in respect of projects in which construction is not complete to date or in which the final settlement account has not been agreed to date
Historic Leinster House€12.82m including VAT13/11/17Project is due for completion Q4 2019
Miesian Plaza

Carried out by Landlord under lease contract arrangements
€23.5m including VATAt Final Account Negotiations

Client Funded Capital Projects

Project NameFinal Agreed Tender PriceTender Contract DateFinal Overall Amount PaidDate of Final PaymentReason final amount paid exceeded the final tender priceDetails available in respect of projects in which construction is not complete to date or in which the final settlement account has not been agreed to date
National Children’s Detention Centre€49.3m including VAT16/8/13€52.8mNovember 2018Cost of additional Works over and above those specified in Tender Docs
Historic Wings, National Gallery€29.291m including VAT17/1/14Conciliation process
Kevin Street Garda Divisional HQ €31.020m including VAT30/1/15Conciliation process
Wexford Garda Divisional HQ€25.295m including VAT3/7/15The release of the final payment to the contractor is expected to issue shortly.
Galway Garda Divisional HQ€28.324m including VAT2/10/15Conciliation process

Flood Unit

Flood Relief SchemeFinal Agreed Tender Price

(excl. VAT)
Tender Contract DateFinal Overall Amount Paid

(excl. VAT)
Date of Final PaymentReason final amount paid exceeded the final tender priceDetails available in respect of projects in which construction is not complete to date or in which the final settlement account has not been agreed to date
Bandon Flood Relief Scheme€10,988,50010/6/2016Project not completeN/ANot applicable as contract not completed yet.Until contract is complete it will not be possible to provide a final figure.
Skibbereen Flood Relief Scheme€15,856,94220/5/2016Project not completeN/ANot applicable as contract not completed yetUntil contract is complete it will not be possible to provide a final figure.
Fermoy South Flood Relief Scheme€14,536,1309/2/2012€19,171,520*5/06/2016Claims for additional works and change orders arose on the project, some of which resulted in Conciliator’s recommendationsN/A
Mallow South Flood Relief Scheme€5,379,8347/7/2010€10,250,000**14/6/2016Claims for additional works and change orders arose on the project, some of which resulted in Conciliator’s recommendationsN/A
Ennis Lower Flood Relief Scheme€7,106,97116/01/2013€11,278,83914/12/2016Claims for additional works and change orders arose on the project, some of which resulted in Conciliator’s recommendationsN/A
*This is the agreed Final account. Retention of €47,928.80 remains to be paid.

**This is the agreed Final account. Retention sum of €20,000 remains to be paid.

Comments

No comments

Log in or join to post a public comment.