Question 518: To ask the Minister for Education and Science when the necessary funding will be provided for the extra accommodation for a school (details supplied) in County Mayo. [16752/07]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

An application for an extension and refurbishment building project has been received from the school referred to by the Deputy. An assessment of projected enrolments, demographic trends and housing developments in the area will be required to be carried out by the Department in order to assist in determining the long term projected enrolment for the school on which the school's long term accommodation needs will be based. When the long-term projected enrolment has been finalised and agreed with the school authorities my Department will draw up schedules of accommodation for the project which will be notified to the school management authority. The project will then be considered in the context of the multi-annual School Building and Modernisation Programme.

Photo of Olwyn EnrightOlwyn Enright (Laois-Offaly, Fine Gael)
Link to this: Individually | In context

Question 519: To ask the Minister for Education and Science if her attention has been drawn to the fact that students are attending a school (details supplied) in County Tipperary in former council buildings; if her attention has been further drawn to the conditions at the school; if there are any plans to address the situation; and if she will make a statement on the matter. [16757/07]

Photo of Mary HanafinMary Hanafin (Dún Laoghaire, Fianna Fail)
Link to this: Individually | In context

The School Planning Section of the Department is in receipt of an application from the school to which the Deputy refers for major capital works. The application has been assessed in accordance with published prioritisation criteria for large scale building and was assigned a band 2 rating.

The Property Management Section of the Office of Public Works, which acts on behalf of the Department in relation to site acquisitions generally, was requested to explore the possibility of acquiring a site for the school in question. Following an advertisement seeking proposals in relation to possible sites a number of responses were received. Six sites have been visited and their technical suitability as a location for the school was considered.

Following this process, a site on the existing Tipperary Rural and Business Institute (TRBDI) campus emerged as the preferred option. This site is in the ownership of the Institute. The TRBDI, however, has proposed to the Department that its campus be relocated to a large-scale technology park. Expressions of Interest were sought by TRBDI from the private sector to determine what exactly could be provided at the technology park in exchange for the Institute's current property in Clonmel. The Expressions of Interest sought required the incorporation of a suitable site for the school on the current campus or on an alternative site approved by the Department and the Office of Public Works. The Expressions of Interest received by TRBDI have been evaluated and detailed negotiations are being entered into with the company that has submitted the tender provisionally identified as being the most advantageous.While this process is reasonably well advanced, I appreciate that it is taking longer than expected. Given the urgency of the schools' needs as you have outlined them to me, the Department will immediately seek alternative site options in Clonmel, with a view to acquiring a site before the end of the year.

Funding is available for the purchase of the site as part of the record provision of €4.5 billion for school buildings in the National Development Plan. I absolutely appreciate how long the school has been in its current accommodation. I assure you that the Government will do all that we can to have a site for the school by the end of 2007 and that the project will then be progressed in the context of the multi-annual school building and modernisation programme.