Public Accounts Committee: 2021 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 29 - Environment, Climate and Communications
2021 Report of the Comptroller and Auditor General - Chapter 9: Implementation of the National Broadband Plan
(13 Oct 2022) See 1 other result from this debate

..., as Mr. Mulligan can attest, the way of working is defined more by deployment area, whereby we hit rural, suburban and semi-rural homes. It is dictated more by the roll-out from the Eir and the Enet hubs.

Joint Oireachtas Committee on Transport, Tourism and Sport: National Broadband Plan Update: National Broadband Ireland (29 Jun 2022)

...areas, what we would look to do, rather than necessarily adding a fibre connection to some of the premises in Dublin, is to procure what we classify as a fibre leased line from the likes of Eir or Enet. It would be a more expensive service but over the life of 25 years it would still likely be cheaper than us bringing fibre all the way through Dublin to connect.

Joint Oireachtas Committee on Transport, Tourism and Sport: Shannon Group: Chairperson Designate (25 May 2022) See 2 other results from this debate

...and chair of Fibrus, a telecommunications provider which has raised £500 million to invest in broadband infrastructure in the North of Ireland. Before Fibrus, I spent 12 years as CEO of Limerick-based Enet, a telecoms provider, taking it from start-up to its £200 million acquisition by the Irish Infrastructure Fund in 2017. As CEO of Enet, l also led what is now known as...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (23 Feb 2022)

Ossian Smyth: ...into infrastructure access agreements with the relevant entities. NBI will be utilising over 1.5 million poles and over 15,000 kilometres of duct networks.As part of the rental agreements, eir and enet are fully responsible for the maintenance and upkeep of infrastructure in use by NBI. The full cost of this is included in the annual rental charges to NBI. In the case of eir, the...

Written Answers — Department of Communications, Climate Action and Environment: Broadband Infrastructure (22 Feb 2022)

Eamon Ryan: I propose to take Questions Nos. 151 to 153, inclusive, together. I am advised by enet, the company that manages the Metropolitan Area Networks (MANs) on behalf of the State that three telecommunications operators are currently using the fibre based Metropolitan Area Network (MAN) infrastructure at Knock. While the services provided by these operators are a commercial matter...

Public Accounts Committee: 2020 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 29 - Environment, Climate and Communications
National Broadband Plan Expenditure and Related Matters
(10 Feb 2022) See 5 other results from this debate

...on the project. That includes our specialist subcontractors, the likes of Integro, Indigo, KN Group, Secto, Actavo and TLI. We are also working with infrastructure operators such as Open Eir and Enet. I acknowledge all of the hard work that has been done by everybody involved to date, as well as the collective commitment to bring high-speed broadband to those who need it most. Across...

Joint Oireachtas Committee on Transport, Tourism and Sport: National Broadband Plan Update: National Broadband Ireland (27 Jan 2022)

...give an example. The Irish infrastructure fund, in which Ireland Strategic Investment Fund, ISIF, is an investor, has 24 pension funds in that fund. Although they were party to an investment in Enet, Eircom and other assets in Ireland and I know the team, I do not know what the 23 funds are. I do not know anything about who the investors are in that, under confidentiality agreements....

Seanad: Broadband Roll-out: Statements (26 Jan 2022)

Lynn Boylan: ...about the financial and corporate arrangements. There are several operational problems faced currently such as the problems of Eir-NBI duplication and the fact that NBI is dependent on capacity within Eir, Enet and, to a lesser degree, ESB. There were difficulties in crossing lands owned by CIE, although those are largely dealt with. There were difficulties dealing with local...

Public Accounts Committee: 2020 Report of the Comptroller and Auditor General and Appropriation Accounts
Vote 29 - Environment, Climate and Communications
Chapter 9 - Remediation of Landfill Sites
(14 Oct 2021) See 1 other result from this debate

...is fully responsible for all 679 schools. Through that contract with us and NBI, NBI then procures different companies across different parts of Ireland to help them to roll that out, whether its Enet, Viatel or Ripplecom. Many companies offer it. At the moment, the majority of schools and BCPs are using an 8.5 high-spec wireless link until the fibre network is fully deployed across the...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (5 Oct 2021)

Ossian Smyth: ...possibility of bringing forward premises which are currently scheduled in years 6 and 7 of the current plan to an earlier date. As part of that work NBI is engaging with current build partners (eir and enet) to bring forward build activities and is also actively reviewing other possible build partners where such options could also speed up the build process. However, the primary focus must...

Joint Oireachtas Committee on Transport, Tourism and Sport: Business of Joint Committee
Update on National Broadband Plan: National Broadband Ireland
(15 Sep 2021)

..., onboarded and working on the project. That includes our key sub-contractors Actavo, Entegro, Indigo, KN Group, Secto and TLI. We are also working with infrastructure operators such as Open Eir and Enet. I would like to acknowledge all the hard work that has been done by everyone involved to date, and the collective commitment to bring high-speed broadband to those that need it most....

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (13 Jul 2021) See 1 other result from this answer

Ossian Smyth: .... Exploring the potential to accelerate the network rollout is being undertaken in parallel with the measures required to mitigate delays arising as a result of Covid-19. As part of that work NBI is engaging with all current build partners (eir and enet) to bring forward build activities and is also actively reviewing other possible build partners where such options could also speed...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (1 Jun 2021)

Ossian Smyth: .... NBI has established a dedicated team to investigate acceleration of the rollout from its current contracted schedule of seven years.  As part of this investigation NBI is engaging with current build partners (eir and enet) to reschedule build activities and is also reviewing potential additional build partners as an option to speed up the build process. Exploring the potential...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (1 Jun 2021)

Ossian Smyth: ...earlier date. A dedicated team in NBI is investigating the acceleration of the rollout from its current contracted schedule of seven years.  As part of this investigation NBI is engaging with current build partners (eir and enet) to reschedule build activities and to review potential additional build partners as an option to speed up the build process.  Exploring the potential...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (18 May 2021)

Eamon Ryan: ..., Actavo and Entegro. Further employment is being provided by build subcontractors including KN Group, Actavo, TLI and Secto, as well as technology partners such as Nokia, who are providing the broadband equipment for the project. Another key partner is Enet who are providing infrastructure and services from the State owned Metropolitan Area Networks and its wider...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (21 Apr 2021)

Eamon Ryan: ...are underway. NBI has established a dedicated team to investigate acceleration of the roll out from its current contracted schedule of seven years.  As part of that work NBI is engaging with current build partners (eir and enet) to bring forward build activities and is also actively reviewing other possible build partners where such options could also speed up the build process....

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (10 Mar 2021)

Eamon Ryan: ...established a dedicated team to investigate acceleration of the rollout from its current contracted schedule of seven years.  As part of that work NBI is engaging with current build partners (eir and enet) to bring forward build activities and is also actively reviewing other possible build partners such as the ESB where such options could also speed up the build process. Exploring...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (4 Mar 2021)

Eamon Ryan: ...25km in radius and in total they cover 96% of Ireland’s landmass. The architecture of the network design is specifically based on the design of the NBI network coming from the eir exchanges or the metropolitan area networks (MANs) managed by Enet. It is based on an engineering design that allows NBI to get to every premises as quickly as possible working within the confines of...

Written Answers — Department of Communications, Climate Action and Environment: National Broadband Plan (24 Feb 2021)

Eamon Ryan: ...Ireland’s landmass. The architecture of the network design is specifically based on the design of the NBI network coming from the eir exchanges or the metropolitan area networks (MANs) managed by Enet. It is based on an engineering design that allows NBI to get to every premises as quickly as possible working within the confines of how fibre networks are built. Each DA creates a...

Written Answers — Department of Communications, Climate Action and Environment: Broadband Infrastructure (18 Feb 2021)

Eamon Ryan: ...has established a dedicated team to investigate acceleration of the rollout from its current contracted schedule of seven years As part of that work NBI is engaging with all current build partners (eir and enet) to bring forward build activities and is also actively reviewing other possible build partners such as the ESB where such options could also speed up the build process. Exploring...