Saincheisteanna Tráthúla - Topical Issue Debate
Schools Building Projects
9:50 am
Marian Harkin (Sligo-Leitrim, Independent) | Oireachtas source
I thank the Deputy for raising this matter and giving me the opportunity, on behalf of the Minister for Education and Youth, to outline to the Dáil the current position in relation to the joint school project for St. John Bosco Junior Boys School, St. John Bosco Senior Boys School and Mary, Help of Christians Girls' National School in Dublin 7.
This joint school building project will deliver two new 16-classroom primary schools with additional classrooms for children with special educational needs for both the senior boys' school and the girls' school and a new 11-classroom primary school with additional classrooms for children with special education needs for the junior boys' school.
Initially, it had been anticipated that this joint project would be delivered in the form of an extension and refurbishment. However, due to a scope change to include an increase in classrooms for children with special educational needs, it was decided that new school buildings would be provided. The design team submitted the initial stage 1 report in April 2023 and following the submission of an addendum report in August 2023, the project was approved to the next stage. The design team submitted their stage 2a submission report in January 2024.
Upon review, some key concerns were identified by Department officials. From January 2024 to May 2025, there was significant communication between the design team and the Department to discuss and assist in progressing the stage 2a submission to include a review and audit of the floor area schedules to refine some design elements to meet the approved schedule of accommodation.
Upon receipt of the revised stage 2a report, Department officials carried out an initial review. In early June 2025, a further meeting was held with the wider design team, school authorities and Department officials in attendance. At that meeting, the school was provided with a progress update and advised that the design team were due to submit an addendum stage 2a report to the Department. The outstanding information for the addendum stage 2a report was received by the Department officials on 31 October 2025 and is currently under review by them. They visited the school on Friday 27 March 2026 and discussed potential options for a solution with the school authorities. Further discussions were held on 18 June. Department officials will continue to engage and update the school authorities of progress regarding these decisions. In June, the Department issued primary schools with their school-specific patronage survey results and explanatory information, marking the next stage in the process of engaging school communities on the future direction of their schools. Where the survey shows demand for change, boards of management have the opportunity to consider being included in the first group of schools to action the survey results. Schools have been asked to inform the Department and their patron by 31 October 2026 should the school wish to be included in this first group of schools to action the primary school survey results.