Oireachtas Joint and Select Committees

Thursday, 16 July 2026

Public Accounts Committee

Financial Statements 2024: National Transport Authority (Resumed)

Ms Anne Shaw (Chief Executive Officer, National Transport Authority) called and examined.

2:00 am

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

This morning, we engage with the National Transport Authority, NTA, and Iarnród Éireann to resume discussion on the National Transport Authority's 2024 financial statements. On behalf of the committee I would like welcome officials from the NTA: Ms Anne Shaw, chief executive officer, and Mr. Hugh Creegan, deputy chief executive officer and director of transport, planning and investment. From Iarnród Éireann, we are joined by Ms Mary Considine, chief executive officer, and Mr. Paul Hendrick, director of capital investments. We are also joined by Mr. Tomás Campbell, principal officer at the heavy rail investments division of the Department of Transport, who is attending in a representative capacity. Finally, we are joined by officials from the Office of the Comptroller and Auditor General, including Ms Colette Drinan, secretary and director of audit, on behalf of the C and AG, who is a permanent witness to the committee, and Ms. Georgina O'Mahony, deputy director of audit. The witnesses are all very welcome.

Before we begin, I wish to explain some limitations to parliamentary privilege and the practice of the Houses as regards references you may make to other persons in your evidence. The evidence of witnesses physically present or who give evidence from within the parliamentary precincts is protected pursuant to both the Constitution and statute by absolute privilege. This means that you have an absolute defence against any defamation action for anything you say at the meeting. However, you are expected not to abuse this privilege and it is my duty as Cathaoirleach to ensure that this privilege is not abused. Therefore, if your statements are potentially defamatory in relation to an identifiable person or entity, you will be directed to discontinue your remarks. It is imperative that you comply with any such direction. Witnesses are also reminded of the long-standing parliamentary practice that they should not criticise or make charges against any person or entity, by name or in such a way as to make him, her or it identifiable, or otherwise engage in speech that might be regarded as damaging to the good name of the person or entity.

I now invite Ms Drinan to deliver her opening statement on behalf of the Office of the Comptroller and Auditor General.

Ms Colette Drinan:

The National Transport Authority’s financial statements for 2024 were previously examined at a meeting of the Committee of Public Accounts on 15 January 2026. At that meeting, the Comptroller and Auditor General outlined the main features of the authority’s financial situation. He also summarised the evolution of the national train control centre project up to mid-2025, drawing attention to the ongoing delays in relation to development of the train management system and the anticipated cost overrun associated with the project, projected then to be in the order of 28%.

Further review of the train control project was undertaken in the context of the audit of the authority’s financial statements for 2025. The Comptroller and Auditor General certified the 2025 financial statements on 17 June 2026. Once the financial statements are received by the Department of Transport, the Minister has statutory responsibility for their presentation to the Oireachtas.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I now call invite the chief executive officer to deliver the opening statement on behalf of the NTA. Ms Shaw, as set out in the letter of invitation, you have five minutes to make your opening statement.

Ms Anne Shaw:

I thank the committee for the invitation to appear before it today to continue its consideration of the National Transport Authority's 2024 financial statements. This is with particular focus on the national train control centre project and the associated traffic management system contract. I am joined by Mr. Hugh Creegan, deputy chief executive and director of transport planning at the NTA, and I also welcome representatives of Iarnród Éireann, the delivery agency for the national train control centre. Together, we will seek to address the committee's questions fully and transparently, where possible, recognising that some issues remain commercially and legally sensitive. We have provided a detailed briefing document and other information as part of our submission last Friday.

It is worth clarifying the NTA's responsibilities in relation to major transport investment projects. The NTA is the statutory body responsible for the planning, provision and funding of public transport and active travel infrastructure. We also act as the approving authority for major public transport investment programmes, including BusConnects, DART+, MetroLink and the national train control centre programme.

The Government's infrastructure guidelines clearly distinguish between the roles of the sponsoring agency and the approving authority. Under these arrangements, the sponsoring agency is responsible for the planning, procurement, contract management and delivery of a project, including the achievement of its approved scope, budget, programme and intended benefits. The approving authority is responsible for funding the project, approving key decisions at defined stages of delivery and overseeing implementation through appropriate reporting and assurance arrangements.

In its role as approving authority, the NTA provides oversight of delivery of the capital programme by the various sponsoring agencies, and reports progress to the Department of Transport through the major projects governance oversight group. We work closely with project delivery bodies to address risks, assess proposed changes and consider any implications for budgets, delivery schedules and the wider investment portfolio.

Many major transport investments continue to progress successfully, including BusConnects which continues to advance, with all 12 core bus corridors having received planning permission and construction under way on two schemes, plus the procurement of a third corridor to commence shortly. The DART+ programme also continues to advance with confirmed railway orders and construction procurement under way. MetroLink has also received planning consent and is now moving into its procurement and construction stage. Active travel investment is also delivering a large number of benefits.

The NTA is also investing in new bus depots to support service expansion, with the Jamestown depot now operational, planning consent secured for a new bus depot in Blanchardstown, a new Go-Ahead Ireland depot opening shortly in Northwest Business Park in Dublin, and the Tivoli depot in Cork due to open in quarter 3 of 2026. In the case of the National Train Control Centre programme, the NTA is the approving authority and Iarnród Éireann is the sponsoring agency. Accordingly, while the NTA is responsible for funding, oversight and approval at key decision points, responsibility for the delivery and procurement of the contract is with Iarnród Éireann. The committee is rightly concerned about the write-down reported by Iarnród Éireann and the delays affecting the traffic management system project. Let me be clear that the NTA takes these issues extremely seriously. Protecting public funds and ensuring value for money are central to our assessment of all requests and recommendations from sponsoring agencies.

Over the lifetime of the project, Iarnród Éireann, with the support of the NTA, has sought to address delivery challenges through revised programmes and alternative implementation strategies. While an alternative delivery model remained an option, no formal recommendation seeking such a change was made by the Iarnród Éireann board to the NTA until recently. Instead, Iarnród Éireann and the NTA engaged extensively with Indra to help to develop and implement revised delivery strategies to progress the project. These approaches were informed by commitments and actions by Indra to address issues on the project, recognising the risks inherent in all approaches. At the centre of these efforts was the objective of ensuring the successful delivery of a traffic management system capable of supporting both current operations and future network expansion.

Following its internal governance processes, Iarnród Éireann formally informed the NTA on 29 June of the decision by its board regarding the existing role of Indra and the proposed way forward. The NTA requested additional information on 30 June to support consideration of that decision by the NTA, including its board and capital programme committee. The NTA received this extensive supporting information, including project risks, privileged legal advice, potential liabilities, future delivery options and implications for the wider programme. As approving authority, the NTA considered the implications of Iarnród Éireann's decision for the overall project, as well as the wider capital programme. The evidence indicates that the supplier is unlikely to deliver the required system in full specification within any reasonable timeframe and an alternative delivery approach is needed. Given these ongoing costs, the matter was considered as a priority through the NTA's governance processes, and the NTA board has now accepted Iarnród Éireann's decision regarding the role of Indra going forward. This was communicated to Iarnród Éireann on 13 July.

Both organisations, together with the Department of Transport, will continue to assess the implications of this decision, including additional funding requirements for delivering the traffic management system within the overall rail investment budget envelope to achieve the best possible outcome. Separately, the NTA has commissioned an independent review of the project, which is due to report in September. The review will examine governance, delivery and project oversight arrangements within both Iarnród Éireann and the NTA, and identify lessons to strengthen the delivery of future major infrastructure projects and, in particular, technology projects. Committee members may also be aware of the next generation ticketing project, which is being delivered directly by the NTA with Indra as the supplier. I can confirm that this integrated ticketing project remains on budget and on schedule. The contracting mechanism is different from that of the NTCC contract, with payment due only to successful delivery of each of the 34 key milestones.

We understand the committee is also interested in progress in delivering bus fleet electrification and, in particular, the cost of buses in storage pending absorption into the fleet. This information is detailed in a note provided to the committee. While there have been delays in delivering charging infrastructure, accounting for these buses needing to be in storage, the costs incurred are offset by the avoidance of inflationary increases that would have arisen on later purchase of those buses. In the meantime, the buses are stored and maintained by the manufacturer to ensure they remain in optimal condition and are expected to be fully absorbed into both Dublin Bus and Bus Éireann fleets by quarter 1 of 2027. I welcome the opportunity to assist the committee today and to outline the actions being taken to protect public funds and secure the best outcome for the public.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I thank Ms Shaw. I will now ask Ms Considine to deliver the opening statement on behalf of Iarnród Éireann.

Ms Mary Considine:

I thank the Cathaoirleach and committee members for the invitation to discuss matters relating to the National Train Control Centre, NTCC, project with the committee. Iarnród Éireann is at a time of record demand and record investment. The portfolio of projects that we are overseeing is progressing well in the main. However, the serious problems encountered with the traffic management system, TMS, contract with Indra are of deep concern to us as a management team and to our board. The project has reached a point where Iarnród Éireann has no certainty as to when the contractor will fulfil its contractual obligations, and no confidence in its ability to do so, despite the extensive and continuing efforts of Iarnród Éireann and the National Transport Authority as the approving agency.

I have detailed what the NTCC is and the progress with the other elements of that, which are all on time and on schedule. However, the delivery of the TMS, originally due to be completed in June 2024, is yet to be completed by Indra. The joint Iarnród Éireann-NTA appendix, which I have attached to this statement, details the extensive procurement process supported and advised by external subject matter specialists. Additionally, the NTA would have commissioned specialists to undertake an independent technical review of the TMS scope of services prior to providing approval to release the tender documents to the market. Ultimately, from seven pre-qualified suppliers, two bids were received in early 2019. Each bidder was required to submit a compliance matrix to demonstrate that their proposed product solution would meet a minimum of 70% of the system requirements without the need for further software development.

Indra's compliance document was assessed by our specialist consultants, which determined it would meet 96% of the contract requirements. This, together with its systems integration plan and references by it to a 15-year history of 21 successful deployments in multiple national railways, led us to believe that Indra had a mature developed product ready for deployment into Ireland with minimal additional software development required. Iarnród Éireann also engaged Turas to provide project management support services, and Ricardo Rail to provide system integration and safety assurance services to support the delivery of the contract.

Post contract award, and early in the preliminary design phase, Indra advised that its deployed TMS product would no longer be supportable over the life of the maintenance contract, and it would be upgraded to a newer version in 2021. It reassured Iarnród Éireann that the software would be developed in a manner that would support future safety certifications and that its "generic product", as it called it, would be delivered in 2021 prior to the commencement of the Irish TMS software development process. It should be noted that, as of today, to the best of our knowledge software supported by this generic product has yet to be deployed in any railway.

The timeline provided outlines how the issues impacting the TMS programme unfolded. Management ensured that our board and the NTA, as approving authority, and the Department of Transport through the major projects governance oversight group, MPGOG, were advised, and in the case of commercial resettlements that both our board and NTA approval were received. While the timeline is comprehensive, I would highlight two specific milestones. First, when the re-baselined programme requested by us in the end of 2023 and accepted in early 2024 was sliding significantly off-track by mid-2024, Iarnród Éireann advised the NTA of an increasing lack of confidence in Indra's ability to deliver the project. Indra agreed to the request of NTA and Iarnród Éireann to take steps to restore confidence, and an alternative delivery strategy was developed comprising the delivery of a minimum viable product initially, with full functionality to be delivered over eight phases. Second, by mid-2025, testing identified a number of systemic issues, and Indra's own independent safety assessor also confirmed that the software was not ready to be deployed into service.

We discussed a continuing lack of confidence in Indra with the NTA in mid-2025. The NTA, from that point, took a significantly more active role in project oversight and contract management, holding fortnightly meetings with Indra and Iarnród Éireann.

Notwithstanding that, Indra’s project delivery model was restricted to the commissioning of the Rosslare line, which the committee will see referred to as CP1. It is a relatively simple section of the network with minimal functionality representing approximately 3% of the project scope. A further 16-month delay in the CP1 commissioning milestone had been indicated by the end of 2025 and ultimately, in April 2026, Indra formally released its redeveloped CP1 software product to us for testing. It was immediately apparent, through our railway signalling principles testing, that many of the systemic issues that existed in 2025 remained and, in this context, our board took the decision to impair the carrying value of the asset in the financial statements for the year ending 31 December 2025, with the accounts submitted to the Department of Transport prior to publication.

Upon completion of the comprehensive testing process, it was concluded that the software was demonstrably not suitable for training or commissioning. Regrettably, therefore, six years on and two years after the original commissioning date, Indra still does not have a developed product fit for safe deployment on our rail network. On 22 June the Iarnród Éireann board reached decisions regarding the existing Indra contracts and the proposed way forward to deliver a necessary replacement of the existing signalling control system and we formally sought the approval of the NTA to implement those board decisions.

The committee will appreciate that, with the acceptance by the NTA of the decision relating to Indra, and as a result of sensitive commercial and legal considerations at this point, we may be unable to give absolute clarity on aspects of the decision at this time. I sincerely apologise to the committee for this in advance but I assure it that we are seeking to act in a way that can deliver the TMS component of this project in a manner that supports our wider investment programme, protects today's railway and minimises any future exposure of the taxpayer.

I am joined today by my colleague, Mr. Paul Hendrick, director of capital investment and we welcome questions from the committee.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Please note that we will suspend the meeting at approximately 12.30 p.m. for a short 15 minute break and resume shortly thereafter.

I open the floor to members. The lead speaker today is Deputy Paul Murphy, who has 15 minutes. All other members have ten minutes. If time permits, we will allow members in for a second round of shorter slots.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

I thank the witnesses for coming before us and for the extensive briefing documents. One of the things that struck me was the diagram of a long saga, which has resulted in approximately €50 million of public money being effectively flushed down the drain and us still not being very far along on what we clearly desperately need in a new traffic management system.

My starting question is: who is responsible for this disaster? Where does responsibility lie?

Ms Anne Shaw:

I will answer first. We have already clarified, in terms of the infrastructure guidelines, what the roles of each of the organisations are but both organisations continue to work together and collaborate for the successful delivery, in the same way as we work with all our sponsoring agencies on all our projects. The delivery of the project and contract that is in place sits with Irish Rail. That does not mean the NTA does not continue to support that work and provide oversight and advice as part of that. I do not know whether Ms Considine wants to add anything.

Ms Mary Considine:

I thank Deputy Murphy. I can hear his frustration about where we are. There is deep regret right across Iarnród Éireann that we are in this position. However, as I outlined in my opening statement and as we detailed in the joint appendix, every opportunity has been given to the contractor to deliver. There has been significant support, including third party specialist support, to help it and we find ourselves in a very difficult position. The reality is that we now need to move at the earliest opportunity to make decisions that will allow us to put in place a traffic control system and minimise any further exposure of the Exchequer. We have a significant role to play in providing public transport and ensuring we have a reliable service and we want to future-proof the expansion of the railway. That is ultimately what we want to do in the most cost effective manner.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Sure. Effectively what the witnesses are saying is that Indra is responsible. Fine. I agree from what I have read that Indra screwed over Irish Rail, the NTA and the public but the question is why we signed such a contract that has allowed it to do so.

Let us go back to the start. There were two bidders for the contract, which seems like a small number. Who made the decision that Indra would get the contract?

Ms Mary Considine:

There was an extensive procurement process, including market research, market consultation and engagement. Ultimately, seven bidders pre-qualified and two were appointed. They went through a technical review by the team and then Iarnród Éireann, in the determining of that, hired specialists, Ricardo rail, to advise it on the appointment. Separately, I understand, while I do not speak for the NTA, that the NTA hired Jacobs to review the tender. All of that was done.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Did the private company Ricardo make the decision?

Ms Mary Considine:

No, it advised Iarnród Éireann.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Who made the decision?

Ms Mary Considine:

Ultimately, it was Iarnród Éireann, based on a 242 page compliance document that Indra supplied, which showed it met 96% of the compliance criteria.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

The board of Iarnród Éireann ultimately made the decision.

Ms Mary Considine:

Yes, subject to the funding of the approving authority.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Was there appropriate technical expertise on the board to make that decision, including digital and IT expertise, to be able to make the decision that this was the correct bidder or was the board just led by what Ricardo said?

Ms Mary Considine:

I believe there was appropriate experience on the board. I was not there at the time. I do not know whether my colleague can interject but we do rely on technical expertise for advice.

Mr. Paul Hendrick:

I was not in the business at the time either but all the projects in this scenario go through a standard process. They go through a standard procurement evaluation and follow set criteria for the project team and any outside technical advisers the team has on the project. That leads to a recommendation based on a scoring system for that bid and the recommendation goes to the Irish Rail board for a decision.

The membership of the board changes from time to time based on tenure but there are typically one or two non-executive board directors who have technical backgrounds and then there are other business specialists. We would have to go back to check who was on the board at the time but we follow a set process.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

When one reads through it, what seems to be a key factor is that, effectively, part of the contract says that the proposed product solution is to have a minimum of 70% of system requirements without the need for further software. That is part of the compliance matrix. Indra said not to worry about that, that it would do 96%. There would be 4% new but that it had this great thing, DaVinci 2.0, which is working elsewhere and that it could be used. Indra got the contract on that basis and then a few months later it said it turned out that they are not going to continue to support that product - it is Indra's product but it was not going to be able to continue to support it, which does not seem to make any sense; it seems to be a choice about obsolescence made by Indra - and that a new version, DaVinci 3.0, would be needed. Then, according to the project statement:

The project team, supported by expert consultant review from Turas and Ricardo Rail, [which designed the tender process in the first place] determined that Indra’s approach remained compliant with the TMS contract.

This seems to be at the heart of the problem. The tendering process was based on contractors having to have software already in place. Indra won the contract on the basis of having said it did and then after getting the contract, it said it would have to develop new software, yet that was found not to be a breach of the contract. Is that the core of the problem?

Ms Mary Considine:

I might refer - and then I will hand over to Mr. Hendrick for more detail - to 1.18 in our appendix document. As part of its bid, Indra outlined the technological evolution of its DaVinci 1.0 to DaVinci 2.0, that is how it evolved over the lifetime of the product. Therefore, that, with the advice our team sought from external experts, all led them to believe that Indra was still compliant with the contract. Specific advice was sought at the time from Ricardo and Turas to make sure Indra was still compliant with the original contract and that was the advice given to Iarnród Éireann.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Does that suggest there was a problem with the contract? Indra won the contract by saying it had the software and then said it would need new software and that would take a bunch of time. Iarnród Éireann still does not have it. This new software does not exist anywhere in the world according to the documents. Does that not indicate there was a problem with the contract?

Ms Mary Considine:

Quite a number of assurances were given at the time that the company's generic product had already been in development since 2018. Safety assurance would have been got on that, and that feedback would have been given back.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Forget about those assurances. They are clearly worthless now so, in hindsight, was there a problem with the contract? Should we not have signed it, if it allowed the company to win it on one basis and then to say that it needed new software?

Ms Mary Considine:

In reality, Indra is a multibillion-dollar company that provides systems all over the world. It pointed to its 15-year history of 21 successful redeployments all over the rail network globally. I was not there at the time but I spoke at length to our team, and there was no reason to believe that in the context of the bid put forward, which had gone through all the technical scrutiny and was passed by not only Irish Rail but also the specialists advising us, Indra was not developing its generic product, as it led us to believe, and that it was evolving situation.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Surely we should have had a contract that would not have left Irish Rail having to rely on Indra's good faith and on whether it believed things or not. We should surely have had a contract that said the company had to have the software already and could not be developing new software. Is that not a fundamental flaw here, that happened right at the start of the development of the contract? Ms Considine does not agree.

Ms Mary Considine:

The advice to the company at the time did not agree with that.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Was that the advice to Irish Rail from Ricardo?

Ms Mary Considine:

The advice provided to Irish Rail did not support terminating the contract.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Yes, but again, does this not go back to the point that this suggests there was a problem with the original contract? If the contract allowed Indra to win this competition on the basis that it had the software, and then the company was able to say it did not have the software, either it was in breach of the contract or there was a problem with the contract.

Mr. Paul Hendrick:

We follow an open tender process, in the Official Journal of the European Union, OJEU, and have a competition open to the EU market to respond. There are a set of requirements in the contract that allows the open market to respond in the pre-qualification and bid stages. In the contract, Indra was, effectively, the designer hired. It was a design-and-build contract, so Indra was hired to deploy what is its system but to meet the client's requirements. In picking that process, we cannot overprescribe the solution we want. We have to have a set of output requirements in the contract to make it a compliant EU procurement process.

It was a surprise to the team when Indra moved from DaVinci 2.0 to DaVinci 3.0. That was not expected. I fully agree that was not expected to happen. In the discussions around it, it was seen as a normal product development process for these products, because there was previously a DaVinci 1.0. It was rolled out as part of a number of applications. Indra then moved to DaVinci 2.0, which it had been running for about ten years, and it was moving to the next version of it. The company was adamant that the next version was, effectively, going to continue to give the underlying 96% compliance and that it was going to be a better product than the previous one and the one it was going to support.

The experience we have had since that clearly shows that something has gone wrong between Indra moving from DaVinci 2.0 to DaVinci 3.0, which is where we are now, because if we got DaVinci 2.0 that other jurisdictions have, we should not be in the position we are in now. That is fully acknowledged.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Yes. In terms of lessons being learned, if we are just going to repeat the process of having these kinds of vague contracts that can be changed by companies that are just interested in maximising their own profit, we are going to repeat this experience again. Are there no lessons to be learned in terms of the type of contract signed?

Mr. Paul Hendrick:

There absolutely are lessons to be learned and there is-----

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Are there lessons about the contract?

Mr. Paul Hendrick:

I do not see anything materially wrong with the contract itself. Going forward, I think we need to consider the process. The textbook would always say that you would do an open tendering process for major engineering and construction projects and go out and seek tenders from the open market. Those who can comply with the client requirements that have been put together would then have the ability to get into the evaluation process. If they succeed in the evaluation process, they win and you appoint them. That would be standard.

However, that is not always the right way to deliver a major engineering and construction project. An open tender process can sometimes lead to the potential issues we have experienced. A direct award approach or a direct discussion with a particular supplier who has a specific product that meets the needs of the business could be used. That is usually seen, however, as not being the default way to run a public procurement process for a major engineering project. We can definitely take on board lessons around the process. I would say that the contract, and how it was structured, was not an unusual one. I do not think there are any major-----

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Is Irish Rail going to attempt to get back any of the €31 million we have given to Indra? Is there any prospect of that happening?

Ms Mary Considine:

I know I am repeating what I said in my opening statement, but we are at a sensitive stage and looking at all options under legal advice. We will, however, be looking at everything to minimise the exposure for the taxpayer.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Indra has another contract, an integrated ticketing contract with the NTA. In its opening statement, the NTA said that the contracting mechanism is different from that for the NTCC contract, with payment due only following the successful delivery of each of 34 key milestones. Does that mean that the payment for this contract was not contingent on the delivery of key milestones?

Mr. Paul Hendrick:

The contract we have is called a new engineering contract, NEC, target cost contract, which is quite a common contract used on major engineering projects in Ireland, the UK and the rest of Europe. It is also used for other contracts in the public transport sphere, including other schemes the NTA would oversee. The nature of this contract is such that it effectively shares any pain and gain up to a point. In other words, if a project is finished below the target price, the gain is shared between the contractor and the client, and if the project overruns against the target price, there is pain sharing, up to a cap, after which the supplier takes all the pain. It is also a contract that gives full visibility to the client team in terms of the actual resources and costs being incurred on the project. Effectively, interim progress payments are paid against those fully transparent costs.

We did, through commercial reset number two, as the Deputy might have seen in the statement, at the end of 2024, introduce additional performance milestones given our concerns. We actually had a bit of a hybrid contract at the end, where we had a combination of approaches. We did have a milestone approach in the end but, unfortunately, that milestone approach has not succeeded, obviously, in terms of how it turned out.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

When we look at this, the number of private companies involved in it is quite something. A private company, Ricardo, is designing the contract. There is Turas, Indra obviously, and then this engineering company is brought in to look at it. Will Mr. Hendrick list all the private companies involved in this contract in one way or another?

Mr. Paul Hendrick:

It is worth saying that in the context of the major projects we deliver, we have inside Iarnród Éireann a train operations business, which is pretty much a directly employed staff model, an infrastructure engineering business that manages the steady-state infrastructure and a mechanical rolling stock business that manages all the train fleets in terms of maintenance. Those are predominantly directly employed models where there are Irish Rail payroll staff. For major projects, though, and we must consider the cyclical nature of these, we did have a capital investments unit back in the 2000s. When the recession hit, that unit was closed. No capital was available.

We re-established the capital investments unit as a business in late 2018 as we were coming out of the austerity era. We have 200 staff on our books who work in that business, dedicated to developing and delivering major capital infrastructure projects. When the projects go to the delivery phase, we are much more market-facing, so we are reliant on the support of the supply chain in terms of the major contractors and professional advisers. We do not have the funding to be able to guarantee directly employing that level of staff because we are only funded on an annual basis. Each year, our funding could drop. We cannot guarantee that we will have any work for them.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

Is this not the consequence of the hollowed-out neoliberal state, where everything is outsourced? Irish Rail is relying on one company to develop a contract and another company to fulfil it. The end result is that the public pays the price. Would it not be better value for money if Irish Rail actually had the appropriate staff to be able to do some of this management and so on?

Mr. Paul Hendrick:

It is a balancing act. We have to try to strike a balance. This is a particularly niche project for the railway. It is a very complex project. The type of skill sets and people we need are not commonly available. Therefore, this type of project results in having to lean in more towards bringing in specialists temporarily because we could not guarantee that level of work for a niche, specialist project.

Photo of Paul MurphyPaul Murphy (Dublin South West, Solidarity)
Link to this: Individually | In context | Oireachtas source

I thank Mr. Hendrick.

Photo of Joanna ByrneJoanna Byrne (Louth, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I thank all the witnesses for joining us. I will stay with the procurement process for the moment. We have established that the board of Iarnród Éireann was responsible for awarding the contract after the procurement process. On the issue of due diligence, Iarnród Éireann's statement highlighted that Indra's system integration plan referenced a 15-year history of 21 successful deployments, which is understandable.

Iarnród Éireann sought specialist advice from Ricardo Rail before proceeding to contract stage. Am I right on that? Did Ricardo Rail do due diligence with regard to the delivery of projects that Indra claimed to have completed in other countries? Did Iarnród Éireann do that? Who was responsible for due diligence and for the reassurances that Indra was capable of doing what it had tendered for?

Mr. Paul Hendrick:

The team that worked on the project right through from development to delivery was a hybrid team. There was Irish Rail staff on the team, supported or augmented by the specialist providers with expertise from Ricardo Rail. As part of the procurement process starting in 2015, they went through a market research stage to understand what suppliers were out there and what type of products and technologies were available on the market before putting the requirements together. That also involved an interested candidate who could potentially deliver the work coming to meet Irish Rail before the formal procurement process started, where it could engage in one-on-one discussions to understand what was possible. The market consultation was done once the process was started to look at the requirements and how we had set up the contract in order to make sure we got the right structure for delivering the project.

Photo of Joanna ByrneJoanna Byrne (Louth, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

There is a 15-year documented history that led to Indra winning the tender. It was awarded the contract in 2020. Shortly afterwards, in 2021, concerns were raised and difficulties arose with regard to commitments it was not able to fulfil in Lithuania. That is a short period, despite its supposedly long-standing history of being able to deliver. That is what I am trying to get at. Was the due diligence sufficient or were there downfalls in that regard? If there were, whose feet did they fall at?

Mr. Paul Hendrick:

Ultimately, Iarnród Éireann is responsible for the procurement, management and delivery of the project, irrespective of the support we have from the supply chain.

Photo of Joanna ByrneJoanna Byrne (Louth, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Coming back to 2021, concerns were noticed at that stage. Iarnród Éireann was reassured in 2021 that the generic product would still be delivered, and it was not. Why did it take Iarnród Éireann until 2025 to raise concerns with the NTA and say it did not have confidence in the project being delivered?

Mr. Paul Hendrick:

If we go through the whole project, there was regular interaction between Iarnród Éireann and NTA all the way through. There were monthly interactions. There were progress challenges on the project in 2022 and we put together the first commercial reset of the contract. That was done in conjunction with the NTA. As it is the approving authority, we do not make any of those arrangements without its approval. It has the right to reject any proposals and to support us if it thinks the proposal makes sense. We engaged with the NTA throughout the contract. On commercial reset number 1, where we extended the completion timeline by five months, we did it with the support of the NTA.

When we went through the delivery phase during 2023, the hardware was installed in the NTCC building, which was a positive progress milestone for Indra. It eventually completed the generic product, which its project was reliant on, in late 2023. That was another positive progress sign. However, the detailed software development, which only became visible to the project team in early 2024, is where we heard serious alarm bells as a project team. At that point, we escalated those concerns to the NTA to flag that we had done reset number 1, were four years into the project and had serious concerns about whether Indra would be able to successfully complete the project. We started that discussion in summer 2024, and then again in 2025.

Photo of Joanna ByrneJoanna Byrne (Louth, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

On a separate point, Spain's supreme court in May of this year upheld a €13.5 million fine against Indra for participating in a price-fixing and market-sharing cartel. This dates from an original judgment in 2023. Was Iarnród Éireann aware of that throughout 2023 to 2026?

Mr. Paul Hendrick:

I am not sure.

Photo of Joanna ByrneJoanna Byrne (Louth, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

We are looking at a loss of tens of millions in Irish taxpayers' money to a company that engaged in cartel-like behaviour because of a decision made by Iarnród Éireann and insufficient due diligence as to the company's capability to deliver a project. What does Mr. Hendrick say to the Irish people in that regard?

Mr. Paul Hendrick:

I cannot comment on the particular case. I am genuinely not familiar with it or au fait with it. Indra is an organisation with a turnover of €5 billion-plus and it is successfully delivering projects across the globe in many sectors. We went through a clear, comprehensive procurement process, as we do on all our projects. Indra was the legitimate successful applicant. We deeply regret how this project has panned out with Indra. This was not what we expected. I have 25 years of major infrastructure project experience. This is unprecedented. Every project has problems and challenges - every single project I have worked on - but you work through it and overcome it, and deliver on time and in budget. Sometimes it goes slightly over, but you always get the project delivered eventually.

Looking back on the last 25 or 30 years, Irish Rail does a lot of major engineering construction-type contracts, given the nature of the railway. We cannot point to another example of this occurring in Iarnród Éireann. I cannot point to another example of this in my career dealing with major projects. That is not to excuse it, but it is really unprecedented. We are genuinely surprised given the capability of the organisation, delivering a project probably worth €5 million per annum to it when it is turning over €5 billion per annum and has tens of thousands of people working across the globe. We were sure this would not be a problem for it and that it would eventually overcome the issues that arose. That was our expectation. Was that reasonable based on the evidence at the time? We thought it was. Our experience has led us to a different position now.

Photo of Joanna ByrneJoanna Byrne (Louth, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

On a more positive and parochial note, and picking up on Mr. Hendrick's line about getting there eventually, I will move on to my home town of Drogheda. It is the largest town and next emerging city in Ireland. When the NTA was with us in January, I asked about the possibility of a north Drogheda train station. I understand it falls outside the greater Dublin area and was not an issue for the NTA, but it would be remiss of me not to use the opportunity of having Irish Rail here with us. Ms Considine has said she is open to the possibility of a train station on the north side of Drogheda. Is there any light at the end of the tunnel with regard to securing that? Louth County Council has just been awarded funding for phase 3 of the port access-northern cross route, which unlocks the land that was a barrier in moving towards that. What concerns me is that a developer is seeking planning permission, which has been refused in recent weeks by Louth County Council. It was deemed an incomplete application. He is seeking to develop on land that has been earmarked, going back 20 or 25 years, for a train station. It includes land owned by Irish Rail. Concern is growing among elected officials in Drogheda, past and present, and the people of Drogheda, who are seeing a huge population burst with all the development going on. Commuters in Drogheda are getting increasingly frustrated by the lack of parking and their inability to utilise facilities on the south side of town around MacBride railway station.

Ms Mary Considine:

To start on a positive note, the first fleet order will be coming into service on the new DART+. We have the charging station in Drogheda, and the new Enterprise fleet to serve Drogheda is also on order. There are many positive things happening for commuters in the area. I hear the Deputy's concerns about infrastructure. I have had discussions with Louth County Council around the new north Drogheda station. We are hearing about parking and a study completed earlier this year points to that.

To the Deputy's question on the station and parking, both of those are subject to funding. There is a constrained pot of funding. One of the discussions I had with the CEO was about whether there were other ways, such as through development levies, of funding the station.

At the moment, we do not have the funding allocated for that. It is something that will be kept under continuous review by us and the NTA, as the funding authority.

Photo of Joanna ByrneJoanna Byrne (Louth, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Is that the main barrier? I am sorry, Chair, I understand I am over time. Is that the main barrier at the moment? There is consensus and a will for a train station in the north of Drogheda. That is what I am picking up. Without committing the witnesses to anything, is funding the main barrier?

Ms Mary Considine:

There are funding constraints. We will always look at what is possible.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

It is good to see some of the witnesses again. I hope the feeling is mutual.

Ms Anne Shaw:

Always.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

I would say that is the case. This is a "Yes" or "No" question. Was this the first project in Ireland in which Indra was involved?

Mr. Hugh Creegan:

No.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

What were the other projects in which it was involved?

Mr. Hugh Creegan:

It was involved with the Dublin Port tunnel when it was being built. Indra put in the control system for that tunnel. It has also been involved with some toll schemes around the country.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Have the projects in which it has been involved in Ireland always been successful and delivered on time and on budget?

Mr. Hugh Creegan:

It is going back over 20 years. I have no knowledge that it has not, if I could answer in that way.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Is Indra the main contractor for the next generation ticketing? It is. How can the public have any faith that Indra is going to do this successfully? I know that the witnesses will point to 15 years of success and why Indra was appointed for this project in particular. I ask the witnesses to be brief. How can the public have any faith that Indra will successfully do next generation ticketing? That is not even getting into the issue of next generation ticketing itself. How can the public have any faith that it will be delivered on time and on budget with this private company?

Ms Anne Shaw:

Currently, the next generation ticketing project is being delivered on time and on budget.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

It is currently.

Ms Anne Shaw:

Key milestones are being achieved.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

That is not the case in Cork, but-----

Ms Anne Shaw:

That gives us some confidence.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

It is not being delivered in Cork right now.

Ms Anne Shaw:

The scope of the project does not yet include Cork.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

It definitely does not.

Ms Anne Shaw:

Within the scope of the project that has been commissioned, Indra is delivering on time and on budget. It is fair to say that prior to engaging any contractor or vendor to deliver this system, there was quite an extensive piece of work undertaken by the NTA, again with external expertise to provide us with that. There was a pre-mortem, if you like, of all the things that needed to be covered off before we did the specification and went out to market, as well as all the market engagement. Again,-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Ms Shaw has full confidence that Indra will deliver next generation ticketing across the country.

Ms Anne Shaw:

Given the current performance, the positive collaboration between the teams and how it is being managed within the NTA and the governance and oversight that exists-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Has this project given Ms Shaw, as the person in charge of the NTA, any questions as to whether Indra will definitely deliver? Can she see herself coming before the committee in a couple of years' time to speak about Indra not delivering next generation ticketing on time and on budget? I hope that will not be the case.

Ms Anne Shaw:

I hope not, too. Having reviewed where we are within this particular project, I have confidence in my own team and their expertise and the relationship they have with Indra, and the way that the contract is being managed and set up. This is a very different kind of system to rail, which has more complex considerations. That is why they are different contracts.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

I hope so, for the benefit of the public, who have suffered on a number of occasions. On Irish Rail, who is the one person who has accountability over this project? Is it one of the witnesses?

Ms Mary Considine:

Ultimately, as an executive team, we have accountability. We report to a board of directors who ultimately make decisions.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

How many are on the executive team?

Ms Mary Considine:

Today, there are 11.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Are all 11 taking responsibility? Does one particular individual on the executive team that was over this project now take accountability for it?

Ms Mary Considine:

There would have been a number of changes to the team since the project was initiated and-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Is there someone on the executive team right now who was also on the executive team when it was initiated? How many?

Ms Mary Considine:

Not from a capital investment perspective, no. There has been a change at director level.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Who took over the running of this project?

Ms Mary Considine:

Mr. Hendrick's area would have taken over the running of the project.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

How many people are working in Mr. Hendrick's area?

Mr. Paul Hendrick:

We have 200 staff across the whole portfolio of projects, including DART+, the Cork area commuter rail programme, Ceannt Station and other projects. There is a project team from Irish Rail that was managing this particular project.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

How many are on that team?

Mr. Paul Hendrick:

There are probably five or six staff and they are supported by external-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

What consequences have those staff members faced?

Mr. Paul Hendrick:

They are still working through the project and managing the issues.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

What consequences have they faced for the loss of €50 million? Is the answer "None"?

Mr. Paul Hendrick:

I am meaning to go back through the process here.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

I am asking a simple question. What consequences did those people face?

Mr. Paul Hendrick:

For Indra's lack of a development of a product-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

For their accountability over this project and their lack of governance of the project.

Mr. Paul Hendrick:

I do not think-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

For the loss of €50 million from the taxpayer. What consequences have those people faced? Have there been any consequences in terms of their job specification or pay, for example? I am not necessarily saying that money should be taken from them in any way, shape or form. What consequences have those people faced? The reason I ask is that if I were working in a private company, which those people are not, and lost €50 million, I would probably be sacked.

Ms Mary Considine:

I will come in. Ultimately, if somebody was found to have done something wrong, we would be taking action. The reality is that our team have, through their best endeavours, done everything to support this project. They have leant in. They have tried to make up the gaps, but fundamentally, when you strip it all back, we have a contractor that has an underdeveloped project and it has not delivered for us.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Understandably-----

Ms Mary Considine:

That is really disappointing.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Understandably, there are a lot of questions to be asked of the contractor. There were five or six individuals within Irish Rail who had accountability over this project. As well as the contractor, those individuals failed to deliver it. They ultimately lost €50 million of taxpayers' money and are now facing absolutely no consequences. They can walk away from this thinking that despite losing €50 million for the taxpayer, they do not have to face any consequences. They have faced no consequences. I am not saying they will, but what if they go again and lose another €50 million for the taxpayer? They would again face no consequences. Do the witnesses take my point on board? Do they agree with my point that if I were working for a private company and lost €50 million, I could be sacked or demoted? Those are just two options. Do the witnesses accept that, "Yes" or "No"?

Ms Mary Considine:

I-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

I am asking for a "Yes" or a "No".

Ms Mary Considine:

I understand what the Deputy is saying. The project team worked on a project that delivered a building that was brought in on time and on budget, and all the other elements.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

I am not necessarily saying that the project team did not work hard, but they failed.

Ms Mary Considine:

I would-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

In terms of the €50 million, they failed. It is a "Yes" or "No" question. Does Ms Considine believe that if those five or six people were working for a private company they would have faced consequences?

Ms Mary Considine:

If they had not done their jobs, had not reported and had not put the appropriate governance in place, there would have been consequences.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

They obviously did not put the appropriate governance-----

Ms Mary Considine:

They flagged and reported-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

They obviously did not put the appropriate governance in place because they lost €50 million for the taxpayer. They did not lose the money to themselves. They obviously could not care less. The taxpayer lost €50 million. What consequences did those people face? Does Ms Considine accept that those people who were over this project face absolutely no consequence now for losing €50 million? That is a "Yes" or "No" question.

Ms Mary Considine:

I do not accept that they face no consequences. I think-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

So what consequences-----

Ms Mary Considine:

-----they are very disappointed and-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

What consequences-----

Ms Mary Considine:

-----regret the decision.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Ms Considine does not accept that they did not face any consequences. That is fine and good. What consequences did they face?

Ms Mary Considine:

They are working hard to try to resolve this issue.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

There is no disputing the fact that they are working hard. I am not saying they are not. They are probably five or six very competent individuals. I do not know them. What consequences do those people face right now? I will reiterate the point. If I were working in a private company and lost €50 million for the owner of that private company, I am sure that I would be demoted, sacked, subject to a loss of pay or whatever else. What consequences do those people face? Is the answer "None"? Do they ultimately face no consequences?

Ms Mary Considine:

Well----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

They will not be demoted. They will not lose out on any pay. They will walk away at 5 p.m. or 6 p.m. I am not disputing that they work hard, but they ultimately face no consequences. We can see it from the Irish taxpayers' point of view. Ms Considine is an Irish taxpayer. All around this room are representatives of the Irish taxpayers. They are watching today and hearing that five or six individuals lost €50 million of their money and ultimately will face no consequences at all. They will not be demoted. They will not lose any pay. They obviously will not be sacked. They will ultimately face no consequences. What stops them and Irish Rail as a whole from doing something along these lines again in the future, with a lack of governance and accountability and whatever else, and facing no consequences again because they did not face any consequences for the loss of €50 million? There is nothing to stop that.

We have a systemic issue right across the State. I am not necessarily saying it is an issue that is limited to Irish Rail, but it also affects Irish Rail. A significant number of people across the State are working for the State and face absolutely zero consequences for the lack of delivery of projects or failure in respect of the spending of public money.

The witnesses spoke to Deputy Murphy in particular about lessons learned. Will the NTA and Irish Rail identify one decision that should have been taken six months before this was brought to the board's attention?

Ms Anne Shaw:

We have an independent review that is ongoing and it will report in September. It will look at all of the governance and key decision points taken throughout, from the beginning of pre-procurement to where we find ourselves today.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

It is ad hoc right now, knowing the project and the delivery of-----

Ms Anne Shaw:

Hindsight is something-----

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Yes, hindsight. We have heard about hindsight loads of times.

Ms Anne Shaw:

With the information available and the expertise provided to the NTA and Irish Rail in making the decisions that have been made in the past, those were felt to be the right decisions in order to successfully deliver the traffic management system as well as, as Ms Considine has said, to reduce the cost exposure to the public purse.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

Very briefly, what is the relationship between the NTA and Irish Rail now? How good is it? Does the NTA ask Irish Rail what it is doing?

Ms Anne Shaw:

We are both agencies of the State. We work collaboratively together on a large number of projects.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

The must be some sort of anger among staff members of the NTA, saying Irish Rail messed this up.

Ms Anne Shaw:

Where things go wrong, we need to support each other to make sure we can successfully conclude and put things right, and that is the relationship we have. We continue to work together to deliver all of the other projects we are involved in together and to make sure we still deliver a traffic management system for the railway network and do it positively with both teams.

Photo of Eoghan KennyEoghan Kenny (Cork North-Central, Labour)
Link to this: Individually | In context | Oireachtas source

As a Mallow man, I can say the Cork commuter rail line is going very well, so I thank the witnesses. Well done.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

As Mr. Hendrick has said, sometimes things go wrong on projects and it is about how we deal with them. For me, looking at Irish Rail and the NTA, the question is how both continued to support, approve, fund and defend a failing project for years after serious warning signs emerged. Not only that, and the witnesses might clarify the figure for me, but it looks as though as much, if not more, was spent on project support as there was paid and committed to Indra. That is a serious red flag and should have been picked up well before now. Ms Considine might tell me how much we have paid in project support to prop up this fiasco.

Ms Mary Considine:

In total, I believe it is €28 million or €29 million.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Is Ms Considine sure it is €29 million?

Ms Mary Considine:

Third-party costs and project support amount to €29 million.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

What about Irish Rail's internal costs?

Ms Mary Considine:

They are about €2.6 million.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

We are over €30 million, which is a similar amount to what we paid to Indra. In terms of looking at the NTA, there is a serious oversight failure here. Irish Rail warned the NTA repeatedly, the NTA approved multiple resets, a commercial reset, budgeting increases and continuation after confidence collapsed. The NTA explicitly resisted a development of plan B last year. The NTA took a hands-on role from mid-2025. That is not oversight; it is being complicit in this whole fiasco.

I want to look at the correspondence sent to us in April. The NTA sent us correspondence in April and attached board minutes of Irish Rail. The tone of the correspondence the NTA sent to us is of a project that is delayed but progressing through testing and that has future delivery phases. Yet, the Iarnród Éireann board minutes of February, several weeks earlier, record significant concerns about the contractor's ability to deliver the programme and note that the CP1 project is only a small portion of the scope and that Irish Rail directors were deeply concerned. My question to the NTA is to ask why the picture was painted to the Committee of Public Accounts that this was a project progressing. More importantly, was it trying to paint the same picture to the major project governance and oversight group as it was to the committee or was it actually conveying Irish Rail's concerns to the oversight group?

Ms Anne Shaw:

To answer the first question, I do not think we have been painting a rosy picture. We have been working on a number of key decision points with Irish Rail with, as we have already mentioned, expert advice about the different resets that have happened over the lifetime of this project. With the information available at the time, I think those were considered to be the right decisions to move forward, with the ultimate aim of delivering the traffic management system for the railway network.

The reports we gave to the committee in April were about the reset to look at CP1. CP1 was progressing well at that time. We worked with Irish Rail and Indra in terms of that.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Just to note, the Irish Rail board of directors was deeply concerned and Ms Shaw is saying it was progressing well. Just to note, there is a serious difference there.

Ms Anne Shaw:

We got an agreed approach in terms of what we were doing with the reset that had been done and to move forward with just CP1 and the Rosslare section of the network. That was progressing to plan and was being reported on that basis.

Just to say in terms of MPGOG, there were a number of occasions when we attended MPGOG and Irish Rail also came and gave a deep dive on the projects. MPGOG also has independent expertise that understands railway systems sitting on it. There are six independent experts on that governance and oversight group. Lots of questions are asked and there are lots of discussions, including about confidence in delivery. I do not think we have been painting a rosy picture-----

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I certainly feel the NTA was painting a picture to the Committee of Public Accounts that was different from the picture that Irish Rail was expressing.

Ms Anne Shaw:

At that point in time when we came before the committee in April, that particular CP1 element, because that was what all the information was based on, was progressing-----

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am talking about correspondence in April. It was very different in tone from what the Irish Rail board minutes were saying. I have serious issues with that and I hope Ms Shaw can confirm to me that MPGOG was fully aware of Irish Rail's concerns and did not just have the picture the NTA was painting to us. It is important.

Mr. Tomás Campbell:

I will come in on MPGOG. It is worth noting that we have been very concerned about this project for a number of years and we have been kept informed on the issues. From an MPGOG perspective, at the time period in question we all knew that April would be a key milestone with delivery of the software. When the NTA was reporting into MPGOG we all knew that once the software was seen, CP1 would be viable from the timelines indicated. In the most recent meetings of MPGOG, in May and June, we had extensive discussions about how the software testing was going and the next steps. It is really important for the Department that we get the project onto a sustainable footing and go forward on the best possible basis. For MPGOG itself, we also have a mechanism in place to report to the Minister each quarter. The Minister and the management board have been kept informed of these issues. I do not think it is fair to say the NTA-----

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

So everyone knew this was a failing project and no one stepped in to resolve it. Is that what Mr. Campbell is saying?

Mr. Tomás Campbell:

I think that what MPGOG wanted to see was that Iarnród Éireann and the NTA were taking the expected steps and I believe they were. When the re-baselined programme was agreed in November 2024 it made the project more deliverable for Indra. Everyone agreed it would be easier to deliver CP1, acknowledging it was a relatively small commissioning for use.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I do not accept that. We are spending as much in project support to prop up a failed project and a contractor that was failing repeatedly to deliver. Everyone from the NTA to the Department was fine with that. It is not acceptable and it is not good enough. The taxpayer is rightly annoyed.

My next question is on the correspondence between the NTA and Irish Rail this week. I noted an article in The Irish Times today that seems to indicate the NTA is pointing fingers at Irish Rail and that it is saying this is its financial problem and if it wants to terminate the contract, it should do it but it will have to pay the consequences. Is that the position? How will that affect major projects and services?

Ms Anne Shaw:

I do not think that is a correct assumption from what Deputy Boland has read in The Irish Times today.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Ms Shaw might please share the letter with the committee after the meeting.

Ms Anne Shaw:

We will try but with the caveat that if there are any commercial sensitivities-----

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

They can be redacted.

Ms Anne Shaw:

We will try to get it to the committee. In terms of answering the question, we have considered the decision of the Irish Rail board. When we met the Oireachtas joint committee a couple of weeks ago, we said we would expeditiously deal with the matter so as to make sure things can be taken forward as swiftly as possible in the interests of the Irish taxpayer as well. We need to assess the consequences of these discussions and the continued delivery of the traffic management system. We still need to make sure we deliver the traffic management system for the railway for existing and new services planned over the investment programme. We need to consider what the financial impact requirement is and look across the wider programme to make sure we can continue to deliver that as well.

It will be a case of rephasing and reprioritising certain things over that period of time but ultimately to make sure that we deliver that.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Given that Irish Rail raised concerns last year, and the NTA is now saying it is a decision for Irish Rail, why was Irish Rail not allowed terminate last year and explore plan B?

Ms Anne Shaw:

I think that at that time the Irish Rail board, having reviewed the information and the proposals, did not make that request. The agreement between the organisations and the board-----

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Does Ms Shaw mean that Irish Rail did not make the request in writing? Is Ms Shaw saying that it is just because Irish Rail did not make the request in writing, notwithstanding that it has been raising serious red flags to the NTA since 2023, and we are now suggesting that it terminates? I assume that it was agreed between the NTA and Irish Rail that it would not be put in writing.

Ms Anne Shaw:

There were discussions with various options about how this project could move forward. The decision of the Irish Rail board at that time was to move forward doing the Rosslare section and the CP1 section as well. With the information that is now available-----

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Was the phasing not agreed after Irish Rail suggested terminating?

Ms Anne Shaw:

Does Mr. Creegan want to come in here? There were discussions around the various options, and it was agreed by all parties, including the Irish Rail board, to move forward with the option that was progressed over last year.

Mr. Hugh Creegan:

The phasing proposal was developed in 2024 but what changes-----

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

After Irish Rail had suggested terminating.

Mr. Hugh Creegan:

It was after a discussion about the problems the project had and the options to deal with them. We then convened a tripartite meeting with ourselves, Indra and Irish Rail to go through the options. Out of that, Indra was required to produce a remedial plan, and it did produce a plan shortly after that. It looked a credible plan, and on that basis, we moved forward at that time. In 2025, because I think the Deputy mentioned it, we focused activity on the first phase called CP1, which she is aware of.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

How much has it cost us since 2024 to continue with this failed project? If we had terminated it two years ago or even last year, how much would we have saved?

Mr. Paul Hendrick:

Since the summer of 2025, we have probably incurred an expenditure of close to €10 million. I will have to come back to the Deputy to confirm that.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Is that with Indra, all external factors and Irish Rail's costs?

Mr. Paul Hendrick:

That is the total project cost and a lot of that would be in the assessment and in the financial statements in the write down.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

I thank the witnesses for being here and for their continued presence. It is clearly a project that has gone horribly wrong for both Irish Rail and the NTA but, ultimately, for the taxpayer as well. I was struck to hear from the NTA that it has commissioned an independent review of this project, to look at issues of governance, delivery and project oversight. Do the witnesses agree with me that commissioning an independent review is an offensive waste of public money? I would argue that Ms Shaw and her organisation are fully aware of what has gone wrong here. Ms Considine and her organisation are fully aware of what has gone wrong here, and Mr. Campbell and the Department are fully aware of what has gone wrong here. Given the prevalence of private involvement and consultancy, or whatever we want to call it, misguide advice, throughout, why do we need a third party to bring together all of this data that was shared with us today to tell us what has gone wrong? What is the budget for that independent review?

Mr. Hugh Creegan:

I think it is €226,000.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

Some €226,000, to do what? We know the flaws and problems. Mr. Hendrick has spoken about the lessons that need to be learned. Other than to try to assuage the very taxpayer that has been robbed of this service and of this money, this makes no sense. Who is doing that review?

Ms Anne Shaw:

EY is doing the review but I think it is important to have an independent report, so that neither organisation can be accused of trying to put a different picture on the information.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

Who is paying for that report?

Ms Anne Shaw:

It is coming out of the NTA budget.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

How is it independent, if the NTA is paying for it? It is an absolute offensive waste of a quarter of a million euro. I ask the NTA to reconsider whether it is necessary. I do not think it is.

Ms Anne Shaw:

I still think the independent nature of the outputs and recommendations-----

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

It will not be independent. With respect Ms Shaw, there will be no independence.

Ms Anne Shaw:

-----will provide us with the lessons learned.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

It appears that Indra was provided with this contract for the delivery of the project, based on its core TMS project. That is how I understood the witnesses very welcome briefing documents. It was because it had a solid and flexible logic. That is what was quoted. Indra also advised the witnesses of a 15-year history of 21 successful deployments across a number of different countries. Are the witnesses aware of anybody in their organisations who met with colleagues from any of those 21 deployments to hear from them about their experiences of working with this service provider?

Ms Mary Considine:

I believe there have been discussion with Lithuania and other countries.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

Were they prior to the contract being awarded?

Ms Mary Considine:

I could not confirm that. I am not certain.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

We know what happened afterwards. I am curious about what due diligence was done before the contracts were signed. Was it simply the case that because of its size and scale we took Indra's word for it, or did we do our due diligence to make sure that we spoke to those who worked with this organisation before? From the perspective of the NTA, did anybody meet with any of those countries that signed these contracts with Indra prior to signing that agreement?

Ms Anne Shaw:

No, not that I am aware of.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

Is it industry standard for a tender brief to be 50% on cost and 50% on qualitative submission?

Mr. Paul Hendrick:

It depends on the type of project.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

Is it industry standard?

Mr. Paul Hendrick:

No, because sometimes it can be 30:70 in terms of cost and quality. It can be 70:30.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

Who made the determination that this was the appropriate ratio, 50% on cost and 50% on what has turned out to be a myth.

Mr. Paul Hendrick:

Iarnród Éireann; we would have as a business.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

What the rationale for that decision?

Mr. Paul Hendrick:

As part of the market research and market consultation process that we went through before we actually started the procurement competition, we would have taken on board how important it was to ensure that we did not make it a price sensitive decision. In other words, if it was 80% price and 20% quality, there was a risk then that somebody would have a weighted opportunity to win the bid with potentially a price that did not reflect the quality of what is needed. So, the quality of what we were going to get on this really complex project was really important and that would have had a bearing on trying to get the quality up as a strong factor in the evaluations such that-----

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

Iarnród Éireann could have gone 60% or 70% with the quality then. It could have done that.

Mr. Paul Hendrick:

Agreed.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

I do not know how it could have been a decent qualitative submission if it was a promise or a hope of delivery, not "This is what we do" because Iarnród Éireann was dependent on software that did not exist.

Mr. Paul Hendrick:

Going back ten years ago, a lot of the criteria would have been weighted towards price but given the scale and the complexity of the projects that we are facing, we have already moved going forward to a model that is along the lines of what the Deputy just mentioned there.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

Was Indra the cheapest bidder?

Mr. Paul Hendrick:

It was.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

By how much?

Mr. Paul Hendrick:

There was a maintenance price and a capital price on the bid. There was a capital price for the works, and then there was a maintenance proposal to support the maintenance of the asset when it was built but on the capital price it was probably about 50% cheaper than the losing bidder.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

It was 50% cheaper on the price, which was worth 50% of the award criteria, and in the qualitative submission it told Iarnród Éireann that it would deliver its own internal software, which was not ready but it would have it. We agreed to sign the contract based on that promise, alongside its track record with other countries on what it delivered before, but our service that we need was dependent on new software that it did not have at that time.

Mr. Paul Hendrick:

That is really good question but just to say that when Indra submitted its bid, going back to the promise, because that is what a contract is it is a promise to do versus a promise to pay, it offered us Da Vinci 2.0 in its bid submission. The way it worked-----

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

Indra did not have it to offer.

Mr. Paul Hendrick:

Let us say that Indra did have Da Vinci 2.0. I just want to say that when it put in its compliance matrix, it was obviously populating and self-declaring and that looks like it was marking its own homework but we reviewed that compliance matrix. It had to be substantiated. You could not just say, "Yes, we comply". You had to show evidence of how your solution could meet those particular requirements. We had that review done also by Ricardo, which had the subject matter expertise out there on other projects. It authenticated that the bid submission was a bona fide bid submission from Indra for Da Vinci 2.0. The problem was post-contract when Indra moved away from Da Vinci 2.0 because it was moving to 3.0. That is where-----

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

In simple terms, is that not a breach of contract? Indra changed the landscape.

Mr. Paul Hendrick:

It is difficult. We recognised the concern as a business but when we went through it, we were not able to identify a clear breach such that we would be able to lawfully stop the contract.

Remember that if you try to do something you are not entitled to do, the company can bring a challenge. The Deputy's question is very fair.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

Mr. Hendrick mentioned the word "slippage". I am not going to be pedantic, but slippage of 20 months on a four-year contract is more than slippage. At one point, he was notified that it would be that long. There was then a resettlement to the tune of €1.4 million. Was Indra paid €1.4 million in addition, even though it had delayed the project by 20 months? I seek a "Yes" or "No" answer.

Mr. Paul Hendrick:

We reset our target price by an additional €1.4 million. There were other issues it was arguing. It was making arguments against us at that time.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

I know it was looking for €2.3 million in the resettlement.

In the time I have left, will Ms Shaw rule out, or just for the record state, what impact, if any, this has on the delivery of MetroLink?

Ms Anne Shaw:

This will have no impact on the delivery of MetroLink.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

None.

With regard to the DART+ expansion and the projects that are really important, will Ms Considine state what impact the whole process will have on the delivery time of those services?

Ms Mary Considine:

We have been very focused on addressing that point. We have put obsolescence provisions in place, with the support of funding from the Department of Transport, to protect the train control system in the denser part of the network around the greater Dublin area and to future-proof for the DART+ expansion. What we want to do now is move to protect the rest of the network and support the other vital capital projects that are happening around the country.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

Can Ms Considine guarantee that there will be no delays to those programmes because of this?

Ms Mary Considine:

We can say that there will be no delay to DART+, and we are working to find solutions for the other parts of the country.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

If the interim measures in place were sufficient, we would not be in this mess in the first place. We are obviously in some form of limbo now where we need to find a long-term solution. Are there any health and safety risks associated with where this whole project stands now, as regards the current rail network but also the future expansion?

Ms Mary Considine:

To give assurance to the committee, the current technology, even though it is life-expired, is fail-safe technology. What that means is that something will stop running if there is an issue and we will have an outage like we had on 29 May that affects services. It is really unfortunate, but it will fail safe, so we will not be compromising safety. Safety is absolutely crucial. We will stop running services rather than compromise safety. We obviously do not want to stop running services either, so we need a solution here.

Photo of Aidan FarrellyAidan Farrelly (Kildare North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

I thank the witnesses.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I thank the witnesses for attending this morning. I do not want to rehash what has already been covered, but it really is difficult for an ordinary person, and I see myself as an ordinary person, to understand the contract situation. Reading through the submissions, I note that there were flags going up on this contract as early as 2020. If a multibillion euro corporation that was supposed to specialise in this area was failing to meet very basic requirements of a contract so early in its term, why were red flags not going up all over the place? Is there any answer to that?

Ms Mary Considine:

I will hand over to Mr. Hendrick because he will be able to go into more detail, but if the Deputy reviews the correspondence that we have put before the committee, he will see that red flags were being raised. Even in the first commercial resettlement, there were assurances given by Indra that it was addressing the issue. It never raised any issue with specifications, nor did it state it could not meet the criteria. It accepted and signed up to the rebasing of the contracts, and unfortunately it did not deliver. That led to Mr. Hendrick and his team flagging very serious concerns in early 2024.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

As early as 2024.

Ms Mary Considine:

Early, and there would have been-----

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

It is four years. I see that Indra used things like the pandemic to explain it. The pandemic has been blamed for everything. What I cannot understand is that, for four years, these flags were going up very early on in the term of the contract. Four years is a long time.

Ms Mary Considine:

Maybe Mr. Hendrick can talk about the measures that were put in place.

Mr. Paul Hendrick:

The concerns that were raised related to the DaVinci 2.0 platform that Indra was advising us about post contract. It had not advised at any time going into the contract that it was going to move from version 2.0 to version 3.0. It did cause a concern. Our team went through a due diligence process with the company to ask what this meant. It reassured Irish Rail by saying that this was the next generation of the product. It has a product development history. It states it has had versions 1.0 and 2.0 and is moving to 3.0 as a business. It stated that this would be the case for TMS applications that it was involved with in other jurisdictions, so it would not have version 2.0 in one place and version 3.0 in another. Rather, the aim was to roll it out consistently. The concerns we would have had were to make sure we would still get the offering promised with version 2.0 with version 3.0. They were the undertakings that Indra gave to the business, and we worked forward on that basis.

What happened from 2022 to 2024 was that we had programme concerns. "Slippages" is the word we have used but there were significant programme concerns. The movement from version 2.0 to 3.0 has turned into a whole new process for Indra as a business. It was developing the next version of the product "outside the project", as it is called. In other words, there was an activity it was engaging in as a business that the project it had committed to doing for us was dependent on.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

In 2020?

Mr. Paul Hendrick:

From 2020, yes.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Mr. Hendrick is now saying that, between 2022 and 2024, serious slippage happened, but we are talking now about two to four years.

Mr. Paul Hendrick:

Yes. It promised us that the product development process, which relates to what is called the generic product, as the Deputy might have seen in the note, would be finished. Indra guaranteed it would be finished in 2021, such that it would have no effect on the programme whatsoever. In the end, it took Indra until the end of 2023 to have the generic product process that it was engaging in as a corporate organisation outside the project completed. That was a driving factor and really delayed the project.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

It really feels like Indra gamed the contract. What is really interesting is that it was 50% less expensive than the next tenderer. Did that not raise concerns that it had lowballed the State on this contract? We have seen it in other big State infrastructure contracts, with lowballing and then coming back and back until the cost escalates or the contractor cannot meet the terms of the contract.

Mr. Paul Hendrick:

As part of the procurement evaluation process, we would carefully examine the commercial offerings of any bid to assess them from the point of view-----

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Fifty percent is a huge gap. If there is a gap of 10% or 15%, someone somewhere says the company should wait a minute. I do not want to ask who the other firms that tendered were. Mr. Hendrick probably cannot tell me that. Can he? Were they reputable corporations?

Mr. Paul Hendrick:

Yes.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

International?

Mr. Paul Hendrick:

Yes.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Okay. Fifty percent is just incredible. If a builder came in and said he could build something for 50% less, you would be expecting wet bags of concrete to be stuck in the wall. Someone would be cutting costs somewhere. It is incredible. It is just a reflection on things.

Consider the third-party advice to support Indra. Who did Irish Rail bring in to provide that third-party hand-holding advice to a multibillion-euro corporation that was supposed to deliver a huge infrastructure project? I saw in the note that Irish Rail brought in some external contractor to help it through some of its issues. Was that another contractor?

Mr. Paul Hendrick:

We had two organisations, called Ricardo Rail and Turas, which provided effectively temporary staff to help us manage the project, including technically. They were helping Irish Rail, I should say. They were working for-----

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Helping Irish Rail.

Mr. Paul Hendrick:

They were working for Irish Rail and helping Irish Rail.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Was anyone brought in to help Indra or advise it? Did Indra subcontract any work?

Mr. Paul Hendrick:

I am not sure, to be honest, exactly in what way Indra’s staff were contracted. It had a lot of people working for it, advising and doing the work for Indra directly.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Again, I do not want to rehash what has come before. The contract is with the NTA and Irish Rail delivers it. The advice is that there is going to be a review to decide on how to terminate this contract. Am I reading that correctly, or am I misinterpreting that?

Ms Anne Shaw:

The contract is between Irish Rail and Indra. Irish Rail will need to have conversations directly with Indra in terms of managing the next steps. The NTA will continue to work with Irish Rail to support any way forward.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The ticketing system contract is going to Indra. Again, for the benefit of the ordinary public, how are we to understand that a corporation that has not delivered on a project is being brought in to deliver another development for the NTA, namely, the next-generation ticketing system?

How does the NTA explain that to the public?

Ms Anne Shaw:

Again, there was a compliant procurement process where Indra was successful in that contract. As I mentioned earlier, there was a lot of pre-mortem, as it were, prior to developing the procurement strategy about all the things that needed to be included in the same way there was a review of all the different expertise globally, the different organisations that deliver against these projects. Indra has got that global presence in this particular field as well. It is very different technology to rail.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Is Ms Shaw confident it will deliver on that contract?

Ms Anne Shaw:

It is currently being delivered on time and on budget. All the milestones are being met. The teams are colocated and working successfully to deliver against those milestones.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Does the NTA’s external consultants who advised on the original contract, Ricardo, culpable here in any way? What happens if I get advice and it is deficient, and obviously its advice was deficient?

Mr. Paul Hendrick:

Well-----

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Maybe "deficient" is too strong a word. Let us say it has given the NTA advice, as a specialist company, which has turned out to be erroneous.

Mr. Paul Hendrick:

There will be the EY review which the NTA mentioned which will look at everything that has happened as a full look back. A lot of this happened before my time in the business. I am not here trying to defend anyone, to be clear; the facts are the facts and we will go through where all the real causes are. Based on the undertakings and representations that Indra made through the pre-call and the bid process, how Ricardo and the project team assessed it was not unreasonable based on the information they were given to review. That is just my opinion.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Therefore it comes back to Indra not delivering and undervaluing what was required and a whole range of things. Low-balling, I would say.

Finally to the NTA, the State will spend a lot of money on MetroLink. Does the NTA think it is capable of delivering MetroLink?

Ms Anne Shaw:

Obviously we are coming close to the next approval gate for MetroLink. There has been a lot of work to develop the project team and a lot of work to make sure we have the right design and systems in place as well. There have been thorough assessments around both the project execution and how that will be delivered. What is being delivered, all the costings, etc., are all in the process of being assured against that as well.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I have run out of time here and I do not want to take anyone else’s time. Ms Shaw could accept the public has, perhaps, had its confidence shaken in the NTA and Irish Rail in the management of this particular contract

Ms Anne Shaw:

Yes.

Photo of Martin DalyMartin Daly (Roscommon-Galway, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

That is all I can say. I cannot answer that. I thank the Cathaoirleach.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Before I let the next speaker in, the committee’s function here is to establish how public funds are managed. Members may refer to third parties insofar as it relates to decisions, the decisions and oversight of Irish Rail and the NTA, but the committee cannot make findings as regards the contractors’ liabilities.

Deputy Bennett is next.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I welcome the witnesses and thank them for coming in.

I have heard numerous dates and timelines for the national train control centre project, NTCC. When did the witnesses first became concerned about the NTCC?

Ms Mary Considine:

If you take the overall NTCC project itself, despite Covid and everything, the building was delivered within budget. That is quite a futuristic building that will centralise the entire control system but will also future-proof for Dublin City Council, and the gardaí are also in there. The building itself went to plan. In terms of the signalling, electrical and telecommunications elements of the project, a lot of that was delivered in conjunction with our own team, it went to plan and the hardware was installed. I know we are repeating ourselves, there were concerns about Indra and its performance from early on with the traffic management system, TMS.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

What was the first year?

Ms Mary Considine:

I would say late 2020 there were initial concerns.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

So that is 2020-2026 and it has only become public now at this stage really. In the last six months, would you say?

Mr. Paul Hendrick:

If I could go back, we did the first commercial reset No. 1 in late 2022. I came into my role in September-----

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Mr. Hendrick is saying 2022 then.

Mr. Paul Hendrick:

We had initial-----

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

This is why I am confused because everyone keeps mentioning different years and we are only finding out here in 2026.

Mr. Paul Hendrick:

There was a number of programme challenges at that point.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Okay. I am not worried about any of that. All I want to know is the first year it was highlighted. We are only hearing about it in here in 2026, so I want to know what has happened in the meantime. When did the Department find out, Mr. Campbell?

Mr. Tomás Campbell:

It predates my time on the project as well.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I am not asking that. I am asking what year did it come to the Department?

Mr. Tomás Campbell:

I think around 2022.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

In 2022.

Mr. Tomás Campbell:

There were concerns around the time-----

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

What happened in 2022? What response did the Department have to this problem at the time?

Mr. Tomás Campbell:

We had a deep dive on the project in November 2022. From the Department’s perspective, we wanted to assure ourselves that the NTA and Iarnród Éireann were managing the project as we would expect and also the implications for the wider rail transport programme and mitigations in place.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

In 2022, how much had been spent at that time?

Mr. Tomás Campbell:

I would handover to Iarnród Éireann.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Okay. Does Mr. Hendrick know that figure?

Mr. Paul Hendrick:

Can I come back to the Deputy on that to make sure I give the accurate figure?

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Okay. Did you seek any assistance from the Department at that stage, saying “We’re in trouble here”. Were we €50 million in trouble at that stage? Sorry, I am not getting any answers.

Mr. Paul Hendrick:

Apologies.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

At that stage, in 2022, was Irish Rail €50 million in trouble? Is that how far it was?

Mr. Paul Hendrick:

No.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

It was not. So why did the Department do anything at that stage? That is for Mr. Campbell.

Mr. Tomás Campbell:

The approving authority function was delegated to the NTA and that was in line with infrastructure guidelines. The Department would allocate the budget.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Did it come to the Department at that stage to say it was in trouble?

Mr. Tomás Campbell:

I do not believe at that time.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Before the State spent €50 million.

Mr. Tomás Campbell:

At that time I do not think any of us would have known it would escalate-----

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Nobody knew. I just find it incredible that one organisation, one State body after another, comes in here and nobody knows what is going on in the Department. Nobody seems to know.

Mr. Tomás Campbell:

We-----

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Do we not get reports back from every State body? The Government gives money to State bodies. I do not understand. There is no oversight in the Department where it is watching timeframes and timelines, where the money is being spent and how it is being spent. This is taxpayers’ money.

Mr. Tomás Campbell:

I accept that. We all deeply regret where we have got to but throughout that period NTA management of that programme was in line with what we would have expected.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

In line with what the Department expected but it was having problems in 2022 and there was nothing done about it. It is now 2026 and now the issues are just coming to us at the Committee of Public Accounts.

Mr. Tomás Campbell:

Throughout that period, MPGOG reported on a quarterly basis to the Minister and to the management board. The issues were being escalated. We were aware of them and we were very concerned.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

The Department was very concerned. It was not that concerned if it did not do anything for four years.

Mr. Tomás Campbell:

From an overall-----

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

From 2022 to 2026.

Mr. Tomás Campbell:

From an overall rail portfolio perspective, we were assured that there were mitigations in place for, say, the Galway Ceannt Station, for Waterford North Quays project and for the Foynes line, that the contagion of the wider programme was being managed.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Okay. I am just trying to think for the future, how do we avoid something like this ever happening again where something is highlighted to the Department in 2022 and nothing is done until 2026 and now the State is €50 million worse off? That is money that could have been spent on the MetroLink or other things but it has not been because the State has lost that money.

Am I correct that we are also paying Indra to run the next-generation ticketing system?

Ms Anne Shaw:

That is correct.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

The NTA must have great confidence in it that it actually managed to procure another contract from the State.

Ms Anne Shaw:

As I already mentioned, that project is being run well. It is currently on target, on budget-----

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

On target, on budget.

Ms Anne Shaw:

-----with all milestones being met.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

On target and on budget. Contactless payment was introduced to Ireland in 2011. That is the same year as the Leap cards. Why were Leap cards introduced but we were not using contactless payment. In New York, London and everywhere else in the world, they are using contactless payment. What is so great about this new-generation ticketing system? How much are we paying Indra for that system?

Ms Anne Shaw:

The next-generation ticketing will also incorporate the current Leap system to enable that to continue as we transition to fully contactless payment.

Contactless payment will, with an account-based system, allow people to pay for their transport after the fact, and after the system has worked out how transport has been used and get the best price whether people use their phone, bank card or watch.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

What is so good about this new ticketing system that could not have been used back in 2011 when other countries introduced contactless payment there and then? Why do we still not have a contactless payment system in Ireland 15 years later? The witnesses say it is going to be such a magnificent system.

Mr. Hugh Creegan:

Yes, the Deputy is right that the technology was introduced in 2011. It started a good many years before that. At that time, contactless payment by bank cards was a relatively new development. The key thing in London at that stage was the Oyster card. At the point that project started, it was the right decision made. It was introduced in 2011 and is now-----

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Why are we moving at a snail's pace?

Mr. Hugh Creegan:

The project we are on now is to produce the next generation of ticketing.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

It is 2026.

Mr. Hugh Creegan:

It is.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

This technology was introduced in London in 2011.

Mr. Hugh Creegan:

The Leap card has worked.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Fifteen years.

Mr. Hugh Creegan:

Yes, and the Leap card has worked very successfully over that intervening period with very many millions of journeys taken, but we have now reached the point of upgrading to the new system. That is what is under way with the current project.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Okay. I want to ask about the rail network. I have brought to the attention of a few committees the fact that there is no rail network in County Monaghan, which is where I live. Again, it is unbelievable that is the situation in this day and age. Back in the 1950s there was a railway running through Monaghan. I would like to have an update on that. What has happened? Have there been any further reviews? It has come to my attention that there will be a rail service between Portadown and Clones at some stage. Maybe we could have an update on that if there is something coming down the tracks.

Mr. Tomás Campbell:

I can come in on that one.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Yes.

Mr. Tomás Campbell:

The All-Island Strategic Rail Review was published in July 2024 in conjunction with the Department for Infrastructure in Northern Ireland. It was the first ever all-island rail plan. In that, there is, as the Deputy mentioned, a line proposed from Mullingar to Portadown. That is not being funded in the next five years. Under the national development plan, we have set aside €100 million in the next five years for a range of early interventions, which are foundational investments in the network that increase resilience and capacity in the network. In the 2030s, we will deliver a number of major projects and we are doing the preparatory work for that now. We developed a plan for those major projects in the 2030s with the support of the European Investment Bank and published a plan for that in December of last year.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I am delighted to see that you are coming up with plan for a united Ireland and we are in preparation for that. That is good news.

We have a bus station in Monaghan town that really needs to be developed and upgraded. Planning permission was in place for that but the building never actually happened. That bus station is closed to the public at night-time, even though buses run through Monaghan at night-time. Can anybody give me an update on that?

Mr. Hugh Creegan:

The bus stations around the country are owned by Bus Éireann-CIÉ, and because they are not all running PSO services only and a lot of the stations run a commercial service, the Expressway service, we are limited in what we can do to fund upgrades. I do not know where an upgrade is for the Monaghan station. I do know that, because of state-aid issues, we are limited in what we are able to do.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Does Mr. Creegan not find it concerning that so much money from the transport authority seems to go to Dublin? Why are we not concerned? Why do the witnesses not know about Monaghan? Is it not relevant that we in Monaghan do not have a rail network and our transport system is very behind the times in that we do not even have a bus going on the hour every hour to Dublin? There is a lot of work to be done there, and for rural counties. Not enough is being done, and I want to highlight that here today. The witnesses should make sure it is put high on the Department's agenda. Rural Ireland has been left behind again in terms of both rail and bus services.

Mr. Tomás Campbell:

To be fair to the National Transport Authority, most of the statutory limit is the greater Dublin area. Some of it is national. We currently have the Dublin Transport Authority (Amendment) Bill going through the Oireachtas. I think that had Committee Stage at the end of June. That will be enacted in the autumn and that will put the infrastructural delivery aspect of NTA's remit on a national basis, so that will give it more levers across the country.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Just one more thing-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Very briefly, Deputy.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Did the witnesses receive media training before attending here?

Mr. Tomás Campbell:

No.

Photo of Cathy BennettCathy Bennett (Cavan-Monaghan, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Nobody did. Thank you.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Thanks for that. We will take a short break.

Sitting suspended at 12.35 p.m. and resumed at 12.54 p.m.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I thank the witnesses for coming in. I want to get a bit granular regarding the €50 million write-off and the timeline involved. When was the first €4 million to €5 million of the €50 million spent?

Ms Mary Considine:

Obviously, there was spending from the outset with this project, even prior to the contract being awarded.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I want to get into the first steps of the process.

Ms Mary Considine:

We set out the financial details in the appendix. I will dig them out.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I just want to try and go through that. I think it is important to do so.

Ms Mary Considine:

If we look at appendix 1 of the financial briefing, which is attached to our document, we see that the initial spend happened in 2015.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Could Ms Considine read it out for those who do not have copies of the report? I just want to go through it.

Ms Mary Considine:

I apologise. Perhaps Mr. Hendrick could read it for me. The print is a bit small.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Not everyone will have access to the appendix. Could Ms Considine outline when the first €5 million was spent.

Ms Mary Considine:

I think it was 2015. I will just bring it up on screen because it will be easier to read. I apologise to the Deputy.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am just conscious of the time. Can we try to get the information?

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Perhaps Deputy Neville could move on to his next question.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

No, I want to go through it on a granularly.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

That is no problem.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Do we not know when the money was spent?

Ms Mary Considine:

We do. I am sorry. I am just trying to open the appendix.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am asking high-level questions here.

Ms Mary Considine:

Yes.

Mr. Paul Hendrick:

Could I answer in terms of the €50 million write-down against the-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

No, could Mr. Hendrick just do it in the way I am asking, please?

Mr. Paul Hendrick:

I am not sure that we have the information.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Do the witnesses not know when they spent the money? What I want to find out is when the money was spent. Some €2.5 million was spent, but we are still not sure when it was spent never to mind who spent it.

Ms Mary Considine:

At a high level, in relation to the spend, the impairment review looked at the carrying value of the asset-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

No, I genuinely do not want to do that.

Ms Mary Considine:

Yes, okay.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I only have 15 minutes. Do we just not have a clue when it was spent?

Ms Mary Considine:

It was spent from 2015 onwards. Anything relating to the software element of the TMS project was prior to-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

But we do not know when elements of the €50 million were spent or when they were written off.

Ms Mary Considine:

We do. We just do not have it to hand.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

How was it assessed?

Mr. Paul Hendrick:

The €50 million write-down is predominantly based on us not having a developed product. When the board made the decision to do the impairment review-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I do not want to talk about the board and the impairment review. I am asking what checks and balances there were along the way when money was spent in order to ensure that we were getting value for money.

Mr. Paul Hendrick:

The decision on the write-down is what drives whether we assess whether there is an impairment or not. Throughout the project-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am an accountant, so I know how the impairment process works. I am talking about the process along the way. Are the witnesses telling me that they only looked at it at the very end to see if it was working?

Mr. Paul Hendrick:

Each year, we assessed it on the basis of the carrying value. Every expenditure we have on a capital project goes into our fixed assets, so we capitalise the cost.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Yes, the costs are capitalised. That is why this should be very easy. I know how that works. It should be very easy to say that amounts of €5 million here, €10 million there and €15 million there were capitalised. The asset will grow in value to a certain point, and then, obviously, the witnesses examined it at the very end and saw that it was worth nothing. Why did that happen? I want to know the steps as to how it happened and how it built up to €50 million. If we are saying that we do not know-----

Ms Mary Considine:

We do. I have it open in front of me.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

This is €50 million. This is really important. The information should be at the witnesses' fingertips.

Ms Mary Considine:

In 2013, there was a spend of just under €400,000.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I know. That is why my first question was about the first level of significant funding.

Ms Mary Considine:

Yes. The first level of funding was in 2013.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

When did it rise to €10 million, €15 million and €20 million? Why did someone not cry stop at €25 million?

Ms Mary Considine:

The first significant spend was in 2019. That would primarily have been on ICT and ICT enablement works.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

How much was that?

Ms Mary Considine:

That was €2.5 million out of a total €3.2 million.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

So €2.5 million was spent in 2019. What is the total value there?

Ms Mary Considine:

The total value at that point-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

How much of the €50 million was capitalised by 2019? This is very simple.

Ms Mary Considine:

In 2019, there was a total figure of €3.2 million capitalised.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Of the €50 million. In 2020, how much was capitalised?

Ms Mary Considine:

It was €6.1 million.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

So now we are up to €9 million. What was it in 2021?

Ms Mary Considine:

It was €7.3 million.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

So now we are up at €16 million. Keep going.

Ms Mary Considine:

Then we had a spend of €14 million in 2022 and a spend of €21.7 million in 2013.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

So by 2023 there was €20 million spent.

Ms Mary Considine:

Yes.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

How much was spent in 2024?

Ms Mary Considine:

In 2024, in total it was about €14 million.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

What about 2025?

Ms Mary Considine:

In 2025, it was €15 million.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

What about 2026?

Ms Mary Considine:

In 2026, to date it is about €3 million spent.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

So, we spent another €3 million on the project.

Ms Mary Considine:

To date, yes.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Is that of the €50 million?

Ms Mary Considine:

No, that is not included in the €50 million.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It is not related.

Ms Mary Considine:

No.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

When did the spending stop on the €50 million?

Ms Mary Considine:

The €50 million is the impairment figure at the end of 2025.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Was no money spent on the project in 2026?

Ms Mary Considine:

There was spend on servicing the contract, which was about €3 million, that has not been capitalised.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

There a further €3 million on that recurring-----

Ms Mary Considine:

Yes, recurring across the spend.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

There is a €3 million cost in 2026 was for a project that was written off in 2025.

Ms Mary Considine:

Yes.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The State has written off an asset but it is still incurring a €3 million cost every year on the same. Is that what Ms Considine is saying?

Ms Mary Considine:

We are incurring ongoing costs so long as we are still in contract with Indra.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

How long will this contract go on with Indra for a project we do not have?

Ms Mary Considine:

As I referred to in my opening statement, the board took a decision on 22 June based on the principles testing report that came to us on 16 June. We sought the approval of the NTA. They have written back to us confirming their consent to implement the board decision. We are in the legal process at the moment.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Going back to the audits at the end of 2024, when it was not written down, was there any impairment review done of the asset?

Mr. Paul Hendrick:

At the time it was carried at its carrying value-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I get that but was there an impairment review?

Mr. Paul Hendrick:

Can I finish?

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Okay.

Mr. Paul Hendrick:

The reason it was carried was because the prospects of it generating an economic asset was greater than 50% in accordance with the FRS 102 accounting standard.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

In fairness, how-----

Mr. Paul Hendrick:

If I can finish. What changed in early 2026 is that as we were developing the project with Indra, we got to the point where we could no longer convincingly demonstrate to the board of directors of Iarnród Éireann that there was a greater than 50% probability of this project delivering a useful economic asset. Once that fell below this-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I get that but-----

Mr. Paul Hendrick:

-----it triggered the impairment. What we then had to do was the impairment review based on financial statements for the end of 2025. The cumulative expenditure on the project since 2013 is €150 million, including VAT, because we have to carry VAT an a project with non-recoverable VAT. When we assess that €150 million, we then have to assess the writedown percentages. The way we did that was to look at the Indra contract and look at the software to make a decision on whether we could we carry and reuse any of that software if Indra were not the future supplier to finish this project. We made the decision that we could not and we had to write off 100% of the software cost with Indra. We also looked at hardware that Indra had installed and we were able to reuse a lot of that hardware so we carried some of the value through the hardware.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

How much is the value of the hardware?

Mr. Paul Hendrick:

The hardware is about €4 million and we were able to carry about 65% of that. If we look at the total, it is about €30 million and we were only able to carry about €2.5 million in total. We wrote off the majority of the money on the software, which was about €27 million or €28 million.

Ms Mary Considine:

It was €28.2 million.

Mr. Paul Hendrick:

The rest of the money then is hardware. We have been able to retain some value from the Indra contract purely because of the hardware we could reuse with a different supplier if-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

All along, the decision was made to carry out. Iarnród Éireann did the impairment review but obviously it did its own internal test on the 50%.

Mr. Paul Hendrick:

Yes.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I totally get that but was that same test done the previous year and were the witnesses happy to go along with it?

Mr. Paul Hendrick:

We did not have anything to trigger a review so we were happy to carry the value in the financial statements.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

So people were-----

Mr. Paul Hendrick:

We believed we were going to get an economic asset out of the project because we believed Indra at the end of 2024. We did a settlement agreement-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

What was the trigger whereby Iarnród Éireann knew it would not get it?

Mr. Paul Hendrick:

It was as we came through 2025 and we started to look at the testing, which was the second round of testing on CPU-1 and the results that were coming through. When we got the initial results, after we were given the software on 20 April, the board was trying to close the accounts. On 6 May we had a board meeting. I had to present to that board meeting and advise them of the outcome of the testing process, which was starting to fail.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I know but-----

Mr. Paul Hendrick:

If I could just finish up.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am under-----

Mr. Paul Hendrick:

On the basis of that failure it triggered the impairment review. We then had to go away and assess the quantum of what that writedown should be based on the situation we were in.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Was any more spent after that? Mr. Hendrick went to the board, which is a process, which I totally get. The board, however, does not run the company. As Mr. Hendrick will be aware, we all know the role of a board and what it does, but ultimately it is the CEO and CFO who actually know, or should know, what is happening on the ground. I want to take the board out of it. At what point was the previous CEO, made aware by Mr. Hendrick and the team that Iarnród Éireann had an impaired asset? When was the first time the question was raised? Was any more money spent on it after that?

Mr. Paul Hendrick:

We did not have an impaired asset at-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Potentially.

Mr. Paul Hendrick:

-----at the end of the accounts up to the end of 2024. From the end of 2025 when we were closing those accounts in early 2026-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

No. I am saying there was a question mark. There was not just a lightbulb moment when someone said, "We had better write off €50 million". Surely there was a concern somewhere.

Ms Mary Considine:

When we initially looked at approving the accounts at the end of March, there obviously was a real deep concern by the board and they questioned-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Was that this year?

Ms Mary Considine:

Yes, this year.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

When was it questioned first? That is what I am trying to get at.

Ms Mary Considine:

In reviewing the financial statements for 2025, they would have considered the carrying value of the asset. The decision was deferred until we could see whether the principles testing would succeed when on CPU-1, which was delivered on the 20 April.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Was that a year later?

Ms Mary Considine:

No, it was the same year, March this year. In April, the CPU-1 was delivered and on 6 May, there was concrete evidence at that stage that the testing was failing and the board made the decision to impair the asset.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

There was no concern up until there was a concern, and then Iarnród Éireann wrote it off within weeks. Is that right?

Ms Mary Considine:

I think there would have been flags and concerns all the way through, as we outlined in all our correspondence. We have been reporting to the committees, to our board and to the NTA. As we discussed earlier, there were two commercial resettlements, including a very significant one at the end of 2024. The teams were working through 2025 to deliver.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am finished my time. I think it is a big thing for the witnesses to say that all the way along there were concerns but at no point was it in the impairment review, potentially, and Iarnród Éireann just kept capitalising all the way through. Yet, Ms Considine is saying she had concerns. If there are concerns about the value of an asset, no accountant should continue to capitalise while there are concerns there. Ultimately, she has just said that this was the case.

Ms Mary Considine:

There were concerns with the delivery of the project.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

That should never have happened. The clock keeps ticking and money keeps going out the door. Now the State has a bigger bill to deal with than it had.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Deputy Neville was killed by his own analogy there. Let me try to sum up what we have listened to so far. Essentially, Irish Rail is saying that they thought they were buying a generic project and it has ended up being involved in a software development project. It was buying something it thought was reasonably off the shelf and in the end, it has been involved in a sort of speculative project where they Indra developed the software and at the end of it all, there is nothing to show for it.

Ms Mary Considine:

I cannot disagree with how the Deputy has summarised it. As we said, we believed we were buying 2.0 and it was then evolving to 3.0, and they are still in development.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Far from being a masterpiece, the da Vinci has ended up basically being a bag of paint with no paint. That is fine. That is Iarnród Éireann's case, but then the question is: how did it take so long to get to this? How did the Committee of Public Accounts and the Comptroller and Auditor General not know before that?

There was a lot of emphasis on Lithuania. Am I correct that while Indra was involved in many deployments, they were mostly single high-speed rail projects and simpler projects? Lithuania was significant because it was their first national scheme. Is that correct?

Mr. Paul Hendrick:

I think that is fair to say.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

This is why that was significant. Was it known that that project was delayed when the contract was awarded?

Mr. Paul Hendrick:

Yes. They had completed the project a year later than the original contract . They had completed the project, albeit a year later.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Did that delay form part of the tendering process?

Mr. Paul Hendrick:

It was assessed as part of the pre-qualification process.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Within a number of months by quarter three in 2020, Iarnród Éireann was already raising red flags and had concerns about the programme delays. Is that correct?

Mr. Paul Hendrick:

Yes. We had concerns because of the fact they were moving to this version 3.0 of the product.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

At that point, was any contact made with the unsuccessful bidder?

Mr. Paul Hendrick:

No, not that I am aware of. I was not here at the time but I do not believe there was.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Was the NTA aware of any contact being made with the unsuccessful bidder after the contract was made?

Mr. Hugh Creegan:

No.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Is correct that at no time were any proposals put to the unsuccessful bidder to try to partner with the successful bidder to deliver the project?

Mr. Paul Hendrick:

No.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Mr. Creegan?

Mr. Hugh Creegan:

I am not aware of any, no.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Okay. So, at that point, while Iarnród Éireann had concerns, it had confidence that Indra would be able to deliver the project.

Mr. Paul Hendrick:

Based on the reassurance and the commitments given to us by Indra.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Let me take Mr. Hendrick through each phase. The baseline was reset on four occasions. Deputy Neville has gone through a useful chronology, as each year Iarnród Éireann was getting an amount of €10 million and €15 million. Will Mr. Hendrick talk us through the process of how that gets approved each year? What is the mechanism or what are the points where things are opened that Iarnród Éireann gets to review work done and approves spending to continue?

Mr. Paul Hendrick:

Is this in relation to the contract or in relation to the financial statements?

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The contract.

Mr. Paul Hendrick:

If I could just talk about 2022-----

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Who signs off on the work and who agrees the next plan of work?

Mr. Paul Hendrick:

We do. Irish Rail does, as the client team.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Talk me through those timelines.

Mr. Paul Hendrick:

If I could speak about commercial reset No. 1, I came into my role in September 2022. The project was over two years old at that stage. I encountered the project and the project team working with Indra with serious concerns. They were talking about the project sliding up to two years off programme with various debates going on around what the cause and issues were. One of the actions that I took with the team was to say that we needed to arrest this, it was at large, and we needed to put it under control. So, we went into a dialogue with Indra for three months, culminating in reset No. 1, which added five months to the completion programme - June 2024 to November 2024.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

And costs.

Mr. Paul Hendrick:

And there was an update to the start price.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Am I correct in saying that that was described as a charge on the contractor's account?

Mr. Paul Hendrick:

No. It is the target price. We changed the target price by 8% with that. We had a five-month extension time, so we were still getting the project delivered by the end of 2024.

The benefits of doing that was it took a project that was at large where people were not operating to the original programme. They could not give clarity when milestones would be achieved.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

On the review of baseline 1, was the NTA informed of that?

Mr. Paul Hendrick:

Just to clarify, when we got to the point where we had something that we thought could be agreed between Indra and Iarnród Éireann, we brought that to the NTA. Before we executed it, be brought it to the NTA for its approval and we did not execute it until the NTA granted us the approval in early 2024.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

On that basis, was Ms Shaw still hopeful at that point that the project could be delivered?

Mr. Hugh Creegan:

Yes. We received the various proposals from Irish Rail and each time felt it was the right step to take.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

There was baseline 1, baseline 2, baseline 3, baseline 4. By the time Irish Rail got to baseline 4, had Mr. Hendrick very low confidence in this project?

Mr. Paul Hendrick:

May I just talk about the intermediate baselines?

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Yes.

Mr. Paul Hendrick:

In 2023, Indra, which it had a right to do under the contract, reset the programme. It moved it out twice. It moved the completion date from November 2024 to March 2025 and then, at the end of 2023, it moved it again, this time to August 2025, but that meant it was resetting to its account. In other words, we were not adjusting the target price or resetting the contract, and Indra was just advising us that it was going to be later than what we had agreed in commercial reset No. 1.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

But-----

Mr. Paul Hendrick:

That was causing us concern because of slippage on it. We were obviously looking for Indra to recover and find ways to deal with it, but when we came into summer 2024 - this was before we got to commercial reset No. 2 - the serious concerns we had were that the software we had been given to test was way short of the expectation.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

This is where I want to get to. By July 2024, had Iarnród Éireann already considered replacing Indra?

Mr. Paul Hendrick:

Yes, as a potential solution.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Am I correct in saying that Iarnród Éireann communicated that to the NTA?

Mr. Paul Hendrick:

Yes, verbally in a discussion with the NTA.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

At that time, was the NTA in contract or in tendering process in regard to the ticket management system?

Mr. Hugh Creegan:

I think we would have been at the tendering stage. I cannot swear to that. Certainly, we were at the tendering stage.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I suppose what I am asking is whether there is an interplay here. When Irish Rail raised the concerns, was the NTA fearful of ending the relationship with Indra on the train management system because the NTA was about to embark on a relationship for the ticket management system?

Mr. Hugh Creegan:

Absolutely not.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Was that not a consideration at all?

Mr. Hugh Creegan:

It was not. It never was a consideration.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Okay.

Mr. Hugh Creegan:

They were two separate projects and had to be managed appropriately in each case.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Does Ms Considine feel that, when she made the request to the NTA or when Iarnród Éireann started to consider replacing Indra, Iarnród Éireann had the support of the NTA on that or does she feel that the NTA was overly cautious?

Ms Mary Considine:

We made decisions at our board on 22 June and we took those forward to the NTA for approval. Our understanding is we required the approval of the NTA to implement those decisions.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

If the decision had been made in 2024 to end the contract with Indra at that point, would we have saved money as a result?

Ms Mary Considine:

It is very evident from the schedules here that we would have saved money if the contract had been terminated.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Can Ms Considine quantify that for the committee?

Ms Mary Considine:

I cannot comment. I was not here in 2024 but, obviously, if the contract was terminated at that stage-----

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Can Mr. Hendrick quantify what might have been saved?

Mr. Paul Hendrick:

It is hypothetical. Going back to Deputy Neville's comment on the €50 million writedown, a lot of the writedown is happening from 2021 onwards. That is where the majority of the writedown is. In summer 2024, our expenditure was probably €25 million less than the €150 million we were at at the end of December. It is a hypothetical. If you make a change at that time, you end up with a different synopsis.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Of course. Certainly, a sum in the multiple millions of euro could have been saved.

Mr. Paul Hendrick:

Potentially.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I will go back to the support contracts. The idea that support contracts would be of equal value to the contract itself is a mind-blowing concept. Of the €30 million, would Iarnród Éireann be able to provide us with a list of the support contracts and the value of those contracts?

Mr. Paul Hendrick:

Yes, we can. I suppose the principal ones were Ricardo Rail and Turas. They were in the order of €28 million, including VAT. What I should say-----

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Then what is remaining would be-----

Mr. Paul Hendrick:

Smaller ancillaries.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Were there any other contracts that would be in the range of €1 million or €2 million?

Mr. Paul Hendrick:

There might be one or two, yes. I would have to come back to the committee with the specifics.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

What role would they have held? What work would they have done?

Mr. Paul Hendrick:

We brought in some extra project support staff to support us, and particularly the project director that we brought in in October 2025 to help us because of the level of challenge and difficulty.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

What was the value of the contract for the project director?

Mr. Paul Hendrick:

He is a freelance organisation so he has got a couple of staff with him. There is a budget there north of €2 million but it is not expended. It is probably a few hundred grands' worth of expenditure.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

In 2025, a project director was appointed on a contract basis with a value of more than €2 million.

Mr. Paul Hendrick:

Based on a projected forecast of supporting the project for the coming years because we are not going to finish this project any time in the next two to three years on the basis of the way we are going, plus some additional support staff. It is a provisional budget. It is not expended.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

In a project that costs €150 million and may reach €250 million, I imagine the idea that an additional €2 million was set aside only a number of months ago while Iarnród Éireann was still dealing with the other issues would be concerning to members of the committee.

Mr. Paul Hendrick:

I should say he is replacing other staff. There are other staff who have been dialled out of the project, from Ricardo Rail and from Turas. We have had staff changes on our side where people have left to take up other roles in other organisations, and one or two in other roles within the business. Given the length of the project, you are always going to have a certain level of churn. Staff are moving around in the capital projects function.

Photo of Paul McAuliffePaul McAuliffe (Dublin North-West, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The €50 million can be an impaired asset. It can be written off but, in reality, it is not written off because it is not available for other services. I just think of the Luas figures in my own area. There is a price tag of €600 million on that. You are talking about €50 million, and perhaps more if the impairment grows. As for the scale of this, it is one of the biggest impairments of an asset that this company has ever seen. I am sure there are bigger, but it is very rare to see this scale of impairment. Given that we have come to the last day of term in the Dáil, there is a lot more that this committee needs to do on this issue.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I thank the witnesses for being here. At the outset, I want to start in the here and now as opposed to looking back on the project. In its opening statement, Iarnród Éireann makes reference to the decisions taken at the board meeting in June. Ms Considine mentioned that she may not be able to provide full details, but what can she tell us about those decisions taken at the recent board meeting?

Ms Mary Considine:

I thank Deputy McGrath. We have real focus now and it is about moving forward. I have said that there is huge regret that we find ourselves in this position as a collective and it is about now finding a way forward to deliver a train control system that future-proofs the network and minimises further exposure to the Exchequer.

We moved to act as early as we could to bring proposals to the board to get their support as a board - the board is very focused on this as well and very conscious of its obligation for taxpayers' money - and bring those decisions to the NTA for its consideration.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Can Ms Considine give the committee some details of those decisions?

Ms Mary Considine:

I cannot go into them but they are around the contract. The NTA has considered our decisions and agreed to the decisions taken.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

However, at this time, Irish Rail is still in contract with Indra.

Ms Mary Considine:

Yes, we are still in contract and working through that but we are talking about a matter of weeks to resolve it.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

What are our financial obligations to Indra at this point?

Ms Mary Considine:

I will ask Mr. Hendrick to come in on that. We believe that under-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

It was touched on in a response to Deputy Neville earlier. There was a figure of €3 million so far in 2026.

Ms Mary Considine:

There is €3 million spent on the contract so far in 2026. That was not paid to Indra. They are third-party costs and our costs.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

That is not a payment to Indra. That is third-party costs.

Mr. Paul Hendrick:

Mostly, yes. We stopped paying Indra in February this year because of the way the contract works. It has hit the ceiling and no more payments have been due since then.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

We are not on the hook to Indra.

Mr. Paul Hendrick:

We are not paying it at the moment under the contract because we have no obligation to pay it. It is making claims under the contract, but, so far, we have not established any entitlement to those claims.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Did the NTA agree to the decisions made at the board meeting in June?

Ms Anne Shaw:

Yes.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

However, we do not know the nature of those decisions and Iarnród Éireann is not in a position to tell us about them.

Ms Mary Considine:

We are not. The Deputy will appreciate that the last thing we want to do is compromise-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The decisions are about the contract with Indra.

Ms Mary Considine:

Yes.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Will Ms Considine give a high level breakdown of the headline figure for the writedown value of €50 million? She mentioned the €28.2 million on software.

Ms Mary Considine:

Yes, I can. Some €28.2 million relates to Indra, €8.5 million of the third-party costs relate to Turas and €6.76 million relate to Ricardo, and the other €2 million is for SET and ICT enabling works. However, the majority of it is the first three items, the TMS with Indra and the €8.5 million and €6.76 million for the two specialist service providers.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I will go back to the money spent so far this year. Is there further expenditure to come on obligations that have to be met, which will be effectively wasted? Are there still obligations to pay money to third parties or others?

Ms Mary Considine:

There will be work even supporting the review the NTA is carrying out and there will be work in implementing the decisions we have taken. However, we are talking about minimising it and working at the earliest to deal-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Can Ms Considine give us a value? We have the value of the report. I think €230,000 roughly was mentioned. What additional funds are still to be spent to close this out as a project to meet obligations that will not result in anything other than totting up more on the €50 million writedown?

Ms Mary Considine:

I believe - correct me if I am wrong - that we have moved to significantly reduce the resources involved in this and minimise the costs.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I understand that, but will Ms Considine give us some sense of it?

Ms Mary Considine:

There is still probably a couple of hundred thousand of euro per month.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

A couple of hundred thousand of euro per month.

Mr. Paul Hendrick:

I will go back to the question. We still need to complete the project with whatever solution we land on and that will take a number of years.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I understand the project has to be completed. That is not wasted money, in the sense that it has to happen. What is the element that will close out the wasted phase of this?

Mr. Paul Hendrick:

I would say it is a few hundred grand per month, maximum for the next couple of months. Then, when we move to the final solution to deliver the project-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The €50 million is, therefore, going to grow.

Mr. Paul Hendrick:

Yes, a bit, but it will stop, based on the decisions-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

It could grow to €50.5 million.

Ms Mary Considine:

The €50 million was an impairment figure written off on the balance sheet. There are ongoing current costs.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

My point is Irish Rail has not closed out this yet.

Ms Mary Considine:

We have not.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Therefore, there will be additional expenditure to close out the wasted phase of this. Irish Rail accepts that.

Ms Mary Considine:

Yes.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

It is not in a position to say how much it will be, but it will be several hundred thousand euro.

The need for the TMS was identified and the contract was signed in 2020 to be delivered in 2024. It is not there. What is the current state of the TMS?

Ms Mary Considine:

For the current TMS, we are using old technology. It is more than 20 years old and it will no longer be supported. That was the reason for moving to start this project in the first place but, in the interim period, once we knew the principles testing was not succeeding on the current version we had from Indra, we moved to look at a plan B around obsolescence to de-risk the greater Dublin area initially.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Is the current system functional and safe?

Ms Mary Considine:

The current system is safe. As I explained earlier, it is fail-safe. We will stop operations, but we will not compromise safety.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

What is Irish Rail stopping?

Ms Mary Considine:

If there were a breakdown in the technology in the morning, it would have an impact on operations. We had a failure at the end of May.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

There are operational implications.

Ms Mary Considine:

Yes, there are operational implications, but not safety implications.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Service delivery will be impacted by a failure.

Ms Mary Considine:

If we had not moved to de-risk the obsolescence risk, which we have now moved to do in the greater Dublin area. We need to look at a solution for the whole country.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Where is Irish Rail in terms of replacing that system? It is trying to close out the Indra project. It needs a traffic management system. Where is it on delivering one?

Ms Mary Considine:

All the decisions are interrelated so once we work through the next few weeks, we will engage with the NTA and the Department as our funders to secure funding for the way forward. We have a proposal to move forward.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Does Irish Rail have an estimated cost for what it will take to get to a traffic management system that is modern and up-to-date?

Ms Mary Considine:

We do, but for commercial reasons - we are in discussions - I cannot disclose that figure here.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Can I have a ballpark figure?

Ms Mary Considine:

Unfortunately, I cannot say, because I do not want to compromise-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Will it be tens of millions of euro?

Ms Mary Considine:

It will be a significant figure but I cannot disclose it because we want to preserve commercial integrity.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Will it be in the order of the €50 million writedown?

Ms Mary Considine:

I am not in a position to say, unfortunately.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

It will be a significant sum.

Does Iarnród Éireann have a timeline for when it hopes to get an updated traffic management system?

Ms Mary Considine:

We do. We are hopeful the obsolescence provisions can be addressed in 2027-28 and then we will move to complete the traffic management system by the end of the decade.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

We were due to have it by the end of 2024 but it will be 2030 at the earliest, from what Ms Considine said.

I will turn to the implications for budgets. With respect, Ms Considine kind of skirted around the implication for other projects earlier. This will have significant implications for other projects overseen by the NTA and Irish Rail. There is a €50 million writedown and to replace the TMS will cost an unknown amount but it will be a sizeable figure, as Ms Considine said. The money has to come from somewhere. Let us be honest about that. What will it have an impact on? Will the NTA address that point as the approving authority?

Ms Anne Shaw:

We will have to look at it across the whole portfolio across the rail network to understand what is safety critical, what capacity is and so on and then work out what we will need to change in delivery timescales-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

It is going to have implications for projects.

Ms Anne Shaw:

The replacement of the traffic management system, as Ms Considine said, is a requirement so we have to make sure we can deliver it within the timeframe that has been set out. Then we will take that into consideration. Once we understand what that delivery is and its costs, we will need to do a review of the rest of the portfolio to be able to understand the impact.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Ms Shaw mentioned the review that is costing almost €250,000. What is its aim?

Ms Anne Shaw:

Is the Deputy talking about the EY review that has been commissioned by the NTA?

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Yes.

Ms Anne Shaw:

It is to look back at the governance, decision-making and controls of the project from pre-procurement to where we find ourselves today. It will give us information about how the project was managed, how the governance was organised-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Respectfully, is there not enough ability within Iarnród Éireann and the NTA to sit down and figure out what went wrong here without bringing in a third party at a cost of €250,000, adding to the overall waste of public money? Is there not enough expertise within the organisations to pinpoint where things went wrong?

Ms Anne Shaw:

As I mentioned in reply to a question earlier, it is always valuable to have an independent view, particularly so the organisations are not accused of not putting all the information into it.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Are the terms of reference for the review such that there will ultimately be some accountability for what went wrong?

Ms Anne Shaw:

There will be a series of findings and recommendations and both organisations will deliver against those recommendations, working with our colleagues in the Department of Transport.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

In this whole fiasco, it seems there is Iarnród Éireann, the NTA and the Department of Transport and everyone is responsible, but no one is responsible. Where does the accountability fall for this?

Ms Anne Shaw:

There is accountability at different stages of the project. There is accountability in Iarnród Éireann for the delivery. There is accountability in the NTA for the approvals and oversight of the project and accountability in the Department for the overall programme.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

There is effectively no accountability. All parties here have said that it predates their time in office, so ultimately there will be no accountability for this.

Ms Anne Shaw:

There are certainly people who will take responsibility and accountability for this project, particularly in moving this project forward.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Finally, regarding the NTA, I have to say I have serious concerns about the organisation as a whole. We have constant correspondence between this committee and the NTA. We just have to look to the electric buses and the whole debacle over their storage, and the Busconnects project in Cork with €75 million spent on that alone and effectively very little to show for it. We have ongoing issues relating to bus reliability that have been highlighted for years now, and we seem to be making no progress with them.

The NTA is currently pumping out replies to anyone who asks about the delivery of new services that it does not have funding for it, and is pointing the finger to the Department of Transport, yet we are here today discussing a monumental waste of public money. There are serious governance and management issues with the NTA that have to be addressed.

Would the witnesses like to comment on that?

Ms Anne Shaw:

I take the points the Deputy has raised quite seriously. However, there has been an element of delivery across the projects to move them forward within the project life cycle. We have continued to work through decisions around the capital programme and with the Department of Transport in planning for new services as part of Busconnects. There is always expenditure before you do the infrastructure delivery, etc., to make sure we are delivering the right thing, but those projects are moving forward and will deliver benefits for this country in terms of sustainable public transport access.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Thank you.

Mr. Tomás Campbell:

Briefly, on the PSO point, for the PSO budget this year we got a 43% uplift from the Department of public expenditure, which puts us at a much better baseline in 2027. In the NTA's defence, part of the budget setting was that there would not be new services this year and it would be a year of consolidation. The Minister, Deputy O'Brien, has been clear on that as well.

In the past, we have rolled out new services, particularly with driver availability and the availability of electric buses, which the Deputy mentioned, but this year is about catching up. As part of the budget negotiations in October for 2027, we will be advocating for additional funding for additional services next year, but this year has been to try to consolidate the services.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I thank all the witnesses for being here today. Am I right in saying the original project budget for the national train control centre was €148 million?

Ms Anne Shaw:

Yes.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

In the NTA 2024 accounts, it was estimated the project cost had increased to €189 million, which constituted a 28% cost overrun. Is that correct?

Ms Anne Shaw:

Yes, that is correct.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

In the document the witnesses have supplied for us today, it states, "indicating an optimistic best case of forecast outturn cost." They are now saying it is going to cost €250 million, which would represent a 70% increase on the original budget. What does the NTA attribute that cost increase to?

Mr. Hugh Creegan:

That comment in the briefing note is a briefing given to the Irish Rail board. That figure of €250 million is not settled yet. As it was mentioned earlier, we still have to work through what the next stage of the project is. We will then have a firm figure, but we do not have that yet.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

What is the provenance of that €250 million figure?

Ms Mary Considine:

As I said to Deputy McGrath earlier, we are considering all these and, in a matter of weeks, we hope to have more certainty. However, I cannot confirm the figure at this stage. I think that figure was a rough order of magnitude.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Hold on. The witnesses supplied documents to this committee and told us it was €250 million. I have a very simple question: what is the provenance of that €250 million figure, which is €60 million more than the figure given to us at the end of 2024? Can Ms Considine even explain that €60 million increase?

Ms Mary Considine:

I understand the reference to the €250 million figure was an outer range, if the project was to continue over the next number of years. It is not a figure that relates to where we are today and what would be required.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

How did the NTA get to that figure?

Ms Mary Considine:

I might hand that over to Mr. Hendrick.

Mr. Paul Hendrick:

In reference to the €189 million figure, we put forward a range a few years ago when we were working through the project with Indra and were expecting to complete the project with Indra, but obviously later than planned. Commercial reset number two put us into the 2027 completion timeline and we did a risk assessment against how late it may be against that.

We did a project range forecast of €175 million to €205 million, which is where the €189 million comes from; it is the midpoint.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Can Mr. Hendrick tell me how we are now at €250 million?

Mr. Paul Hendrick:

The source of this goes back to the lack of a developed product from Indra, which is driving the project delays. That €250 million, which is in our briefing note, is an indicative estimate. It is just extrapolating based on time. It is the time delay to complete the project and the level of resource effort that would likely be required to complete the project. That is what it is driven by.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

As for the resource effort Mr. Hendrick is talking about there, is that buying a new TMS software project from a new supplier? The NTA estimates that will cost €60 million.

Mr. Paul Hendrick:

That is provisional because we have not got to the final decision on the way forward.

Ms Mary Considine:

Basically, that was based on Indra continuing over an elongated period.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The witnesses are both saying completely contradictory things. One is saying that relates to the acquisition of new software, while the other is saying it relates to Indra. Which is it?

Mr. Paul Hendrick:

The briefing document, as it was done at the time, was on the basis that if we stayed going with Indra, albeit without any predictability of where it was going to finish, it could end up in that particular zone or territory. We have not finalised that way forward yet, so we cannot-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I just asked Mr. Hendrick a moment ago if that related to the acquisition of a new TMS software, and he said "Yes". He nodded as I was speaking to him.

Mr. Paul Hendrick:

Either way, we are going to have expenditure more than the €205 million we indicated in that range, whatever way we go forward with the project, because the project is going to finish significantly beyond 2027.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I said that is €60 million more, and that figure the NTA has talked about is for the new software it is potentially going to have to acquire-----

Mr. Paul Hendrick:

There will be costs to that new software.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The NTA has estimated that at €60 million.

Mr. Paul Hendrick:

No, we do not have a final figure for that.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I did not say the witnesses had that final figure. I said the figure the witnesses have given us, and by the way, I am only questioning figures they have given us-----

Mr. Paul Hendrick:

Yes, exactly.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

That is all I am doing.

Mr. Paul Hendrick:

That figure relates to Indra.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It does not relate to any future costs the NTA would need to acquire new software.

Mr. Paul Hendrick:

It does not, because we have not got to the final decision or solution there. We still need to finalise what that will be and those figures, so that figure does not relate to it.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

What is the point of the €250 million figure? What is the NTA trying to tell us?

Mr. Paul Hendrick:

If the project continued with Indra, albeit with no definitive timeline. We did an estimate for the board at that time, when we put that into the document, of where this could end up if the project continued with Indra beyond 2030.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

If the project continues to not deliver the software the NTA needs.

Mr. Paul Hendrick:

If the project continued to deliver and was completed as per originally planned, albeit much later.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It would go to €250 million.

Mr. Paul Hendrick:

It could.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

If the contract with Indra is terminated, what do the witnesses think the cost will be?

Mr. Paul Hendrick:

We cannot say the definite number at this time because we have not got the final decision agreed on how we would move forward with that. We will have to finalise that figure.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

According to The Irish Times and the letter Irish Rail sent to the NTA, the plan is to look for an exception outside the normal rules of public procurement and get Siemens Mobility to provide the TMS service. That is what was reported in The Irish Times. That is Irish Rail's plan but it needs approval, is that correct?

Mr. Paul Hendrick:

I do not think we can go into that. It goes back to-----

Ms Mary Considine:

It is unfortunate that things are covered outside of process, but we have to follow the process and preserve the legal and commercial integrity of the discussions that are currently-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It is the NTA's plan to look outside of public procurement to replace the software, is that not correct?

Ms Mary Considine:

At present, we have proven in-use technology on our network that is capable and is part of our strategy to de-risk the obsolescence risk in this area, which is an option going forward. However, we cannot prejudge what will happen over the coming weeks.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Obviously, if you issue a notice, that is a public notice and will be published on eTenders or whatever, if Irish Rail is looking to go outside the public procurement rules. Mr. Hendrick mentioned earlier he was advocating that, in certain circumstances, going outside the tender rules could be a better outcome for the delivery of software. This was reported in The Irish Times with reference to the letter. We are sort of dancing around a pin here. That is the plan. Whatever about Siemens - maybe the witnesses cannot talk about that - the plan is to go outside public procurement to replace the software. The witnesses can say that, can they not?

Mr. Paul Hendrick:

I do not think it is strictly correct to say it is outside of public procurement, per se.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Sorry, the witnesses are looking for a lawful exception to go outside the standard. The NTA is not going to issue a tender; it is going to directly engage. It is going to do it in a different way through the existing public procurement rules.

Mr. Paul Hendrick:

We are looking at different routes and avenues to it, but I have to go back to the comment from my colleague earlier about the whole thing.

We are still in contract with Indra-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Going back to the original contract, is Mr. Hendrick familiar with the term "abnormally low pricing bid"? He indicated that the bid was 50% lower than the other bid that Indra was-----

Mr. Paul Hendrick:

If I may just correct myself, because I misspoke earlier, the unsuccessful tender was 50% higher. Technically, it is just to do with the percentage-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

That is okay, but it was a very big differential.

Mr. Paul Hendrick:

There was a differential between them.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

An enormous differential.

Mr. Paul Hendrick:

Sizeable, yes.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Well, it is not prescribed but, typically, as I understand it, an abnormally low bid would be between 15% and 20%, but Mr. Hendrick said it was 50%.

Mr. Paul Hendrick:

If I may just say this, because I have to be careful around the commercial sensitivities of that information as well, we have the NEC contract model, so we were able to have full insight into how those prices were made up in a way you might not see in other contract models. The differential was driven by the fee approaches that the bidders took. One bidder had a similar cost base, if that makes sense, but how they marked up their cost to generate their price was very different from the successful tender-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Nevertheless, it was 50% more.

Mr. Paul Hendrick:

As a total, it was of that order.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Mr. Hendrick knows the legal obligations that apply to contracting authorities when an abnormally low tender bid happens. Was an investigation carried out at the time?

Mr. Paul Hendrick:

It was investigated. It was assessed. We do a normalisation process to work through that. Based on the visibility of the prime cost of the work for both bidders, they were both in a similar range, but it was the fee differential that was different. We worked through a process to satisfy ourselves that it did not meet the legal standard for abnormally low. That was the procurement decision that was reached and that led to the contract award.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

In respect of the issue Mr. Hendrick raised about the two versions of the software, he said that Iarnród Éireann had examined it and that, legally, Indra was not in breach of contract. Obviously, Iarnród Éireann sought or relied on legal advice in the context of examining this issue.

Mr. Paul Hendrick:

I was not in this position at the time but, in terms of my understanding of what the project team went through, we assessed it with the project team, the engineering professionals on the project and the people who were working to manage the contract. I cannot say whether there was legal advice taken on that particular decision. I would have to come back to the Deputy on it.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

But Mr. Hendrick indicated earlier that, legally, it was not a breach of contract.

Mr. Paul Hendrick:

There are project professionals. Some of them are not lawyers, but they are-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Mr. Hendrick does not know yet whether Iarnród Éireann has assessed whether that constitutes a legal breach of contract.

Mr. Paul Hendrick:

The assessment decision was made by the project team at the time, including by people who are there to professionally manage the contract, not necessarily lawyers. We do not have lawyers working in project delivery, let us say, but they are still responsible for managing the contract, managing claims, deciding whether a claim has entitlement or not, establishing whether there is a breach of contract. This is normal with all our projects. In certain cases, depending on the situation, we also take legal advice. I cannot say whether-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

My time is short, so I will ask just one final question. The restart agreement was a sort of contract agreement at the end of 2024 between Iarnród Éireann and Indra based on all the deliberations, is that correct? Iarnród Éireann agreed to the restart agreement and six months later identified problems. Going forward, is Mr. Hendrick concerned that Iarnród Éireann has sort of lost its right to moan about everything that went wrong before the restart agreement in the context of any future recourse it may wish to take? Is that going to prove problematic for it as the contracting authority?

Mr. Paul Hendrick:

I go back to a comment from my colleague earlier. We are still in contract with Indra. This is all commercially and legally sensitive, so it is difficult for me to-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

During this hearing and in the documents he has provided, however, Mr. Hendrick has identified several moments when challenges, concerns and red flags arose. He has put all that out there. Once Iarnród Éireann executed a new agreement with Indra, is Mr. Hendrick concerned that it might be problematic into the future in terms of any recourse Iarnród Éireann might have against Indra?

Mr. Paul Hendrick:

It depends.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I thank Deputy Geoghegan. I will ask some questions. Six years after the initial contract and two years after the full implementation of the TMS was due to be delivered, how much has actually been delivered? We know it was broken up into different CPs. CP1, for example, represented what percentage of the entirety of the contract?

Mr. Paul Hendrick:

CP1, which was the Rosslare line, was about 3% of the overall-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

About 3%.

Mr. Paul Hendrick:

Yes. It is about 6% of-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

In terms of complexity, that was the easier part to implement. We are talking about a write-down of €50 million, which is growing, and other costs, which I will get into in a moment, and we have not even seen 3% delivered.

Mr. Paul Hendrick:

That is correct.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

We talk about red flags and interventions. That speaks volumes. As regards the contract with Indra, Ms Considine stated that the company has embarked on a legal process. Has Indra been informed legally that the contract is going to be terminated?

Ms Mary Considine:

As stated earlier, we really cannot go into that. We are still in contract with Indra and-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

We are dancing on the head of a pin here. A decision was taken by the board-----

Ms Mary Considine:

Decisions have been taken and-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

-----of Irish Rail, supported by the NTA, and we cannot say what was involved.

Ms Mary Considine:

We would have confirmation of the support of the NTA on Monday afternoon, so we need to work through that. The Cathaoirleach will appreciate that it is only Thursday.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Has ministerial consent been asked for or is ministerial consent needed?

Mr. Tomás Campbell:

At this point, no. Ms Considine mentioned the resilience measures. Because of the delays relating to the traffic management system, which had two parts, which were to deliver a traffic management system for the country-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Has the Minister given approval to terminate the contract?

Mr. Tomás Campbell:

No. Ministerial approval would not be required, but the Minister has approved resilience works through the infrastructure-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I will get to that in a minute. I want to talk about the decision to seek a capital investments lead on the project. Whose decision was it that capital investments in Irish Rail would lead out on this?

Mr. Paul Hendrick:

It would have been the CEO at the time.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

In light of your experience in capital investments, you might give us some examples of IT projects that capital investments delivered successfully in the years prior to the decision to enter this contract.

Mr. Paul Hendrick:

Capital investments is primarily delivering all the new railway infrastructure projects and rolling stock projects-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Physical infrastructure, engineering projects-----

Mr. Paul Hendrick:

-----and that includes signalling. I want to make this distinction, because it is really important. The train control system is a signalling project. It involves-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

What IT experience existed in capital investments?

Mr. Paul Hendrick:

May I just say, it involves hardware and software. We are dealing with hardware and software and other signalling projects, which we are delivering to plan. This is not an IT project. I appreciate that it has the hallmarks of one because of what it has become, but it is a signalling project - a signalling system. Because of the difficulties-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

A signalling project that heavily depended on IT and technology.

Mr. Paul Hendrick:

There is hardware and software in every signalling project, but you should not have an IT-type project delivery when you have a developed signalling product-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

What specific IT experience-----

Mr. Paul Hendrick:

Capital investments are not an IT delivery organisation, and we were not delivering IT projects. I want to make that clear.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Who would be the person within Irish Rail who would have the competent head of technology?

Ms Mary Considine:

Technology sits in a number of areas. There-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Who is the competent head?

Ms Mary Considine:

We have a chief information officer, CIO, for the organisation who would look after all the infrastructure.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

What role did the CIO play?

Ms Mary Considine:

He would have sat on the initial project board. I can confirm that afterwards. We also have operational technology that, as my colleague Mr. Hendrick said-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

The information I have is that the competent head was never involved in the project from the very start right through to design to tender to project management, or, indeed, in the intervening years. You might come back to us-----

Ms Mary Considine:

I will come back and clarify. That is fine.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

-----if you want to contradict that. It has been reported that payment to Indra stopped in April?

Mr. Paul Hendrick:

It was February.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

February. There is a claim by Indra. A figure of €5.67 million has been put out there. What is the timeframe relating to that claim.

Mr. Paul Hendrick:

Indra has raised a number of claims relating to the period 2025 to 2026. We have assessed the claims that have been submitted and they have been rejected as lacking entitlement under the contract.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

All claims have been rejected.

Mr. Paul Hendrick:

They have been professionally assessed. We have assessed them thoroughly against the contract and we have rejected them.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

There is no outstanding claim for €5.67 million.

Mr. Paul Hendrick:

There is a claim there. We have rejected it but Indra has not rejected our rejection of its claim thus far. I am not saying it will not reject our rejection. If it wants to do so, it is entitled to under the contract. All I am saying is that it has not done that yet.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

On the cost, we know there was a write-down of €50 million. The witnesses have touched on the existing train management system in Connolly Station. Over €6 million in funding has been allocated. Is that to strengthen the system or what is it to do?

Ms Mary Considine:

That funding was made available through the Department of Transport to allow us to address the obsolescence issues.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

How much funding was provided?

Ms Mary Considine:

It is in and around the figure the Cathaoirleach mentioned for this year.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

It is €6 million for this year. What is it for next year?

Ms Mary Considine:

I cannot give a figure for next year.

Mr. Tomás Campbell:

Iarnród Éireann submitted a proposal to us for about €20 million over three years for that work.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

That is €20 million over three years.

Mr. Tomás Campbell:

It proposed €20 million over the next three years but we have only given approval for the first year of the project. While we recognise the importance of the resilience works, we did not want to pre-empt the software testing phase with Indra and any subsequent decisions around the TMS more generally. At this point-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

This €20 million is to shore up a 20-year-old system that is outdated-----

Mr. Tomás Campbell:

No.

Ms Mary Considine:

No.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

-----and that was due to be replaced.

Mr. Tomás Campbell:

It is not. It is to deliver a new system that will-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

It is for a completely new system.

Mr. Tomás Campbell:

-----work in parallel with the old system. The benefit of that is that it gives us greater redundancy in signalling in the greater Dublin area. It will support the direction of the DART+ programme. It also frees up some spare parts from the older obsolete system at Connolly Station so it gives us more resilience across the entire network. That system is no longer supported and we are running out of spare parts. Over the next three years, we will see a signalling solution in Dublin and greater resilience across the entirety of the network.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

There are further concerns in relation to a new signalling system in Cork that is due to come into being in August 2027. According to the minutes provided by Irish Rail, if there is a delay to the commissioning date for the Cork signalling system, it could lead to additional costs on the project, including contractor delay claims and internal and external project management claims of up to €800,000 per month. That system depends on a train management system being in place to underpin it. Will the witnesses give us some reassurance? The necessary TMS was to be the system Indra was going to deliver, which is now clearly not going to happen. What reassurance can the witnesses give us that a system will be in place to ensure there are no financial penalties in relation to that particular signalling system?

Ms Mary Considine:

Part of resolving where we are at the moment and moving forward is looking at how we can deliver a train control system for the entire country. As Mr. Campbell has said, with the benefit of funding from the Department, we are able to address the greater Dublin area. We now need to look at a solution for the whole country. The Cork area commuter rail project is a critical project. We do not want to have to delay or implicate that.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

We have just over 12 months.

Ms Mary Considine:

We are looking at options.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

We have just over 12 months. Can you give us assurance that a system will be in place to underpin that new signalling system, which is due to commence in August 2027, to ensure no financial penalties are imposed?

Ms Mary Considine:

That will be a key consideration of ours. We will obviously be putting forward a case for funding to secure that.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

There is no funding and no one in place to deliver that. Am I right in saying there are penalties of up to €800,000 written into that contract in addition to other financial considerations? We are facing serious financial repercussions if we do not have a system in place by August 2027.

Ms Mary Considine:

The Cathaoirleach is right that there will be costs if we do not come up with a solution but, as he has said, there are 12-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

There will be costs to the tune of €800,000 a month.

Ms Mary Considine:

That was an estimated cost. The key thing here is that, as you have rightly said, we are 12 months away. There are options and we need to make sure they are put in place to avoid that cost.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Are you confident we will avoid that cost?

Ms Mary Considine:

We will do everything we can to-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

There is no confidence there.

Ms Mary Considine:

I cannot guarantee the funding but that is certainly our intention.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

We have written off €50 million. That is wasted. Some €20 million is being provided for a system for the greater Dublin area, which is only necessary because of the failure to deliver the TMS. There are further financial considerations next year because of this failure. The millions are ratcheting up here constantly. That is before we actually move towards putting in place a TMS.

Ms Mary Considine:

To clarify, that is a TMS. The work we are doing in the greater Dublin area is a traffic control system. If we come up with a solution for Cork, it will be a permanent solution. This is not wasted money. It is the solution.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I want to talk about the rest of the country outside the GDA. One of my colleagues touched on potentially giving a contract directly to Siemens. I believe Siemens withdrew from the initial tendering process. I would have concerns about bypassing normal procurement rules. Anyone looking to deliver a train management system has the State over a barrel. I would have serious concerns that anyone looking to deliver such a system could just name their price. I might ask the Comptroller and Auditor General's office for a view on concerns relating to bypassing a normal procurement process and awarding a contract of such a nature directly.

Ms Colette Drinan:

I am obviously not going to comment on Iarnród Éireann and its operations specifically. In procurement, openness, transparency and competition are needed to underpin value for money. That is the standard. In exceptional circumstances, stepping away from that can be justified but a very clear audit trail would be necessary. It is a complex matter. There would be a need for legal advice and so on to underpin it.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I would have serious concerns that any prospective deliverer of a TMS will have the State over a barrel because of the situation Irish Rail finds itself in. I will touch on another couple of areas quickly. Have people been recruited to work in the national control centre? How many staff does Irish Rail currently employ in that centre?

Mr. Paul Hendrick:

We have a number of operations. We control a number of aspects of the railway from the national control centre. These include control of the overhead powerlines for the DART network, some of the CCTV systems, level crossings and a part of the network on the Sligo line. That is as was always planned. That has been delivered because it was not dependent on the Indra project. There are a number of staff in there. We would have to come back to the Cathaoirleach with the number. It is low because it is not the full complement.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I have seen some of the recruitment advertising. The figure I have been given is that up to 30 staff have been recruited over the last two years to work on the signalling system and the TMS. Were any people employed specifically to be trained to operate the TMS?

Mr. Paul Hendrick:

We would have employed some people in preparation for CP1 going live.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

How many?

Mr. Paul Hendrick:

I would have to come back to the Cathaoirleach. I do not have the number to hand.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Are they still in employment?

Mr. Paul Hendrick:

Yes, my understanding is that whoever we have employed-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

There are people sitting in the national control centre twiddling their thumbs and waiting for Indra to deliver CP1.

Mr. Paul Hendrick:

No. They are controlling what can be controlled from the NTCC building at the moment based on the assets that are being managed from the building today. We have obviously scaled back recruitment. Until we have certainty on the programme, we need to look at staff-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Could that figure be up to 30 staff?

Mr. Paul Hendrick:

Is the Cathaoirleach asking about all the staff who are in there today across 24-7 operations?

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I am asking about staff working on that kind of-----

Mr. Paul Hendrick:

It could be but I would have to come back to you on it. There would not be 30 on any given shift. There would be a smaller number on a standard shift. We would have to come back to you.

Ms Mary Considine:

To clarify, a number of the control desks have migrated in there, as Mr. Hendrick was saying. There are staff working on those desks on a 24-7 basis. They are using the existing technology, however.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

There has been a considerable cost. Some of these staff would have been trained up on the TMS and CP1.

Mr. Paul Hendrick:

That is limited. We had to scale that back given the programme difficulties with Indra. We only have the staff there to manage what is currently being managed and controlled from the control room.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

You might come back to us with more information on the costs associated with that. We will go back to the members. With the agreement of the witnesses, we will open it up for a second round of five minutes per speaker.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The drip feed of information we have received about this project is not acceptable. It is essential that we get clear and transparent information from the NTA, Irish Rail and the Department on this and all other projects.

When we look at the governance structure of this project, it was more complicated than a small multinational, yet the only entity in this whole fiasco that seems to have been raising red flag, particularly since 2020 and seriously from 2022, was the sponsoring authority. Why did the NTA not step in earlier and resolve this issue? Why did the Department not step in earlier? It is simply not good enough.

Mr. Hugh Creegan:

The NTA has been actively involved over the past four years as the problem arose. It was not the case of us being blind to it. At various points along the problem cycle, we made joint decisions with Irish Rail as to what should happen and that has been the case for the past two years. It has not been the case that we have been blind to it.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Reading between the lines and reading Irish Rail's submissions and the numerous times it raised issues with the NTA, it was screaming, "Help, get us out of this; help, we need to terminate this", at the NTA. The decision - the joint decision apparently - always seemed to continue, that we would throw millions more at this project. What does that say about the NTA's oversight?

Mr. Hugh Creegan:

At each point, we had a particular issue to deal with. We did grapple with the choices and, as the Deputy can see, impairment and all the consequences are really big issues. With Irish Rail, we looked at the alternatives. There was a major meeting with Indra in 2024 where we demanded an immediate plan to remedy the project. We did get a plan off it that seemed credible and we proceeded with that. Ultimately, it did not deliver. Last year, a report from WSP identified something that could deliver this but it would need to be done in a different way with a series of recommendations. Together with Irish Rail, we sought to do exactly that so at each point along the project, we have tried to rescue it.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

That is the point. It was clear to me a year ago, and I was not even in the weeds of it a year ago, that this project was failing when I started questions about it. The NTA was in the weeds of it so it should have been clearer to it much earlier.

I want to move on because we have not even reached the buses. Is the NTA acquiring buses? Is it the approving authority or the sponsoring authority or both? I am so confused by the various different blurred lines of the far too many hats worn by the NTA.

Mr. Hugh Creegan:

When it comes to buses, it is crystal clear. We purchase the buses.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Which means it is the sponsoring authority. Who is the NTA's oversight authority?

Mr. Hugh Creegan:

In the case of BusConnects, we set an internal programme board with-----

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Who does it report to? The NTA probably.

Mr. Hugh Creegan:

No, we have external members and our board is chaired by an external person. That board acts as the approving authority for certain decisions of the project.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Who does that board report to?

Mr. Hugh Creegan:

Ultimately, we all report to the Department of Transport.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

We need to get back into that again in September. In terms of the position the Department and the NTA seem to be taking on the buses, that we are saving money by having buses sitting in storage, as has been said in the Dáil and the documents provided here today, we need to see a very detailed cost-benefit analysis of how the Department is coming to that conclusion. It leads me to believe that the indexation of the inflation clauses in the framework agreement are far too generous. This needs to be looked at by the Department.

In terms of the planning, I refute the contention by the NTA that you cannot plan the planning phase of the delivery of the electric grid charger at the same time as ordering buses. It should not be a case of one after the other, which seems to be what the NTA is saying it should be. The NTA should know how long it is going to take in each local authority for it to obtain the planning permission and then order the buses based on that. It is not rocket science. Some of the stuff in here such as contending that we would have had to delay it until the infrastructure was in place is simply unacceptable if there was any project management capability on this.

Mr. Tomás Campbell:

I will come briefly.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Mr. Campbell is very brave. Mr. Creegan was about to come in there. Let us hear from Mr. Creegan.

Mr. Tomás Campbell:

Regarding the analysis of the storage costs versus the bus one year later, inflation clauses probably may have been standard at the time but that period was the time of the Ukraine war so inflation probably was quite high. That analysis has been done by the NTA and does stack up.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

We have not seen it. All we have seen is this rhetoric. The Committee of Public Accounts has not seen the detail. Do not tell us it is saving us money without showing us.

Mr. Tomás Campbell:

It is costing money but it is costing less as-----

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It certainly is.

Mr. Tomás Campbell:

Mr. Creegan will come back in more detail on this. We have had a century of internal combustion engine buses. They are easy to install. It is a case of build a depot and drive them in. We are doing all of this for the first time. Research and development, getting planning applications in and get planning approval are happening for the first time. All of that has happened for the first time and there have been problems but the NTA has installed-----

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It is not rocket science.

Mr. Hugh Creegan:

We did exactly what the Deputy suggested. We tried to align the provision of chargers and the purchase of buses.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

There were two failed procurement processes. That is a serious reflection on the NTA - two failed procurement processes for electricity-charging infrastructure.

Mr. Hugh Creegan:

We can buy the buses, but when it comes to putting the chargers in the depots, the depots are run by the bus operators so they ran those procurement competitions.

Photo of Grace BolandGrace Boland (Dublin Fingal West, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It is always someone else.

Mr. Hugh Creegan:

They are the facts. We did align the bus purchasing programme and the charger installation programme, so at the start of the process, they were aligned. Due to problems that arose, they became disconnected and we ended up with the problems we have.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I want to bring it back to a really high level. In some ways, I know the answer but what exact amount has been spent on the project to date? Is it €150 million?

Ms Mary Considine:

It is €150 million plus €3 million to date this year.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Could Ms Considine clarify the figure of €3 million?

Ms Mary Considine:

The figure of €3 million is the ongoing cost of managing the project this year.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Who is getting that money?

Ms Mary Considine:

As Mr. Hendrick would have said, we have stopped paying Indra since February so there would be some Indra costs in there and then there would be third-party costs and our own project management costs.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Is Irish Rail continuing to capitalise that?

Ms Mary Considine:

No.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

So that is going through Irish Rail's current expenditure. Does that affect its current budget? Is it something Irish Rail had assumed would be in the costs in its budget?

Mr. Paul Hendrick:

We would have seen it-----

(Interruptions).

Mr. Paul Hendrick:

-----when we set that budget last year.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

So it will affect Irish Rail's current budget. That is money it would not have budgeted for. If it is not capitalising it now-----

Mr. Paul Hendrick:

It is coming out of the capital side, which is going through profit and loss, but it was meant to go into the balance sheet.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I know, but it is actually going through profit and loss. It is an expense. Irish Rail would not have put it in.

Ms Mary Considine:

It is, but it is in and out because of funding.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am very conscious that Ms Considine is new to her role. Was this something she quickly saw as a red flag when she assumed her role? I am conscious that she has come in. It was written off in her time. How long has she been in her role.

Ms Mary Considine:

I am about nine months in.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

So essentially she is trying to clear the decks.

Ms Mary Considine:

My first board meeting was in October when there was a red flag in respect of this. We really focused-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Was it highlighted at the meeting?

Ms Mary Considine:

It would have been flagged as a red flag project in the first board reporting. We are managing a significant portfolio of projects - €3.6 billion in phase six execution - and this was the one with the red flag on it.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Can someone tell me what the old CEO thought of this, because we know Ms Considine cleared the decks? All too often, we come in after hearing that the person who had previous oversight has gone. Does anyone know what his stated view was?

Ms Mary Considine:

I cannot speak for anyone else but if the Deputy looks-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

On the record.

Ms Mary Considine:

-----at all the data, concerns were raised all the way through and there would have been a number of senior meetings with Indra to try to resolve this.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Did he ever wish for it to be written off? It is just interesting that Ms Considine came in and wrote it off straight away. What was his view?

Ms Mary Considine:

As we discussed earlier, there was no discussion at the board about impairment because it was still working on a way forward.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

That was despite the fact that there were a serious amount of flags.

Ms Mary Considine:

There were serious flags but as my colleague has said there were two commercial rebasings of it on the basis that everybody believed the project was going to be delivered.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

With the €152 million capitalised; I am sorry, how much is capitalised on the books now?

Ms Mary Considine:

There is €100 million of-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

There is €100 million capitalised, €53 million written off of a current total expense of-----

Ms Mary Considine:

Yes.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Okay. Where are we with the project? What if I am asked today? Someone says we have wasted €50 million and asks me where we are with the other €100 million. From a holistic perspective-----

Ms Mary Considine:

The €100 million is a building in use. We have-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It is a building in use.

Ms Mary Considine:

It is in use. As we spoke of earlier on, a number of our controllers our working out there based on existing technology.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Are we happy with the build-up of that cost basis? I mean the capitalised nature of it.

Ms Mary Considine:

Yes.

Mr. Paul Hendrick:

No write-down on the building.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

That is what I am saying. The officials are happy that the €50 million is not linked to the €100 million, so it is just the software cost of the same project. What is the building being used for?

Ms Mary Considine:

The building is being used by our own team who are operating on existing technology we plan to replace. Gardaí are also operating out of there and the building has been future-proofed for Dublin City Council.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Dublin City Council.

Ms Mary Considine:

Yes, to look to control the overall traffic system for the city.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Okay, so we have a €100 million building but all the software - essentially, the actual project - is gone.

Ms Mary Considine:

Just on the €100 million, you have the building, hardware costs for the new technology-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am conscious of-----

Ms Mary Considine:

-----and a lot of enabling work was done around the network for the new train control system.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

How much do we believe will have to be spent? I assume this project will have to go ahead in some shape or form. What is the cost going to be of that project?

Ms Mary Considine:

I am just repeating myself, and I apologise, but it is at a sensitive time commercially and legally, so I cannot answer that.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

But we are going to go down that route again.

Ms Mary Considine:

I am happy to come back and clarify once we are through the-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I know, but the project still has to be done.

Ms Mary Considine:

Absolutely.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

That is fine.

This is more maybe for the NTA. What are the ramifications for it? We have a lot of projects coming up like DART+ West, DART+ South West and MetroLink. How do we feel? This involves the Department of public expenditure as well. At the infrastructure committee we had the interim CEO of MetroLink in. At the budgetary oversight committee, the Department of public expenditure was saying it does not really have a role because that role is subbed out to other people. The Department was not aware of this issue when I raised it on Tuesday. It seems strange to me that people at senior levels in that Department are not necessarily aware of a €50 million write-off in an entity where ultimately it is writing the cheques. I am not asking where the learnings are going to be because I hate asking that question, but what are the implications and ramifications considering the significant amount of money we are going to have to spend on infrastructure to bring it up if we can miss out on a project like this which showed many red flags? Was it 63 tests I saw were failed along the way, or where issues were brought up?

Ms Mary Considine:

There were over 600 test log issues with 63 kind of substantial issues, I believe.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

There were 63 flagged failures on a project over many years, yet we just come to the end and someone new comes in and says we need to write that off because ultimately we have nothing to show for it.

Mr. Tomás Campbell:

I will come in first from the Department's perspective. To take the point on the Department of public expenditure, we have been engaging with our Transport Vote colleagues in the Department, so they are aware of these issues. We have been-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The senior levels of the Department of public expenditure were not.

Mr. Tomás Campbell:

That would be at principal officer level. I am not sure internally then how it was communicated-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I just thought it was striking.

Mr. Tomás Campbell:

I am not sure I can comment on the Department of public expenditure's-----

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I will not say the name but it was striking.

Mr. Tomás Campbell:

As I mentioned, we in the Department have been very concerned about this project all along. When you look at the Arts Council IT project, the failings outlined in this committee's report or the Niamh Brennan report were around not having formal structures in place and not escalating these issues up the line. We have those with the MPGOG. We have our independent members.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

My fear here is that it was up the line. My fear is that it was at very senior levels. We have been told that it was at very senior levels yet no decision was made until somebody else came in when somebody left. Then someone else sits here and deals with the consequences. What we see in here all too often is somebody new like Ms Considine having to answer questions about something that happened prior to her tenure. She is having to answer the questions but all those flags were there along the way. There was a significant failure somewhere. I am not saying it was with the Department of Transport but something definitely happened. Money was being spent and wasted and the flags were there, but everyone was tipping along. Then they were out the door and we are left dealing with a mess here. All too often we have seen the same trend.

Mr. Tomás Campbell:

What really changed in the last few months was that Indra delivered the software for CP1 in April. That was the point at which the impairment decision was made and decisions were made about the future of the project and getting onto a sustainable footing going forward.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am going to ask about the timeline. Mr. Campbell has just spoken about April. When did Ms Considine say she came in? Was it nine months ago?

Ms Mary Considine:

I took over in October.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

When was her first board meeting?

Ms Mary Considine:

At the end of October.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

She knew on 1 October. We are talking about April. Even if she was not told at her first one, I am sure it was not the first time it was raised at board level. For the Department of public expenditure to say the first indication it had was in April is significant in itself.

Mr. Tomás Campbell:

Just to clarify for the Deputy, I am from the Department of Transport.

Photo of Joe NevilleJoe Neville (Kildare North, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Well, the Department of Transport or the Department of public expenditure.

Mr. Tomás Campbell:

We knew we had serious concerns about the programme for the past four years. We had a number of deep dives on the project as well. We were concerned about the management of the project itself. We were assured by NTA and Iarnród Éireann management but also we were concerned about the wider portfolio of rail projects and what mitigants were in place. For the Waterford North Quays, Galway Ceannt and Foynes line projects, mitigants were in place. I have mentioned the infrastructure management of the annual contract, which is a mitigant for the greater Dublin area. We have a concern about Cork as well. Ms Considine has mentioned that we are working that through to ensure we can bring Cork online. We have been aware of the issues with this project all along and we have had a number of deep dive discussions on it. We have been escalating that to the Minister and to senior management in the Department as well.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I thank all the witnesses for staying for so long with us to take some supplementary questions. The more I hear, the more I realise the €50 million figure is going to grow significantly. It is not €50 million but a lot more due to the flawed decision to proceed with this project and sign the contract with Indra back in 2020. Just to clarify, the €50 million write-down is one thing and the report that has been commissioned by the NTA is an extra €230,000. The €3 million expenditure in the year to date is effectively part of the written-off project.

Ms Mary Considine:

It is written off, yes.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

That is in addition to the €50 million. Some of that was to Indra and some to third parties. The Chair was probing this, but on the interim works that were required to keep the traffic management system safe and up to speed - works that would not have been necessary if a project was delivered in 2024, for example - what is the amount from 2024 up to now? What was spent between 2020 and 2024 was necessary in any event but between 2024, when the new system should have been in place, and now how much has been spent keeping alive the system that is there?

Ms Mary Considine:

I do not have that figure. I imagine a lot of that work was done by our team in the signalling electrical area, as part of the infrastructure management. That would be part of their day job of supporting the existing system and keeping it going.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

But it took resources and it was necessary because the new system was not delivered in 2024. The point is that it is an aggregate cost in terms of the overall waste.

Ms Mary Considine:

To clarify in case there is any confusion, we have been keeping the system we have, which is life-expired, going. That is done by our own team and they are supporting it-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I understand.

Ms Mary Considine:

-----with their spare parts and all that and the experience they have in managing it. I think the Deputy is asking what we have spent on maintaining an old system. Separately-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

From 2024 until now. In 2024 we should have had a new system but we did not. Obviously the old system had to be kept going and that cost extra money.

Ms Mary Considine:

Yes, and I do not know how much. I do not think it would have been very significant but we will come back. I do not know that figure. We are looking at ways forward to derisk the train control.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I know. The €50 million is what is quoted repeatedly but it is much more than that, ultimately. There will be ongoing legal actions. That is confirmed.

Ms Mary Considine:

It is not confirmed but we are obviously looking at all legal considerations at the moment in relation to the contract.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

It is highly likely there will be ongoing legal actions, which is an additional cost. Going back to the original tender, what was the original contract value with Indra?

Mr. Paul Hendrick:

The target price was €16.4 million, excluding VAT.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

That was the contract value.

Mr. Paul Hendrick:

That was the build contract. There was a different price for the maintenance. If it got it built, there was an annual price to manage that system going forward, but the-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Just help me to understand that. We have a €50 million write-down but the original contract was €16 million. Just explain that to me.

Mr. Paul Hendrick:

In the write-down, the equivalent of the €16 million including VAT was circa €20 million.

Through the commercial resetting we did under resets 1 and 2, that has brought that contract up to about €30 million. We have written down about €28 million of that €30 million because it was predominantly, as we talked about earlier in response to Deputy Neville, the software and part of the hardware. The other costs between the €30 million and the €50 million are also the level of effort we expended with some of our support organisations and our own staff. We went through every single resource. Every effort was allocated to supporting Indra on the software. Once you write down the software, the other writedowns happen as a function of that. It is an indirect consequence of it. That is what brings us up to the €50 million. It is the Indra contract price.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The original contract was €16 million. The writedown was €50 million because of all those actions that had to be taken. Is that correct?

Mr. Paul Hendrick:

It is carrying writedown on other contracts, not just Indra, if that makes sense. There is the Indra contract and the writedown of that. The corollary of that is that in respect of any of the other contracts that were supporting the particular element that has failed, which is the software, we had to make an assessment based on what those individuals were doing in every given month throughout the contract period to identify whether it was linked to that or not in order to comply with our duties regarding the financial statements. That is how we got to that figure.

Ms Mary Considine:

If I may add, the €50 million includes VAT. It would be €43 million plus €7 million in VAT. The €7 million, obviously, goes back to the Exchequer. All our figures and schedules include VAT because we do not recover VAT.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

To return to my original train of thought, we are at €54 million in terms of the report commissioned, the €3 million this year, the €50 million and the interim works that had to be done on the system. We do not have a figure on that, but I presume it is adding up to a few hundred thousand. I am speculating on that. We now also have to deliver a new system. We are six years on. We have inflation, which, it could be argued, will add 30% or 40% to what the value should have been. It is potentially tens of millions in additional costs in that. The €50 million is only the baseline really.

Ms Mary Considine:

The Deputy is correct. There will be additional costs, unfortunately, but we need a train control system and-----

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I understand that.

Ms Mary Considine:

-----and we need to move forward.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I am just saying that quantifying this broad decision at €50 million is not accurate. It is much more than €50 million.

Ms Mary Considine:

Yes. The sum of €50 million is just the impairment.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

We cannot settle on a figure, but it is clearly going to be tens of millions more than €50 million.

Mr. Paul Hendrick:

On the impairment figure for the financial statement, we still carry the full cost of the project as €153 million we have spent to date and whatever we have to spend on top of that. We do not lose that number from how we report the project, but the point is well made.

Photo of Séamus McGrathSéamus McGrath (Cork South-Central, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

I will move on briefly to the NTA, if I may, in relation to a local issue. There are ongoing reliability issues with the bus service in Cork. They have been going on for years. There is deep frustration among the public regarding the cancellation of buses, ongoing unreliability, late buses and the information app not providing accurate information over the years. Endless representations have been made. We have been told that the recruitment of drivers will solve the problem, that new buses are being delivered and that investment is being made, yet we continue to have reliability issues. Is there any end to this?

Ms Anne Shaw:

There is continued investment in the bus network in Cork. There were issues with driver recruitment, but I am pleased to say Bus Éireann is now fully staffed in terms of the numbers of drivers they need for the services they are running. We had intended this year to begin the first phase of the BusConnects service redesign this year. We are still in discussions with the Department of Transport to make sure that we do that next year. We have already put those bus stops in place and they are ready for those new services. There has been some investment down there as well. We are also investing in electrification and Tivoli depot, which I mentioned in my opening statement, is due to open in the next month. That will enable the buses to go out of the current depot to be sited over there. The current depot can then be taken over in terms of putting in the required electrification and so on. It can then also receive some of those electric buses.

There are also issues with bus reliability, as the Deputy mentioned. Older buses are running at the moment. The intention of the electrification programme is to replace those buses. Bus Éireann has also recruited additional mechanics, etc., to get those back on the ground. The current depot is very constrained in terms of being able to do the mechanical repairs, fix the engines, etc. The temporary depot in Tivoli will enable more maintenance to be carried out. It will address some of the issues of buses being off the road.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I thank the witnesses for staying on. Was the NTA aware that Indra's original bid was 50% lower in pricing terms?

Mr. Hugh Creegan:

I am not sure we got the full details. We were certainly informed and gave our consent to award the contract back in 2019.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Did the NTA have sight of its abnormally low price in the investigation that took place?

Mr. Hugh Creegan:

Usually we would and we would usually be informed that the valuation has taken place, that an assessment has concluded and that a certain amount has been recommended, seeking our approval. That would usually be the case. I cannot say for certain. I have not looked back-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

In Mr. Creegan's long experience, has he seen such a big variance in price, 50%, for a contract as big as this?

Mr. Hugh Creegan:

When it comes to systems being bought and something that may be available, there can be big differences. One entity may have a product that is very close to the requirements and another entity may have to do a whole lot of work to get it. A total of 50% is large, but I have seen some up at that level.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Can the public accounts committee be furnished with details of the investigation that took place at the time - the abnormally low-bid investigation?

Mr. Hugh Creegan:

I am not aware that an abnormally low-bid investigation took place-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am sorry; Mr. Hendrick said it did.

Mr. Paul Hendrick:

I did not say that. I said we assessed the tenders just to make sure when we look at them that there is not anything in there that looks unusual. The abnormally low tenders legislation or case law came in in the last few years, but we would have always looked at it to make sure that the tender price is right and reflective of the works we need to do.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Irish Rail did not carry out a Regulation No. 69 abnormally low tender investigation.

Mr. Paul Hendrick:

I am not saying that. We do a full procurement assessment-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am asking the question. Which is it? I thought Mr. Hendrick gave evidence that Irish Rail had carried out a Regulation No. 69 abnormally low bid investigation.

Mr. Paul Hendrick:

I would have to come back to the Deputy. I was not in the business at the time. We can come back to the Deputy with the report that we would do in terms of the procurement assessment.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Every contracting authority, when an abnormally low bid comes in, under EU law and therefore Irish law, has a legal obligation to carry out an investigation. Did that happen?

Mr. Paul Hendrick:

I would have to come back to the Deputy to confirm that. I would expect that it did in terms of what we have done. All our procurements are compliant and we get audited within the business from all our procurements. Nothing has been identified as an issue in terms of how we did the procurement process-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Mr. Hendrick might examine that and come back to the committee. If an investigation was, in fact, carried out, he might provide a report. If an investigation was not carried out, he might provide an explanation as to why it was not carried out at that time. I take his point about the laws and their application. All that is relevant is how they were interpreted at that time.

Mr. Paul Hendrick:

That is fine. We can do that.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The asset value of the TMS software that is being carried or assessed on Iarnród Éireann's books is €100 million. It was €100 million when the impairment review was carried out.

Ms Mary Considine:

It is €100 million for the project. That includes the building, the enabling works, hardware and all that stuff.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I will ask the questions straight. When Indra bid to provide the TMS piece, what value did it put on the project originally? For how much did it say it could deliver TMS project originally?

Ms Mary Considine:

As my colleague Mr. Hendrick mentioned earlier on, including VAT, it was around €20 million initially.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

What did that balloon to?

Ms Mary Considine:

We wrote off €28 million from Indra and then there were third-party costs. There would also have been third-party costs in the project budget, but they have increased significantly because the whole project has been elongated.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Initially, it was going to deliver this project for €20 million. Let us fast-forward miles ahead to March 2026, when the project team presented to the board. Presumably, the project team's presentation to the board was a representation of what Indra was telling the project team. Is that fair? I am going back to the €250 million here now.

Mr. Paul Hendrick:

If I could just go back to the Deputy's question on the €20 million contract price, the commercial reset number 2 reset that to €36 million, including VAT. There was also commercial reset number 1, which reset it as well-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Round 1 was €20 million and round 2 was €36 million.

Mr. Paul Hendrick:

The assessment team would have made a determination on its own basis - not necessarily on the basis of a direct engagement with Indra but on its own knowledge of the costs and expenditure on the project at a projection-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Is Mr. Hendrick on the project team?

Mr. Paul Hendrick:

The project team is reporting to me.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Mr. Hendrick presented to the board in March 2026. Is that right?

Mr. Paul Hendrick:

It is me and the project team. The project team presents.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It is Mr. Hendrick and the project team. They went to the board.

They told the board their assessment was that the global cost would be €250 million.

Mr. Paul Hendrick:

That it could be.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It could be, in the best-case scenario, if we can continue with Indra. Is that right?

Mr. Paul Hendrick:

Yes, and that was based on years of continuing on this project.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

That was the optimistic assessment. Did Mr. Hendrick have other scenarios? Did he have a worst-case scenario?

Mr. Paul Hendrick:

No, we did not.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Mr. Hendrick went to the board with one figure, €250 million. Will he break it down and subtract the building costs from the €250 million? What is the TMS piece?

Mr. Paul Hendrick:

I cannot, at this stage, but we can come back to the Deputy on it.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Come on. Mr. Hendrick is the project team manager and he cannot tell me, out of the €250 million, how much of that relates to the software. Does he know that figure right now?

Mr. Paul Hendrick:

No, I do not. I can come back to the Deputy on it.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

What does Mr. Hendrick think it is? Come on. Mr. Hendrick presented to the board. He is being scrutinised by his board as to what this is. How can he not know?

Mr. Paul Hendrick:

We did not present a breakdown.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

That was in March and we are now in July.

Mr. Paul Hendrick:

We did not present a breakdown, so I will have to come back to the Deputy with the details.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

What is the build cost then, currently?

Mr. Paul Hendrick:

If we go to the €150 million we have spent to the end of 2025, of that €65 million is against the building asset and €85 million is against all the signalling works we did, including the TMS and the signalling enabling works. That brings us up to €150 million to the end of 2025.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

That is €150 million on the build site. Is that correct?

Mr. Paul Hendrick:

It is €150 million on signalling and on the building.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It would be €250 million if it was kept running.

Mr. Paul Hendrick:

Yes, it is a projection of the €150 million continuing.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Is it 60:40, 50:50 or 80:20? Is Mr. Hendrick honestly saying that he cannot even give me a framing between build and software? They are two separate things.

Mr. Paul Hendrick:

Sorry, the build is finished, so it would be predominantly on the signalling and TMS system.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Okay, so what does that figure look like? There is €250 million and that includes the building. What is the TMS figure if it ran all the way?

Mr. Paul Hendrick:

It would be €250 million, minus the €67 million for the building.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

It is €250 million, minus €67 million. Is that what Mr. Hendrick said?

Mr. Paul Hendrick:

Correct, including VAT.

Ms Mary Considine:

To clarify, there are also works done on signalling, SET and all that kind of stuff, which all has value. There is still €19 million of value in the signalling.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Roughly speaking, we are talking about €180 million if Iarnród Éireann kept going with Indra on the TMS software, based on what I have just been told.

Mr. Paul Hendrick:

For all of the signalling systems, excluding the building but including Indra, yes.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

We would be talking about €180 million to the very end, on a project that, in the original tender, the company said would be €20 million.

Mr. Paul Hendrick:

Other costs are included in there, so it is not a direct comparison.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

They are probably marginal enough, though. Will Mr. Hendrick subtract those costs for me?

Mr. Paul Hendrick:

If we could say roughly, the original budget would have had approximately the €65 million for the building, which is good, and €85 million for the rest. If we do it against the €85 million, that would be a more direct comparison in terms of the question the Deputy is asking.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

How did Iarnród Éireann start with €20 million, get to €85 million and then get to what looks to me like €140 million to €180 million, if it ran it the whole way?

Mr. Paul Hendrick:

It is based on assessment of resources working on the project from Indra-----

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

How did the project balloon to such an enormous degree, from day one to where we are now?

Mr. Paul Hendrick:

The problem with this project, all the way through, comes back to the lack of a developed product from Indra. The prolongation on the project, where it is continuing and the resources that are working on the project continue to support this delayed project, obviously get booked to the project cost. The reason this project is delayed and is delaying us continuing all comes back to the lack of a developed product from Indra. That is the source of all of the issues.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

I am over time so I ask for the indulgence of the Chair. Has a termination notice been issued to Indra?

Ms Mary Considine:

We are still in contract with Indra. As I said at the outset, we are in a sensitive legal and commercial position, so we are still in contract.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

The NTA has approved Iarnród Éireann's request to issue a termination notice. Is that correct?

Ms Mary Considine:

It has approved the decision taken by our board. We have not implemented those decisions yet.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Is there no other governance check that has to be gone through to execute on the decision of the board?

Ms Mary Considine:

Not from an approval's perspective but we need to look at the legal options.

Photo of James GeogheganJames Geoghegan (Dublin Bay South, Fine Gael)
Link to this: Individually | In context | Oireachtas source

Iarnród Éireann will not be going back to the NTA or the Department on the next steps. It is all in its world now. Is that correct?

Ms Mary Considine:

Yes, it is back to us.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I have a few concluding questions. I want to go back to the implications of this regarding the cost and the delivery of expanded services. Earlier, Ms Shaw, you said you would have to look at phasing of different schemes in the future. You said there was no impact on the Metro and DART+ projects. I ask you to elaborate. I know there is a process of re-evaluation but what people in Wicklow want to hear is that there will be no impact on the DART+ Coastal South expansion to Wicklow town. What assurances can you give people in my constituency, and others across the State, that are eagerly waiting for expansion of services?

Ms Anne Shaw:

Ultimately, we understand that to deliver the public transport system for this country, we need to make sure that we progress all of the projects we have identified in our investment plans. We need to understand what the next steps are. That is what we and Irish Rail will be concentrating on in terms of how we get to the traffic management system. Ms Considine has already explained what measures are being taken to protect the greater Dublin area. That probably answers the question about DART+ Coastal South in Wicklow.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Expansion to Wicklow is still on track for 2029. Is that correct?

Ms Anne Shaw:

The resilience project that Irish Rail will be delivering will ensure that there is no impact on the DART+ service.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

With the process that will be embarked on, when will we know what services will be impacted in terms of further expansion or the real impact it will have on users of the rail network?

Ms Anne Shaw:

There is a lot of work to be done to understand what the next steps are, working with Irish Rail on how we deliver the traffic management system for the rest of the country. We need to establish the costs and the delivery method. Once we have certainty on the delivery and the costs, we will also be looking across the wider programme.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

When can we expect to have that?

Ms Anne Shaw:

We have to work quite quickly, so over the next few months we should at least have some idea about what the implications are, at least an outline. Detail-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I ask you to revert to the committee as soon as you have that.

Ms Anne Shaw:

-----will need to come through the business cases that we will take through the usual governance processes as well.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I mentioned the signalling system in Cork and the timeline that is in place. Who has the contract for delivering that signalling system?

Mr. Paul Hendrick:

The main contractor for the signalling system in Cork is Alstom.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

In fairness, time penalties were written into the contract. It is a pity the same was not done for the contract with Indra. Would you agree?

Mr. Paul Hendrick:

There are liquidated damages in all of our contracts, including in the Indra contract.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

With the Indra contract, those were not implemented until this year. Is that correct?

Mr. Paul Hendrick:

They have not been levied so far.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Why?

Mr. Paul Hendrick:

When we did the commercial reset number two we effectively reset the programme dates against which those liquidated damages would apply. In the discussions we had with Indra and the NTA in 2025 it was agreed to only focus on CP1. In the nature of what we were doing, we focused on delivering CP1. We did not forfeit our right to those liquidated damages; we just did not levy them at that time. We had agreed that approach in principle at the time. Where we are at the moment is that there are no more payments to Indra in any case, as we sit here today.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

What was the cost quantitative breakdown for the next generation ticketing, NGT, tender?

Ms Anne Shaw:

The whole cost within the business case for NGT was in the cost range. I think it has been reported to the committee before. It ranges from €240 million to €280 million.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

How many companies put in for the tender?

Ms Anne Shaw:

There were three bidders.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Where did Indra rank?

Ms Anne Shaw:

It won the contract.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Was it cheaper, middle or-----

Ms Anne Shaw:

It was done on the same price-quality contract. I do not have the breakdown of what the percentages were.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Was Indra's the cheapest tender bid?

Ms Anne Shaw:

Between price and quality, yes, that is correct.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

How much cheaper?

Ms Anne Shaw:

I cannot answer that at this point. We can come back to the committee with the information.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Please do. Given what we know about the TMS tender, it should have set off so many different alarm bells, particularly in light of what has transpired in Spain and other jurisdictions. I ask you to come to us on that.

I would be really interested to see that.

I want to touch on the issue of electric buses. To hear that keeping the buses in storage for a lengthy time is actually saving us money and it being put forward as a justification that in some bizarre way this approach is ultimately saving us money is an insult to people's intelligence. What we see here is a continuous failure on so many different levels to plan forward. To see 98 buses, valued at €730,000 each including VAT, in storage is an absolute disgrace. As it currently stands, we have over €71 million worth of electric buses still in storage. For someone to come in and try to justify that by saying it saved us money because of inflationary measures is an insult to people's intelligence. Would you agree, Mr. Creegan?

Mr. Hugh Creegan:

We are not trying for one minute to make it out to be a good idea. It was not the plan to have buses in storage. The plan was that the buses would arrive and the chargers would be in place and we would be able to deploy them into operational use.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I get all of that.

Mr. Hugh Creegan:

We simply made the point that there was an offsetting cost, just to acknowledge that, but it was never a plan to have buses in storage.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Well the plan is to keep them in storage and it is going to cost us another €1.5 million by the time the 98 buses eventually come out onto the streets. What measures, if any, have been taken given the concerns this committee has expressed over the last number of months with regard to this information and the cost? Have any measures been taken to try to speed up the process to get these buses out onto the streets, or are we just content with the timeframe? Some of these buses, by the NTA's own information it has furnished, are not going to come into use until next year at some stage.

Mr. Hugh Creegan:

Most of them will come in this year in quarter 3 over the next few months into Dublin Bus. The Galway ones will be in quarter 4 and quarter 1 next year. Nobody is sitting back comfortable with this. Every effort is being made to try to accelerate the installation of the required charging infrastructure in the depots. People are delivering as fast as they can but we are behind.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

It is deeply unacceptable and concerning, to say the least, particularly when we are talking about such a waste of money here with Irish Rail and now we have the electric buses. I also want to touch on the park-and-ride facility in Fassaroe in my own constituency in Wicklow. Information the NTA has furnished the committee shows that €11 million has been spent. The NTA is nearly praising itself that it came in under budget. The expected budget was €12 million. It came in under budget, to use the witnesses' own words, but the fact that it is locked up and no one can actually use it speaks to that failure to plan forward to ensure the critical piece is put in place initially, which is to ensure there are buses and drivers to actually serve that facility. Does Ms Shaw see what is wrong there?

Ms Anne Shaw:

Obviously, the intention was for the opening-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I know the intention

Ms Anne Shaw:

-----of Fassaroe for this year. It was planned in our budget submissions in terms of the operational costs for that park-and-ride facility as well, but we did not receive the funding we needed to do that. We are in discussions with the Department on what the budget allocations will be for 2027. As the operational costs are on an annual basis-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Do the officials in the Department think it is justifiable that an investment to the tune of €11 million to provide critical public transport infrastructure is left locked up, costing €50,000 in additional security costs to ensure that no one can use it? Do they think that is justifiable?

Mr. Tomás Campbell:

No. It is deeply regrettable as well. As was outlined earlier to Deputy Neville, however, it does goes back to the budget settlement with the Department of public expenditure this year for the PSO and that is what funds the services.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

So, it is the underfunding that has facilitated this.

Mr. Tomás Campbell:

We had a 43% uplift in our core PSO this year and it is now at record level. That puts us on a much more sustainable footing.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

The expectation from the NTA was for funding levels to ensure facilities like this would become available.

Mr. Tomás Campbell:

Every Government agency will ask for a budget and it will not get the entirety of the budget in a given year and that does lead to mismatches in terms of when the services will be there, but that would be-----

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

On the Fassaroe facility, some critical elements of that infrastructure have not been delivered. There were to be EV charging points and a substation on site there. I believe that was also to serve the plan, which ultimately has been put on the shelf as well, for the Ashford-Rathnew park-and-ride facilities. Will the NTA give the cost for the substation and explain why that is not included in the cost analysis it provided the committee, and will it give us the contract that it says will, ultimately, be given to a third party to provide the EV charging services?

Mr. Hugh Creegan:

I thought we had this substation cost included. However, on the chargers, we recognised as we started to go through this and based upon conversations with market providers that just us installing them blindly and not having a payment system for them was the incorrect way. What we are going to do is tender for a provider to provide the charging infrastructure at various bays in the parking location. Members will have seen from the note that we have the ducting and the prerequisite engineering put in place for it. Once we get a supplier identified, we can follow through with the chargers then.

Regarding the Ashford-Rathnew park-and-ride site, the planning consent is agreed, as the committee will know, through the local authority. That is down to the funding. We are in a position to start construction next year but it is questionable whether the funding will be there to do it. It is a question of funding for that particular park-and-ride site.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

It is questionable as to whether Ashford-Rathnew will even commence next year.

Mr. Hugh Creegan:

At this stage it is, yes.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Okay. You might provide a note on that. There have been a lot of announcements, in my own constituency and in others, about rolling out new services. We look at new routes in Wicklow that went out to tender and the Glendalough to Bray service that people are still eagerly awaiting. Funding is not in place. We see over in west Wicklow promises made to enhance and increase the frequency of bus services there and these not being delivered. You might furnish a full note on what services had been planned that have not been able to be delivered this year because of the funding shortfall in the PSO.

The last issue I want to touch on relates to Irish Rail and company vehicles. How many company vehicles are currently in use in Irish Rail?

Ms Mary Considine:

I do not have the exact figure. There would be a number of fleet vehicles on the road to support a 24-7 operation around the country. I do not have the exact number.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

I have a figure here of 750.

Ms Mary Considine:

It may be correct. I am assuming it is if the Cathaoirleach has it. I would have thought around 600.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

Are they owned or leased?

Ms Mary Considine:

They are leased.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

They are all leased. The information I have, which you are not disputing, is that there are 750 leased vehicles in Irish Rail.

Ms Mary Considine:

That could be correct. We will have to clarify that. I do not have the figure.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

You might furnish a note to us there because that would be deeply concerning. There are more leased vehicles in Irish Rail than there are rail carriages, which says a lot. You might give us the full breakdown on those, including the costs and the nature and duration of the contracts. There was also a settlement for benefit-in-kind. You might give us some additional information in relation to that, the usage of some of those vehicles. Do you have some of that information to hand?

Ms Mary Considine:

Yes. I do not have the exact figures but there was an exercise we conducted earlier on this year - a self-review - to make sure there was no BIK owing in respect of the last number of years. A thorough review was done, an assessment was made and a settlement with the Revenue based on that figure.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

How much was that settlement?

Ms Mary Considine:

I think it was around €1 million, but I will confirm that.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

It was €1 million. You might furnish the full detail.

Ms Mary Considine:

I will. I just do not have the figures to hand.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

How many vehicles, how many individuals that related to, etc., so if you could give us the full information on that.

Ms Mary Considine:

Yes.

Photo of John BradyJohn Brady (Wicklow, Sinn Fein)
Link to this: Individually | In context | Oireachtas source

That concludes our engagement today. I thank the chief executive officers and the officials from the NTA and Iarnród Éireann for attending. I also thank the representatives from the Department of Transport the Office of the Comptroller and Auditor General for their attendance once again.

Is it agreed that the clerk will seek any follow-up information required and carry out any agreed actions arising from the meeting? Agreed.

This is the final meeting of the committee until after the summer recess. We will next meet on Thursday, 17 September 2026, to discuss the business of the committee. The committee now stands adjourned. Go raibh míle maith agaibh.

The witnesses withdrew.

The committee adjourned at 2.50 p.m. until 9.30 a.m. on Thursday, 17 September 2026.