Written answers

Thursday, 25 April 2024

Department of Housing, Planning, and Local Government

Regeneration Projects

Photo of Peadar TóibínPeadar Tóibín (Meath West, Aontú)
Link to this: Individually | In context | Oireachtas source

215. To ask the Minister for Housing, Planning, and Local Government the status of the regeneration projects for flat complexes within Dublin City Council's jurisdiction, in tabular form; the current stage of progress for these projects, including the movement of tenants out of their accommodation; to indicate any delays encountered; and if he will make a statement on the matter. [18528/24]

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

The National Regeneration Programme ensures the most disadvantaged communities are placed at the centre of all considerations surrounding physical, social and economic regeneration. My Department fully supports a wide ambit of regeneration projects which ensures that complexes with historic disadvantages are placed at the forefront of regeneration.

My Department currently funds multi-year programmes of large-scale regeneration projects in?Dublin and has a long-standing history of supporting?communities through a holistic programme of physical, social and economic regeneration.With the support of my Department and under the care of local authorities, such regeneration projects target the country’s most disadvantaged communities, including those defined by the most extreme social exclusion, unemployment and anti-social behaviour.

A large number of these flat complexes will be effectively rebuilt while others will be refurbished and in some cases will need amalgamations (i.e. two in one) due to unacceptable sizes of some homes.

My Department have provided various levels of approval for the below flat complexes:

Project Current stage of progress Date of Funding Approval
Dolphin House Phase 1 Complete 17/09/2013
Dominick Street Lower (East) Complete 25/06/2016
Dolphin House Phase 1b LA: Procurement of Integrated Design Team and development outline design 16/10/2019
Dorset St / St Mary’s Place Tender Approved 24/04/2020
Constitution Hill LA Procurement of Integrated Design Team and development outline design 05/06/2020
Emmet Road Mixed Tenure Project LA Procurement of Integrated Design Team and development outline design 23/06/2020
Matt Talbot Court LA Procurement of Integrated Design Team and development outline design 28/07/2020
St. Andrews Court LA advancing Statutory Approvals including Part 8, DAC and Fire Safety 18/12/2020
Cromcastle Court & Old Coalyard site LA Procurement of Integrated Design Team and development outline design 10/03/2021
Pearse House LA advancing design for Statutory Approvals including Part 8, DAC and Fire Safety 30/04/2021
O’Devaney Gardens Mixed Tenure On-site 02/06/2021
School Street / Thomas Court Bawn LA advancing design for Statutory Approvals including Part 8, DAC and Fire Safety 04/08/2021
Oliver Bond House Complex LA advancing design for Statutory Approvals including Part 8, DAC and Fire Safety 16/03/2022
Glover Court LA advancing design for Statutory Approvals including Part 8, DAC and Fire Safety 14/06/2022
St. Teresas Gardens / Donore Project LA Procurement of Integrated Design Team and development outline design 07/11/2022
Dominick Street Lower (West) LA advancing design for Statutory Approvals including Part 8, DAC and Fire Safety 17/01/2024
Dolphin House Phase 2 and 3 Mixed Tenure No funding proposal recieved to date N/A

The de-tenanting process is a matter for the local authority.

Delays encountered by the local authority in advancing these projects are a matter for the local authority

My Department looks forward to working with DCC on these important projects.