Written answers

Wednesday, 20 March 2024

Department of Housing, Planning, and Local Government

Housing Provision

Photo of Cian O'CallaghanCian O'Callaghan (Dublin Bay North, Social Democrats)
Link to this: Individually | In context | Oireachtas source

704. To ask the Minister for Housing, Planning, and Local Government the time spent to carry out the four-stage approval process for publicly funded capital projects for each social housing, cost rental, affordable purchase, and mixed tenure development completed in 2022, broken down by tenure type and county, in tabular form; and if he will make a statement on the matter. [13125/24]

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail)
Link to this: Individually | In context | Oireachtas source

Construction of new build social housing units on local authority lands follows the Capital Works Management Framework (CWMF) which includes four pre-construction stages, as follows -

  • Stage 1 – Capital Appraisal
  • Stage 2 – Procurement of Integrated Design Team and development outline design
  • Stage 3 – Statutory Approvals including Part 8, DAC and Fire Safety, detailed design/tender documentation preparation
  • Stage 4 – Tender and Contract Award
As local authorities develop each stage, they are required to provide an updated cost plan and supporting documentation so that the Department, as the funding authority, can review and confirm funding approval. These reviews are required to ensure projects achieve value for money.

An overall target programme of 59 weeks from submission of a valid Stage 1 Capital Appraisal to the award of the construction contract, was agreed with the CCMA Housing Committee and is set out in Housing Circular 2/2018. This target of 59 weeks is the expected timeline for projects of a straightforward nature. The range of local authority social housing projects includes many that are large and complex and require additional time for detailed design and statutory approvals. The 59-week target programme is broken down as follows:

-
Responsible
Target Weeks
Stage 1 – Capital Appraisal Approval, allowing LA to develop proposal
DHLGH
4
Stage 2 – Procurement of Integrated Design Team, develop outline design
Local Authority
12
Stage 2 – Approval-in-Principle
DHLGH
4
Stage 3 – Statutory Approvals include Part 8, DAC and Fire Safety, detailed design/tender documentation preparation; Public consultation can form part of this phase.
Local Authority
18
Stage 3 – Pre-tender Approval
DHLGH
4
Stage 4 – Undertake Tender
Local Authority
10
Stage 4 – Approval to Proceed (including approved budget)
DHLGH
3
Contract Award
Local Authority
4


Accordingly, the target times for both the Department and the local authorities to prepare design, achieve statutory approvals, develop tender documentation, carry out tendering, award contracts and to assess and confirm funding approval for these stages, is as follows -
Target weeks for LA Pre-construction Processes 44 weeks
Target weeks for DHLGH assessments/ approvals 15 weeks


Local authorities have options that allow them to deviate from using the above 4-stage process to achieve funding approval for social housing construction projects, depending on the size and the chosen procurement strategy for individual projects. For example, with projects below €8m and 25 homes or less, local authorities can avail of a single stage approval which takes approx. 4 weeks with the Department. In such instances, local authorities will still need to develop the design, achieve statutory approvals and run a tender programme.

Local authorities also have the option of combining Stage 2 and Stage 3 when ‘Design and Build’ projects are advanced and there is also an option to simply notify the Department if a Stage 3 proposal has been prepared by the local authority within six months of the Stage 2 approval and when the budget is at or close to the previously approved level, thus removing the requirement for the Department to provide a Stage 3 approval.

There were 69 projects completed in 2022 that used the CWMF 4-Stage Pre-construction Programme which were funded in 2021 and 2022. The times taken for these projects within the overall programme, both by DHLGH and by the local authorities, were as follows:
-
No. of Projects Approved within 15 weeks
Average Approval time by DHLGH
DHLGH Approvals
16
22
-
SHIP 4-stage (including Design & Build) Projects Completed in 2022
Average in Weeks
DHLGH time
Average Department Approvals
22
LA time
Average LA Preconstruction processes
104
DHLGH time
Stage 1 – Capital Appraisal Approval to develop proposal
6
LA time
Stage 2 – Procurement of Integrated Design Team, develop outline design, prepare Part 8 documentation
34
DHLGH time
Stage 2 – Approval-in-Principle
6
LA time
Stage 3 – Statutory Approvals including Part 8, DAC and Fire Safety, detailed design/tender documentation preparation; Public consultation can form part of this phase
41
DHLGH time
Stage 3 – Pre-tender Approval
6
LA time
Stage 4 – Tender
20
DHLGH time
Stage 4 – Approval to Proceed (including approved budget)
4
LA time
Contract Award
8
Local Authority
Total weeks to Contract Award
Total for Dept. Approvals in weeks
Total for LA Preconstruction process in weeks
All
127
21
106
Carlow
24
10
15
Cavan
157
33
124
Clare
103
22
81
Cork City
No CWMF 4-stage Project Delivered in 2022
Cork County
136
21
115
DLR
No CWMF 4-stage Project Delivered in 2022
Donegal
217
22
195
Dublin City
140
16
123
Fingal
88
16
72
Galway City
No CWMF 4-stage Project Delivered in 2022
Galway Co
122
28
95
Kerry
97
18
78
Kildare
No CWMF 4-stage Project Delivered in 2022
Kilkenny
No CWMF 4-stage Project Delivered in 2022
Laois
215
30
185
Leitrim
114
23
91
Limerick
153
33
120
Longford
No CWMF 4-stage Project Delivered in 2022
Louth
No CWMF 4-stage Project Delivered in 2022
Mayo
95
16
79
Meath
190
10
178
Monaghan
95
15
79
Offaly
124
14
111
Roscommon
No CWMF 4-stage Project Delivered in 2022
Sligo
72
21
51
South Dublin
115
22
93
Tipperary
153
32
121
Waterford
113
24
89
Westmeath
181
17
163
Wexford
128
18
110
Wicklow
88
17
71

Comments

No comments

Log in or join to post a public comment.