Oireachtas Joint and Select Committees

Thursday, 11 April 2024

Select Committee on Housing, Planning and Local Government

Planning and Development Bill 2023: Committee Stage (Resumed)

Photo of Darragh O'BrienDarragh O'Brien (Dublin Fingal, Fianna Fail) | Oireachtas source

But the permission has been refused. If a developer has completed the first four phases within the time period, and they are fine, that is covered under section 166. If the developer has not commenced or completed another piece then an application must be sought for that. If the planning authority refuses it, the developer cannot do anything with it. The developer cannot work if there is no permission.