Wednesday, 31 January 2024

Select Committee on Finance, Public Expenditure and Reform, and Taoiseach

Estimates for Public Services 2024
Vote 13 - Office of Public Works (Revised)

Photo of Patrick O'DonovanPatrick O'Donovan (Limerick County, Fine Gael) | Oireachtas source

A total of 62 were built there. The other completed projects are: Doorly Park in Sligo, a Sligo County Council site, with 22 units; 28 units in Claremorris, County Mayo, completed last August; 42 units in Rathdowney, County Laois, which is an LDA site; and 64 units in Clonminch, County Offaly. We are now into the second phase of delivery. These projects include Charleville, County Cork, which is under construction; Ballinasloe, County Galway, where 64 units are due to go to construction shortly; and Backweston, which is near Deputy Durkan's area but located in County Dublin, where 132 units are almost completed. Between phases 1 and 2, there are 448 units.